PIP-II Injector Test Warm Front End: Commissioning Update Lionel - - PowerPoint PPT Presentation

pip ii injector test warm front end
SMART_READER_LITE
LIVE PREVIEW

PIP-II Injector Test Warm Front End: Commissioning Update Lionel - - PowerPoint PPT Presentation

FERMILAB-SLIDES-18-100-AD PIP-II Injector Test Warm Front End: Commissioning Update Lionel Prost In partnership with: India/DAE 9 th International Particle Accelerator Italy/INFN Conference UK/STFC France/CEA/Irfu, CNRS/IN2P3 April 29


slide-1
SLIDE 1

In partnership with: India/DAE Italy/INFN UK/STFC France/CEA/Irfu, CNRS/IN2P3

Lionel Prost 9th International Particle Accelerator Conference April 29 – May 4, 2018 Vancouver, BC, Canada

PIP-II Injector Test Warm Front End: Commissioning Update

FERMILAB-SLIDES-18-100-AD This manuscript has been authored by Fermi Research Alliance, LLC under Contract No. DE- AC02-07CH11359 with the U.S. Department of Energy, Office of Science, Office of High Energy Physics.

slide-2
SLIDE 2

Acknowledgement

  • Results summarized within would not have been possible

without the help and dedication of many (and I apologize in advance for missing some), in no particular order:

  • D. Sun, A. Chen, P. Jones, D. Franck, D. Lambert, R. Kellett, C.

Baffes, J. Batko, J. Czajkowski, T. Hamerla, T. Zuchnik, C. Briegel,

  • J. Firebaugh, S. Conlon, G. Brown, R. Hagler, A. Saewert, G.

Saewert, D. Frolov, V. Lebedev, R. Pasquinelli, A. Shemyakin, J. Steimel, B. Hanna, R. Andrews, J.-P. Carneiro, K. Carlson, B. Chase, D. Peterson, J. Edelen, J. Dye, W. Mueller, J. Einstein- Curtis, D. Sharma, S. Khole, V. Scarpine, B. Fellenz, N. Eddy, A. Warner, D. Nicklaus, M. Kucera, D. Arveson, A. Saini, E. Cullerton,

  • M. Hassan, K. Kendziora, P. Derwent, M. Coburn, M. Ibrahim,

V.L.S. Sista, C. Richard

May 3, 2018

  • L. Prost et al. | PIP-II WFE Commissioning Update (THYGBF2)

2

Designates co-authors

  • -----------------------------0

Fermilab

slide-3
SLIDE 3

Outline

  • Proton Improvement Plan II (PIP-II) & PIP-II Injector Test

(PIP2IT)

– Introduction, scope & goals for the Warm Front End (WFE)

  • PIP2IT WFE commissioning status

– Focus on Medium Energy Beam Transfer (MEBT) line

  • Plans for high-power operation

– 10+ kW

  • Conclusion

May 3, 2018

  • L. Prost et al. | PIP-II WFE Commissioning Update (THYGBF2)

3

  • -----------------------------0

Fermilab

slide-4
SLIDE 4

Proton Improvement Plan-II (PIP-II)

  • Upgrades to Fermilab’s accelerator complex

– Central part: 800 MeV, 2 mA (average over ~ms) CW-compatible H- Superconducting Linac and transfer line to Booster

  • Present ‘warm’ Linac: 400 MeV, 30 mA, 40 ms×15 Hz

– MW-class accelerator with multi-user operation capability

  • Platform for future upgrades

– Higher Main Injector power, multiple experiments simultaneously

May 3, 2018

  • L. Prost et al. | PIP-II WFE Commissioning Update (THYGBF2)

4

Layout of PIP-II and its possible future upgrades

  • S. Nagaitsev’s

talk (MOYGB3)

PIP2 linac and transfer line Booster Linac Muon rings

0Fermilab

1

I I I I I I I I I I I
slide-5
SLIDE 5

PIP-II Injector Test (PIP2IT)

  • A test accelerator representing the PIP-II front end

May 3, 2018

  • L. Prost et al. | PIP-II WFE Commissioning Update (THYGBF2)

5

PIP-II Linac scheme

~160 m

30 keV RFQ MEBT HWR SSR1 HEBT 2.1 MeV 10 MeV 25 MeV LEBT Warm front end

LEBT = Low Energy Beam Transport; RFQ= Radio Frequency Quadrupole; MEBT= Medium Energy Beam Transport; HWR = Half-Wave Resonator; SSR1=Single Spoke Resonator; HEBT = High Energy Beam Transport

PIP2IT scheme

  • -----------------------------0

Fermilab

  • - ....

_

___. <. l•i:i••;Ji•l•~tiii~

ii , •

Ji=Cl.22 Ji=0.64 Ji=0.97

..... _

  • +<--- RT ---31>-+-------- SC --------

1111

  • 1111
  • 1111

162.5 MHz 0.03 -10.3 MeV 325 MHz 10.3-185 MeV 650 MHz 185-800 MeV

slide-6
SLIDE 6

Warm Front End scope

  • The Warm Front End (WFE) prepares a H- beam optimized

for injection into the Booster and provides capabilities for future CW operation

  • It is composed of:

– Two Ion Sources (IS) and a Low Energy Beam Transport (LEBT)

  • DC/long pulse operation

– RFQ

  • CW operation (RF)
  • 30 keV

2.1 MeV

May 3, 2018

  • L. Prost et al. | PIP-II WFE Commissioning Update (THYGBF2)

6

– Medium Energy Beam Transport (MEBT)

  • Nominal output current: 2 mA

averaged over ~ms (from ms to CW

  • peration)
  • Bunch-by-bunch chopping

capability

Ion sources LEBT RFQ MEBT

  • -----------------------------0

Fermilab

slide-7
SLIDE 7

PIP2IT WFE main goals

  • Address all critical issues:

– LEBT with low emittance growth compatible with chopping

  • Vacuum management in the LEBT/RFQ region

– Reliable CW RFQ, including couplers – Bunch-by-bunch selection in MEBT

  • Bunch extinction, effective

emittance growth

– Compatibility of high-power deposition in MEBT absorber with SRF downstream

  • Absorber reliability &

lifetime

May 3, 2018

  • L. Prost et al. | PIP-II WFE Commissioning Update (THYGBF2)

7

Warm front end of PIP2IT with HWR installed

Reported previously

/

I

I I I I I

:

.

' --------------------------------

....

  • \

I I I I I I I

I

0Fermilab

slide-8
SLIDE 8

LEBT and RFQ performance highlights

  • LEBT delivers up to 10 mA, 10ms-dc, 20 Hz

– en,rms = 0.13 mm mrad (for 5 mA)

  • RFQ operated pulsed (up to 5 ms) or CW, 162.5 MHz, 60 kV

– Time of Flight measurements → 2.11±0.006 MeV – 98±2% transmission efficiency at 5 mA (pulsed beam)

  • Up to 10 mA with low losses

– en,rms < 0.2 mm mrad (for < 5 mA, nominal)

May 3, 2018

  • L. Prost et al. | PIP-II WFE Commissioning Update (THYGBF2)

8

MEBT configuration for characterization of the RFQ

<

Dipol Bun hing

Emittan

slide-9
SLIDE 9

PIP2IT beam line configuration

  • Full length MEBT has been installed at the CryoModule Test

Facility (CMTF) followed by a high-power dump

May 3, 2018

  • L. Prost et al. | PIP-II WFE Commissioning Update (THYGBF2)

9

– Includes two different prototype kickers (50-Ohm & 200-Ohm), all scraper paddles, prototype absorber, Differential Pumping Insert (DPI) and various diagnostics

Absorber prototype 50-Ohm kicker prototype 200-Ohm kicker prototype DPI F-scraper Fast acting valve ACCT Emittance scanner Fast Faraday Cup RWCM

Dump

Ion Source & RFQ

DPI

200-Ohm kicker

  • --------------------OFermilab

/

slide-10
SLIDE 10

Beam transport

  • Demonstrated 96% availability (over 24 hours) for beam with

nominal MEBT parameters

– 5 mA×0.55 ms×2.1 MeV×20 Hz = 115 W with appropriate bunch pattern for Booster injection

  • Up to 10 mA to the dump with negligible uncontrolled losses

– Dedicated distributed scraping system removes ~2% (halo)

  • Measured beam emittances near the end of the MEBT

– 0.22/0.34 mm mrad (rms, n) Transverse/Longitudinal

May 3, 2018

  • L. Prost et al. | PIP-II WFE Commissioning Update (THYGBF2)

10

Angle, mrad Position, mm

erms,n = 0.22 mm mrad

Vertical phase- space with Allison scanner (5 mA, 10 ms pulse) Bunch length vs. bunching cavity #2 voltage (5 mA, 10 ms pulse) and ‘fit’ with Tracewin

4

50-----------------------------~

~400 (.) lL lL

:.

j350

.c

"'

300 a: + FFC Data
  • Tracewin («,=O, P
,=1.2 mm/mrad, c,=0.34 mm-mrad)

I

2~ ---=

35

':---4

""'
  • -""'

4

"=5---=

50

=---s,f,.s,---- ---==------,

1

cf:
  • ---=

1

=-

s ----=

so

B2 Field (kV)

0Fermilab

slide-11
SLIDE 11

Chopping system concept

  • 2 identical kickers in sync and a beam absorber

– Two broadband travelling-wave kickers separate bunches by 6s – Absorber is rated for 21 kW (i.e. full max. beam power)

  • Beam comes at 29 mrad to decrease power density to <17 W/mm2

May 3, 2018

  • L. Prost et al. | PIP-II WFE Commissioning Update (THYGBF2)

11

3σ envelopes of the transmitted (a) and chopped-out (b) bunches simulated with TraceWin.

20 15

to

E5

5 0 +-iff-+ttllt--

ttt-

...JW

>- -5

  • 10
  • 15

0Fermilab

  • 20 --+-..u.J--...................
  • 1---.........
  • '---r-...L.J/-.W.,--..-'L....ljl.-'--,-..........
W......--'/-W.,..II...J..,~i---........... ,,_..__~.;u.swc.--..-'L-IJ/L-----.........

~~~.....,

15

10

~5

E

5 0

>- ·5

  • 10

10

12

14

iii ii~ If I iii Dlf

  • 15 __

......................

  • -....._.,......

.......

..,.....

__

.................................... 2

4

6 8

10

12

Position (m)

14

slide-12
SLIDE 12

Kickers development

  • Two versions developed in parallel  1 of each prototype

installed at PIP2IT

May 3, 2018

  • L. Prost et al. | PIP-II WFE Commissioning Update (THYGBF2)

12

“50-Ohm”

➢ 24 electrodes per plate connected in vacuum by 50 Ohm cables ➢ Driver: commercially available linear amplifier ▪ Concept tested with similar lower-power amplified

  • D. Sun
  • A. Chen

“200-Ohm”

➢ Helix as a travelling-wave structure ➢ Driver developed at Fermilab ▪ Broadband, DC-coupled switches in push-pull configuration

  • A. Chen
  • G. Saewert
  • G. Saewert’s poster

(WEPML021)

0Fermilab

slide-13
SLIDE 13
  • Demonstrated arbitrary bunch structure

– Kicked bunches intercepted with a scraper → passing bunches recorded with Resistive Wall Current Monitor (RWCM)

Kickers characterization

  • Both kickers (50-Ohm and 200-Ohm) meet specs

– For DV = 500 V (nominal), angle of deflection at the end of either kicker is > 7 mrad (specs)

May 3, 2018

  • L. Prost et al. | PIP-II WFE Commissioning Update (THYGBF2)

13

2.4 ms

Kick

Top scraper partially inserted

RWCM

200-Ohm kicker DPI

  • T. Hamerla
  • F. Frolov
  • G. Saewert
  • J. Simmons
  • D. Sun
  • G. Saewert
  • A. Chen
  • B. Chase
  • V. Lebedev
0.0200 0.0175 0.0150 ~0.0125 jo.0100

J

0.0075 0.0050 , - --tf-f-t-f-+HIIIHIII 0.0025 0.0000 1 800

0Fermilab

PIP2-IT MEBT Wall Current Monitor Signal 1000
slide-14
SLIDE 14

Kickers characterization(cont’)

  • Kickers do not significantly deteriorate

the transverse emittance of the beam

  • Kickers were successfully operated

together in sync

May 3, 2018

  • L. Prost et al. | PIP-II WFE Commissioning Update (THYGBF2)

14

5 mA beam collimated to 1.5 mA and deflected by the 200-Ohm kicker

3s vertical envelope simulated with Tracewin showing both the passing and the deflected bunches in the configuration with both kickers used in sync.

50-Ohm Kicker 200-Ohm Kicker DPI F-scraper

Angle, mrad Position, mm

40 20

e

g

>-
  • 20
  • 40

2

6 Position (m) Passing Beam --

Cent r oid ••••••••·

Deflected Beam - 8 10

0Fermilab

  • 4-,
I I I 1 I I 1 I I I I I I I I
  • 90 -89 -88 -87 -86 -85 -84 -83 -82 ·81 -80 .79 -78 -77 -76 .75

Fast acting valve Emittance scanner

/

ACCT Fast Faraday Cup

slide-15
SLIDE 15

PIP2IT vs. PIP-II WFE beam parameters

May 3, 2018

  • L. Prost et al. | PIP-II WFE Commissioning Update (THYGBF2)

15

At PIP2IT, the bunch pattern for bucket-to-bucket injection into the Booster was demonstrated using only 1 kicker (2 are required to achieve nominal deflection)

* Arbitrary patterns are currently limited to 0.6 ms bursts with average switching frequency of up to 45 MHz during

the burst and 20 Hz bursts repetition rate

PIP-II Beyond PIP-II (cw) PIP2IT (concurrently) PIP2IT (max) Beam energy, MeV 2.1 2.1 2.1 2.1 Bunch frequency, MHz 162.5 162.5 162.5 162.5 Peak current (RFQ exit), mA 5 5 5 10 Macro-pulse length, ms 0.55

  • 0.55

4.8 Macro-pulse rep. rate, Hz 20

  • 20

60 Bunch pattern Booster inj. Arb. Booster inj. Arb.* Output current (averaged over ~ms), mA 2 2 2 10 Average power, kW 0.1 10 0.1 5

,-

  • ,
I ' I

'

.,

  • 0Fermilab

'

., , _______________

; I I
slide-16
SLIDE 16

Path to high-power operation

May 3, 2018

  • L. Prost et al. | PIP-II WFE Commissioning Update (THYGBF2)

16

  • RFQ consolidation

– RFQ couplers were replaced with a new design where the ceramic window is sealed with Viton O-rings (instead of brazing)

  • Identified solutions for the

high-power absorber

  • Machine Protection System (MPS)

– Protection against unexpected and sudden beam loss is critical for going to higher beam power/duty factor

  • Compare current measurements along the beam line

– Complications:

  • Beam is slightly scraped off on purpose
  • Beam current along the beam line varies by design
  • S. Kazakov
  • O. Pronitchev
Copper nut Rotatable flange Hole for ceramic cooling air

0Fermilab

Rotatable flange
slide-17
SLIDE 17

Absorber: Main challenges

  • Three major challenges

– Dissipate high-power beam  Shallow angle of incidence – Significant amount of beam is reflected (~20%)

  • Limit propagation downstream
  • Manage power going to the walls of the vacuum box

May 3, 2018

  • L. Prost et al. | PIP-II WFE Commissioning Update (THYGBF2)

17 Simulation of secondary particles incident on the downstream wall

  • f the absorber box for a flat

absorber surface

Downstream wall of vacuum box (beam going into the page)

Absorber

>800 W escape

Vacuum chamber aperture

  • C. Baffes
  • J. Batko
  • S. Oplt

.............. ............

  • '
  • .

,

.

...

.... .

  • ;.it..-;,

. -~ . ........

.

,. ..

I ••

  • •• •

......

  • ·

. ,

............

.

.............. -----------

0Fermilab

1)
  • I

I

6g # •

1

  • 09
OL
  • 08
06
  • m
slide-18
SLIDE 18

Absorber fabrication status

  • Baffling techniques have been used to limit transmission of

secondary particles downstream

  • Downstream wall was made with a grid pattern to localize

thermal stress and includes multiple layers

May 3, 2018

  • L. Prost et al. | PIP-II WFE Commissioning Update (THYGBF2)

18

Downstream wall of vacuum box (beam going into the page)

  • Design complete

– Procurement has started

Absorber assembly cutout model

  • ---------------------------0

Fermilab

slide-19
SLIDE 19

Summary

  • PIP-II Injector Test WFE works as an integrated system and

demonstrated key technical aspects of the PIP-II WFE design, in particular for the MEBT:

– Arbitrary bunch selection pattern – Two kickers working in sync – Beam to the dump at nominal parameters (5 mA, 0.55 ms, 20 Hz) with low losses and all aperture restrictions (kickers, DPI) – Most beam parameters within specs

  • Most components have been tested with ~1 kW beam

– Moving forward with demonstration of ~10 kW+ operation

  • Machine Protection System is key

May 3, 2018

  • L. Prost et al. | PIP-II WFE Commissioning Update (THYGBF2)

19

  • -----------------------------0

Fermilab

slide-20
SLIDE 20

Plans

  • Prepare for a ~2-year hiatus in the operation of PIP2IT with

beam

– For cryomodules installation and testing (RF)

  • Then, proceed with final round of tests of the MEBT

– Production kickers & absorber

  • Extinction measurements

– Emphasis on vacuum management and protection of SRF from failures upstream

May 3, 2018

  • L. Prost et al. | PIP-II WFE Commissioning Update (THYGBF2)

20

  • ----------------------------------- 0 Fermilab