pattern energy introduction
play

Pattern Energy Introduction Revenue Stabilization and Tax Policy - PowerPoint PPT Presentation

Pattern Energy Introduction Revenue Stabilization and Tax Policy Committee Monday, November 19, 2018 Company Overview Core Competencies Origination & Development Finance & Permitting Construction Greenfield / Acquisition


  1. Pattern Energy Introduction Revenue Stabilization and Tax Policy Committee Monday, November 19, 2018

  2. Company Overview

  3. Core Competencies Origination & Development Finance & Permitting Construction  Greenfield / Acquisition  Contract negotiation  Engineering  Meteorology and analytics  Project finance  Construction management  Community support  Permits / Real estate finalization  Project administration  Utility and supplier relationships  Insurance  Site Biological and Archeological  Transmission /  Third party verification monitoring and mitigation  Hedging  Environmental, Health and Interconnection planning  Community Relations Safety management Corporate Administration & Support 3

  4. Community & Environmental Commitments  We support the communities in our project areas – Ensure our projects succeed by ensuring the project area communities succeed – Strive to build strong relationships with landowners, local officials, and community members – Earn trust through communication and collaboration and work to structure our projects so benefits spread to the local communities  We respect the land and the environment – Consider it our responsibility to produce and transport clean, renewable energy to consumers with the least amount of natural impact – Aim to exceed industry standards and be a leader in the advancement of best practices for the identification, assessment, and mitigation of our environmental impacts 4

  5. Broadview & Grady Wind Curry County, New Mexico Deaf Smith County, Texas

  6. Industrial Revenue Bonds in Rural New Mexico  Village of Grady Taxable Industrial Revenue Bonds  Provided an opportunity to competitively develop the Broadview & Grady Projects  Allows local communities to retain and direct funds from the projects directly to community projects.  Over the 30 year term of the PILT agreements:  $9.0 Million to Curry County  $4.1 Million to Grady Schools  $5.2 Million to Texico Schools 6

  7. Overview - Broadview & Grady Wind  Outside of the IRB & PILT agreements, the two Broadview projects donated $350,000 to the local community, including a $150,000 donation to the Village of Grady, a separate $150,000 donation to the Village of Grady municipal school district, and more than $50,000 in donations to local volunteer fire organizations.  The Grady project is donating an additional $200,000 to a local 501c3  The total donation impact from all three phases of the projects will be $550,000  Overall economic impact to NM expected to be $979.8M (Including PILT)  Expected to contribute more than $30 million to the local community and school system over 25 years through PILT Payments and other benefit programs. 7

  8. Overview - Broadview & Grady Wind  During construction, provided jobs for more than 650 workers during peak activity, with an average of 350 workers on-site throughout the construction process  Now operational, the facility employs 18 full-time workers with nearly half of those positions being filled by local residents 8

  9. Corona & Mesa Canyons Wind Lincoln, Torrance, and Guadalupe Counties, New Mexico

  10. Corona Wind Projects  Approximately 2,200 MW Wind Development  290,000 Acres Privately Owned Land  34,000 Acres of State Land (Applications in Progress)  Lincoln County WECS Permit Application in Progress  Torrance County Special Use District Approved  PRC Location Control & ROW Permit in Progress  Consultation with DoD ongoing  Start of construction work completed for PTC Qualification  Start of construction scheduled for mid-2019  COD by end of 2020 10

  11. Mesa Canyons  Approximately 1,000 MW Wind Development  129,000 Acres Privately Owned Land  12,000 Acres of State Land (Application in Progress)  August 24, 2017 - Lincoln County WECS Permit  February 28, 2018 - PRC Location Control Permit  January 26, 2018 - FAA Determinations of No Hazard  Start of construction scheduled for mid-2019  COD by end of 2020 11

  12. Transmission Paths for Pattern Projects NV UT CO CA APS and PNM Grady & Broadview Transmission Systems Projects AZ Albuquerque Western NM Western Spirit Interconnect Mesa Canyons & SunZia Corona Projects 12

  13. Corona Area Wind Projects – Target Schedule  PTC Work - Complete Q4 2016  Development - Ongoing, Complete H2 2019  Private Real Estate – Ongoing, Complete Q4 2018  State Lands – Ongoing, Complete H1 2019  Local Permitting – Complete Q1 2019  PRC Locational Permit – Complete Q3 2018  Construction Financing – H2 2019  Commercial Operation – by December 31, 2020 13

  14. Photos

  15. 15

  16. 16

  17. 17

  18. 18

  19. Progress BEKW Substation (July 18, 2016) 19

  20. 20

  21. 21

  22. 22

  23. 23

  24. 24

  25. 25

  26. Crystal Coffman Manager, Project Development Pattern Development Phone: (713) 308-4203 Email: crystal.coffman@patternenergy.com Adam Renz External Affairs & Government Relations Pattern Development Phone (713) 308-4284 Email: adam.renz@patternenergy.com

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend