P6, Acumen Fuse & Risk, and Synchro – Putting it all Together

  • n a Major Infrastructure

Program

Presented by: Project Controls Cubed (PC3)

1

slide-2
SLIDE 2

Overview

2

slide-3
SLIDE 3

Project Controls Cubed (PC3)

  • Small company – it doesn’t require a big company
  • Based in Manhattan Beach, CA
  • Three Principles
  • Serelle Corn
  • Jeff Campbell
  • Bob Campbell
  • Everything we will show you here we have done in the last year. Not theory.

3

slide-4
SLIDE 4

P6 is the Data Engine It’s all in the Cloud…

4

slide-5
SLIDE 5

Building the Master Program Schedule

  • Standard Phases
  • Standard Milestones
  • Standard Gates

5

slide-6
SLIDE 6

Building the Master Program Schedule

  • EPS/WBS
  • Cost Loading Req.
  • Planning Schedule
  • Establish Schedule

Acceptance Stds per Specs

  • BIM Object Naming
  • Revit Federated Model
  • Synchro Server
  • Accurate Actual Cost Reporting
  • Design/Construction Schedules Linked

into Master Schedule

  • Review Design Schedules
  • Risk Analysis on Design &

Construction Schedules

  • Build 5D Program Wide

Construction Schedule

  • Turn Over As‐Built

5D Model to Owner

  • Archive 5D Model

for Future Projects with Similar Scope Provide Construction Schedule PDF

  • Accurate Actual Cost

Reporting

  • Construction Schedule

Assimilation into Master

  • Build Program‐

Wide Commission‐ ing/Training Schedule

  • Archive Program

Schedule for Future Projects with Similar Scope

  • Build/Update 5D

Schedule from Contractor Construction Schedules

  • Build 5D Program Wide

Commissioning Schedule

  • Review Contractor

Construction Schedules

  • Risk Analysis on

Commissioning Schedule

  • Provide 4D/5D Model

to Bidders

  • Or Show Animation

at the Kick‐off

6

slide-7
SLIDE 7

Linking Consultant Schedules into the Master Schedule

PROGRAM MGMT Schedule DESIGN Consultant Schedules

ENVIRONMENTAL Consultant Schedule

CONSTRUCTION Contractor Schedules

7

slide-8
SLIDE 8

Managing the Master Program Schedule

  • P6 is the data engine that drives the program
  • Use P6 Reflections so the Master Schedule can function as

both a PLANNING tool and a CONTROL tool

  • Substitute approved consultant schedules and link them in

the Master Schedule using activity codes

  • Define reports using layouts

8

slide-9
SLIDE 9

Using Reflections During Planning

  • Used to Control Project

Schedule Integrity

  • Create Budgets
  • Record Actual Costs
  • Run Performance Reports
  • Used for Alternative Plans
  • Alternative Scenarios
  • Contract Packaging Options
  • Cost‐Loaded Options

Create a Reflection Schedule in P6

Keys to Success:

  • Understand the Merge

Reflection Report

  • Reflections do not delete
  • Delete the old to prepare

for the new

9

slide-10
SLIDE 10

Useful Reports During Planning

10

slide-11
SLIDE 11

Useful Reports During Planning

11

slide-12
SLIDE 12

Important Synchro Tasks During Planning

  • Establish BIM model parameters for 4D/5D.
  • Develop Object Naming Convection.
  • Shared coordinates do not transfer to Revit DWF’s.
  • Navisworks cannot be updated.
  • Implement the work‐around, a Program wide Synchro model

works including updating.

Flashing & Sheet Metal SPC-4.3.2.45 Metal Roof Panels 375 SF $10.00 $3,750 $4.71 $1,767 $0 $25.00 $9,375 $39.71 $14,892 $0.79 $297 SPC-4.3.2.45 Gutters and Downspouts 1 LS $0 $0 $477.50 $478 $477.50 $478 $22.50 $23 SPC-4.3.2.45
  • Misc. Flashings
1 LS $0 $0 $477.50 $478 $477.50 $478 $22.50 $23 SPC-4.3.2.55 Sealants & Moisture Seals 1 LS $0 $0 $955.00 $955 $955.00 $955 $45.00 $45 DIV 8 SPC-4.3.2.55 HM Door & Frame - Pair/Custom -(2'-0"x7'-0" & 3'-0"x7'-0") 1 EA $2,000.00 $2,000 $278.80 $279 $0 $0 $2,278.80 $2,279 $89.85 $90 SPC-4.3.2.55 HM Door & Frame (3'-0"x7'-0") 1 EA $1,050.00 $1,050 $156.82 $157 $0 $0 $1,206.82 $1,207 $50.54 $51 $0 $0 $0 SPC-4.3.2.55 Alum Door & Frame - Ext. Sliding Thermal, Safety Glazing - (3'-0" 2 EA $2,500.00 $5,000 $471.21 $942 $0 $0 $2,971.21 $5,942 $79.21 $158 SPC-4.3.2.55 Windows w/ Glazing 95 SF $45.00 $4,275 $19.63 $1,865 $0 $0 $64.63 $6,140 $3.30 $314 SPC-4.3.2.55 Finish Hardware 4 EA $1,000.00 $4,000 $418.19 $1,673 $0 $0 $1,418.19 $5,673 $134.77 $539 SPC-4.3.2.55 Louvers (Door Louver 2 EA $300.00 $600 $69.70 $139 $0 $0 $369.70 $739 $22.46 $45 DIV 9 Gypsum Board SPC-4.3.2.50 Walls 870 SF $1.38 $1,201 $1.74 $1,516 $0 $0 $3.12 $2,717 $0.47 $410 SPC-4.3.2.50 Ceilings 56 SF $1.38 $77 $3.48 $195 $0 $0 $4.86 $272 $0.47 $26 Lt Ga. Metal Framing $0 SPC-4.3.2.50 6" Wall Studs 600 SF $0.94 $561 $2.09 $1,255 $0 $0 $3.03 $1,816 $0.67 $404 SPC-4.3.2.50 2.5" Furring 900 SF $0.58 $525 $6.44 $5,796 $0 $0 $7.02 $6,321 $1.12 $1,011 SPC-4.3.2.87 Ceramic Tile SPC-4.3.2.87 Ceramic Mosaic Floor Tile 56 SF $10.00 $560 $11.15 $625 $0 $0 $21.15 $1,185 $3.59 $201 SPC-4.3.2.87 Ceramic Wall Tile 130 SF $10.00 $1,300 $13.94 $1,812 $0 $0 $23.94 $3,112 $4.49 $584 SPC-4.3.2.87 Tile Backer Board 130 SF $1.00 $130 $3.48 $453 $0 $0 $4.48 $583 $1.12 $146 SPC-4.3.2.87 Acoustical Treatment SPC-4.3.2.87 Lay-in T Bar Ceiling 150 SF $2.50 $375 $2.09 $314 $0 $0 $4.59 $689 $0.67 $101 SPC-4.3.2.87 Resilient Flooring SPC-4.3.2.87 VCT Flooring 150 SF $3.00 $450 $1.18 $178 $0 $0 $4.18 $628 $0.38 $57 SPC-4.3.2.87 Resilient Base 40 LF $3.00 $120 $1.39 $56 $0 $0 $4.39 $176 $0.45 $18 Painting SPC-4.3.2.50 Gypsum Board 860 SF $1.80 $1,548 $0.68 $582 $0 $0 $2.48 $2,130 $0.06 $53 SPC-4.3.2.50 Paint exposed steel members 9,210 LBS $0.20 $1,842 $0.17 $1,558 $0 $0 $0.37 $3,400 $0.03 $286 SPC-4.3.2.50 Paint steel members/canopy 0 SF $0 $0 $0.00 $0 SPC-4.3.2.55 Doors and Frames 2 EA $80.00 $160 $112.75 $226 $0 $0 $192.75 $386 $20.71 $41 DIV 10 SPC-4.3.2.80 Toilet Accessories SPC-4.3.2.80 Paper Towel Dispenser 1 EA $180.00 $180 $20.91 $21 $0 $0 $200.91 $201 $6.74 $7 SPC-4.3.2.80 Toilet Seat Cover Dispenser 1 EA $167.00 $167 $36.94 $37 $0 $0 $203.94 $204 $11.90 $12 SPC-4.3.2.80 24"X36" Mirror 1 EA $139.00 $139 $55.76 $56 $0 $0 $194.76 $195 $17.97 $18 SPC-4.3.2.80 Toilet Paper Dispenser 1 EA $17.80 $18 $23.21 $23 $0 $0 $41.01 $41 $7.48 $7 SPC-4.3.2.80 42" Grab bar 2 EA $31.50 $63 $27.88 $56 $0 $0 $59.38 $119 $8.98 $18 SPC-4.3.2.80 Mop Rack 0 EA $90.00 $0 $27.88 $0 $0 $0 $117.88 $0 $8.98 $0 SPC-4.3.2.80 Fire Extinguisher Cabinet 2 EA $134.00 $268 $34.85 $70 $0 $0 $168.85 $338 $11.23 $22 SPC-4.3.2.80 Metal Canopies 0 SF $0 $0.17 $0 $0 $0.03 $0 SPC-4.3.2.80 Metal Lockers 2 EA $307.05 $614 $22.55 $45 $0 $0 $329.60 $659 $4.14 $8 DIV 11 SPC-4.3.2.80 Unit litchen w/ sink and undercounter ref 7 LF $400.00 $2,600 $45.10 $293 $0 $0 $445.10 $2,893 $8.29 $54 DIV 14 SPC-4.3.2.65 Fire Protection 176 SF $0 $0 $9.40 $1,654 $9.40 $1,654 $0.60 $106 DIV 22 SPC-4.3.2.65 Water closet, tank-type, 2-pc, floor-mount 1 EA $690.00 $690 $251.31 $251 $0 $0 $941.31 $941 $42.25 $42 Rough in SPC-4.3.2.65 Lavatory, 19"x17", wall-hung, vit china 1 EA $408.00 $408 $251.31 $251 $0 $0 $659.31 $659 $42.25 $42 SPC-4.3.2.65 Kitchen Sink, stainless steel, 19"x18" 1 EA $650.00 $650 $274.87 $275 $0 $0 $924.87 $925 $46.21 $46 SPC-4.3.2.65 Roughins 3 EA $650.00 $1,950 $314.14 $942 $0 $0 $964.14 $2,892 $52.81 $158 SPC-4.3.2.65 Duplex Pkgd Sewer Lift Station, 100-gal, 24 gpm 1 EA $4,500.00 $4,500 $3,141.40 $3,141 $0 $0 $7,641.40 $7,641 $528.08 $528 SPC-4.3.2.65 Duplex PS Control Panel 1 EA $2,000.00 $2,000 $314.14 $314 $0 $0 $2,314.14 $2,314 $52.81 $53 SPC-4.3.2.65 1 RP Backflow Preventer 1 EA $1,100.00 $1,100 $78.53 $79 $0 $0 $1,178.53 $1,179 $13.20 $13

Schedule BIM Model Estimate Same Naming Convention

12

slide-13
SLIDE 13

Important Synchro Tasks During Planning

  • Establish BIM model parameters for 4D/5D
  • Use
  • Consistent nomenclature
  • Shared coordinates
Flashing & Sheet Metal SPC-4.3.2.45 Metal Roof Panels 375 SF $10.00 $3,750 $4.71 $1,767 $0 $25.00 $9,375 $39.71 $14,892 $0.79 $297 SPC-4.3.2.45 Gutters and Downspouts 1 LS $0 $0 $477.50 $478 $477.50 $478 $22.50 $23 SPC-4.3.2.45
  • Misc. Flashings
1 LS $0 $0 $477.50 $478 $477.50 $478 $22.50 $23 SPC-4.3.2.55 Sealants & Moisture Seals 1 LS $0 $0 $955.00 $955 $955.00 $955 $45.00 $45 DIV 8 SPC-4.3.2.55 HM Door & Frame - Pair/Custom -(2'-0"x7'-0" & 3'-0"x7'-0") 1 EA $2,000.00 $2,000 $278.80 $279 $0 $0 $2,278.80 $2,279 $89.85 $90 SPC-4.3.2.55 HM Door & Frame (3'-0"x7'-0") 1 EA $1,050.00 $1,050 $156.82 $157 $0 $0 $1,206.82 $1,207 $50.54 $51 $0 $0 $0 SPC-4.3.2.55 Alum Door & Frame - Ext. Sliding Thermal, Safety Glazing - (3'-0" 2 EA $2,500.00 $5,000 $471.21 $942 $0 $0 $2,971.21 $5,942 $79.21 $158 SPC-4.3.2.55 Windows w/ Glazing 95 SF $45.00 $4,275 $19.63 $1,865 $0 $0 $64.63 $6,140 $3.30 $314 SPC-4.3.2.55 Finish Hardware 4 EA $1,000.00 $4,000 $418.19 $1,673 $0 $0 $1,418.19 $5,673 $134.77 $539 SPC-4.3.2.55 Louvers (Door Louver 2 EA $300.00 $600 $69.70 $139 $0 $0 $369.70 $739 $22.46 $45 DIV 9 Gypsum Board SPC-4.3.2.50 Walls 870 SF $1.38 $1,201 $1.74 $1,516 $0 $0 $3.12 $2,717 $0.47 $410 SPC-4.3.2.50 Ceilings 56 SF $1.38 $77 $3.48 $195 $0 $0 $4.86 $272 $0.47 $26 Lt Ga. Metal Framing $0 SPC-4.3.2.50 6" Wall Studs 600 SF $0.94 $561 $2.09 $1,255 $0 $0 $3.03 $1,816 $0.67 $404 SPC-4.3.2.50 2.5" Furring 900 SF $0.58 $525 $6.44 $5,796 $0 $0 $7.02 $6,321 $1.12 $1,011 SPC-4.3.2.87 Ceramic Tile SPC-4.3.2.87 Ceramic Mosaic Floor Tile 56 SF $10.00 $560 $11.15 $625 $0 $0 $21.15 $1,185 $3.59 $201 SPC-4.3.2.87 Ceramic Wall Tile 130 SF $10.00 $1,300 $13.94 $1,812 $0 $0 $23.94 $3,112 $4.49 $584 SPC-4.3.2.87 Tile Backer Board 130 SF $1.00 $130 $3.48 $453 $0 $0 $4.48 $583 $1.12 $146 SPC-4.3.2.87 Acoustical Treatment SPC-4.3.2.87 Lay-in T Bar Ceiling 150 SF $2.50 $375 $2.09 $314 $0 $0 $4.59 $689 $0.67 $101 SPC-4.3.2.87 Resilient Flooring SPC-4.3.2.87 VCT Flooring 150 SF $3.00 $450 $1.18 $178 $0 $0 $4.18 $628 $0.38 $57 SPC-4.3.2.87 Resilient Base 40 LF $3.00 $120 $1.39 $56 $0 $0 $4.39 $176 $0.45 $18 Painting SPC-4.3.2.50 Gypsum Board 860 SF $1.80 $1,548 $0.68 $582 $0 $0 $2.48 $2,130 $0.06 $53 SPC-4.3.2.50 Paint exposed steel members 9,210 LBS $0.20 $1,842 $0.17 $1,558 $0 $0 $0.37 $3,400 $0.03 $286 SPC-4.3.2.50 Paint steel members/canopy 0 SF $0 $0 $0.00 $0 SPC-4.3.2.55 Doors and Frames 2 EA $80.00 $160 $112.75 $226 $0 $0 $192.75 $386 $20.71 $41 DIV 10 SPC-4.3.2.80 Toilet Accessories SPC-4.3.2.80 Paper Towel Dispenser 1 EA $180.00 $180 $20.91 $21 $0 $0 $200.91 $201 $6.74 $7 SPC-4.3.2.80 Toilet Seat Cover Dispenser 1 EA $167.00 $167 $36.94 $37 $0 $0 $203.94 $204 $11.90 $12 SPC-4.3.2.80 24"X36" Mirror 1 EA $139.00 $139 $55.76 $56 $0 $0 $194.76 $195 $17.97 $18 SPC-4.3.2.80 Toilet Paper Dispenser 1 EA $17.80 $18 $23.21 $23 $0 $0 $41.01 $41 $7.48 $7 SPC-4.3.2.80 42" Grab bar 2 EA $31.50 $63 $27.88 $56 $0 $0 $59.38 $119 $8.98 $18 SPC-4.3.2.80 Mop Rack 0 EA $90.00 $0 $27.88 $0 $0 $0 $117.88 $0 $8.98 $0 SPC-4.3.2.80 Fire Extinguisher Cabinet 2 EA $134.00 $268 $34.85 $70 $0 $0 $168.85 $338 $11.23 $22 SPC-4.3.2.80 Metal Canopies 0 SF $0 $0.17 $0 $0 $0.03 $0 SPC-4.3.2.80 Metal Lockers 2 EA $307.05 $614 $22.55 $45 $0 $0 $329.60 $659 $4.14 $8 DIV 11 SPC-4.3.2.80 Unit litchen w/ sink and undercounter ref 7 LF $400.00 $2,600 $45.10 $293 $0 $0 $445.10 $2,893 $8.29 $54 DIV 14 SPC-4.3.2.65 Fire Protection 176 SF $0 $0 $9.40 $1,654 $9.40 $1,654 $0.60 $106 DIV 22 SPC-4.3.2.65 Water closet, tank-type, 2-pc, floor-mount 1 EA $690.00 $690 $251.31 $251 $0 $0 $941.31 $941 $42.25 $42 Rough in SPC-4.3.2.65 Lavatory, 19"x17", wall-hung, vit china 1 EA $408.00 $408 $251.31 $251 $0 $0 $659.31 $659 $42.25 $42 SPC-4.3.2.65 Kitchen Sink, stainless steel, 19"x18" 1 EA $650.00 $650 $274.87 $275 $0 $0 $924.87 $925 $46.21 $46 SPC-4.3.2.65 Roughins 3 EA $650.00 $1,950 $314.14 $942 $0 $0 $964.14 $2,892 $52.81 $158 SPC-4.3.2.65 Duplex Pkgd Sewer Lift Station, 100-gal, 24 gpm 1 EA $4,500.00 $4,500 $3,141.40 $3,141 $0 $0 $7,641.40 $7,641 $528.08 $528 SPC-4.3.2.65 Duplex PS Control Panel 1 EA $2,000.00 $2,000 $314.14 $314 $0 $0 $2,314.14 $2,314 $52.81 $53 SPC-4.3.2.65 1 RP Backflow Preventer 1 EA $1,100.00 $1,100 $78.53 $79 $0 $0 $1,178.53 $1,179 $13.20 $13

Schedule BIM Model Estimate

S a m e N o m e n c l a t u r e

13

slide-14
SLIDE 14

Scheduling Tools During Design

  • All four tools come together during Design.
  • P6 remains the schedule generator.
  • Use Acumen FUSE for Consultant Schedule

Reviews.

  • Acumen Risk analysis on higher quality schedules.
  • Weather risk analysis using Acumen Risk.
  • Use Synchro to review Designer’s Construction

Schedules.

  • Build program wide Synchro 5D model including all

equipment.

14

slide-15
SLIDE 15

Acumen FUSE for Design Schedule Reviews

15

slide-16
SLIDE 16

Adjust Schedule for Risk

  • Project Manager will normally prepare a Risk Register with Program risks

and specific Project risks

  • Many tools to help evaluate, manage the mitigate these risks
  • Best one to assist schedule and cost risk analysis is Acumen RISK
  • Allows analysis of any combination of risks
  • Quickly see the drivers that affect schedule certainty
  • Select a probability level to help set required program float (cost and schedule)
  • Will give a risk adjusted Critical Path (CP) versus standard CP

16

slide-17
SLIDE 17

Examples of Risk Analysis S3

  • Risk analysis on schedules which passed S2 requirements are high quality.
  • Acumen Risk analysis including duration and cost uncertainty on individual

activities generates realistic risk adjusted schedules which can be imported back into P6 and Synchro.

  • Provides a quantifiable basis for schedule and cost contingency.

17

slide-18
SLIDE 18

Using Synchro for Construction Schedule Reviews

  • Traditional means of reviewing construction schedules is inefficient and

relatively ineffective

  • Synchro gives more thorough and less expensive schedule reviews
  • Much easier to visualize constructability issues
  • Coordinate site logistics
  • Identify construction issues in advance and put corrections in specifications

before they become a construction change order

18

slide-19
SLIDE 19

Synchro Benefits During Design

  • Anticipate construction sequencing issues not evident from traditional

analysis

  • Assures a realistic method of construction lies behind bid document durations
  • Provides better planning of site logistics, particularly on constrained sites
  • Should reduce RFIs and Change Orders
  • Assists operational shutdown planning

19

slide-20
SLIDE 20

Example of Synchro Model Results

  • First model of a Biological Nutrient Removal Facility at PDR stage shows
  • Items missing from the schedule
  • Items constructed out of sequence
  • Areas with difficult construction sequencing
  • Federated model shows:
  • Haul routes and staging areas
  • Conflicts between projects
  • Equipment movements

20

slide-21
SLIDE 21

Weather Risk Analysis – Using FUSE and RISK

  • Example of a weather analysis we performed. Haven’t seen this done

before

  • Process
  • Create risk adjusted schedule in Acumen
  • Import back to the P6 cloud
  • Synch to Synchro
  • Baseline the risk adjusted schedule into your current Synchro schedule
  • Display a 4D model of the variance between the two schedules.
  • Revolutionizes the risk process. Assures a high integrity schedule.
  • Synchro assures entire scope is included and sequence is current.
  • Fuse assures the schedule meets specification
  • RISK allows you to visually see the risk adjusted schedule

21

slide-22
SLIDE 22

Weather Risk Analysis – Using FUSE and RISK

  • Expands the risk process. Assures a high integrity schedule.
  • Synchro assures entire scope is included and sequence is current.
  • FUSE assures the schedule meets specification
  • RISK allows you to visually see the risk adjusted schedule
  • Doing this now. Not theory.

22

slide-23
SLIDE 23

Scheduling Tools During Bid & Award

  • Option to Release Synchro model to

bidders

  • Benefit of tighter, better informed bids
  • Controversial – Spearin Doctrine – Could be

interpreted as dictating means and methods

  • Can include disclaimers
  • Showing the model at the Pre‐Bid Conference

BID & AWARD

23

slide-24
SLIDE 24

Scheduling Tools During Construction

  • Current Program Status ‐ Starting Construction
  • Plan to use Synchro to review Contractor’s

Schedules for content integrity

  • Use Acumen FUSE for schedule quality reviews
  • Several management issues
  • Determined that Designer should maintain BIM Model
  • We will use Synchro model for schedule reviews but not release

model to Contactors

  • We input Change Orders to keep model current

24

slide-25
SLIDE 25

Scheduling Tools During Commissioning & Closeout

  • Synchro is a good tool for visualizing

commissioning

  • Shows duration of shutdowns
  • Good visualization for training O&M
  • Records as‐builts
  • Good basis for next project

COMMISSIONING CLOSEOUT

25

slide-26
SLIDE 26

PUTTING IT ALL TOGETHER

  • Build a Master Schedule in P6 and validate it in FUSE
  • Create a RISK adjusted schedule and baseline into P6
  • Synch the proposed construction schedule into Synchro to reveal any

constructability issues and verify durations

  • Compare side‐by‐side animations of Base 5D schedule and Risk adjusted 5D

Schedule

26

slide-27
SLIDE 27

PUTTING IT ALL TOGETHER

27