Review of the Project for the Consolidation and Upgrade of the CERN Electrical Distribution System October 24-26, 2012
THE HIGH-VOLTAGE NETWORK OF CERN
TODAY
François Duval Head of the Electrical Engineering Group EN Department CERN
Outline Part 1 The High Voltage grid Sources of Energy at CERN - - PowerPoint PPT Presentation
THE HIGH-VOLTAGE NETWORK OF CERN TODAY Franois Duval Head of the Electrical Engineering Group EN Department CERN Review of the Project for the Consolidation and Upgrade of the CERN Electrical Distribution System October 24-26, 2012
Review of the Project for the Consolidation and Upgrade of the CERN Electrical Distribution System October 24-26, 2012
François Duval Head of the Electrical Engineering Group EN Department CERN
The High Voltage grid Sources of Energy at CERN Normal operation Degraded Operating Modes Critical Points Present Power Consumption Estimates at the HL-LHC Horizon Methodology Power Requirements
October 24th, 2012 Review of the Project for the Consolidation and Upgrade of the CERN Electrical Distribution System François Duval - 2
The Status of the CERN Distribution Network Present Consumption and Future Estimates
October 24th, 2012 Review of the Project for the Consolidation and Upgrade of the CERN Electrical Distribution System François Duval - 3
October 24th, 2012 Review of the Project for the Consolidation and Upgrade of the CERN Electrical Distribution System François Duval - 4
October 24th, 2012 Review of the Project for the Consolidation and Upgrade of the CERN Electrical Distribution System François Duval - 5
October 24th, 2012 Review of the Project for the Consolidation and Upgrade of the CERN Electrical Distribution System François Duval - 6
Meyrin & the PS 1950 - 1960’s Prévessin & the SPS 1970’s LHC 1980’s - 2000
October 24th, 2012 Review of the Project for the Consolidation and Upgrade of the CERN Electrical Distribution System François Duval - 7
Main source EDF > 300 MW Alternative source SIG/ALPIQ ≤ 60 MW
October 24th, 2012 Review of the Project for the Consolidation and Upgrade of the CERN Electrical Distribution System François Duval - 8
400 kV From the French grid through an interconnection substation “Bois- Tollot” located 300 m from CERN 400 kV. An OHL is connected to the busbar (no incomer). From this busbar, 5 CBs feed 5 power transformers (3 400/18 kV and 2 400/66 kV) 66 kV Feeds 5 LHC Points & the Prevessin Distribution Substation (BE9) from a double busbar substation with no redundancy. 20 kV Safety feeders from public distribution at LHC points 18 kV Various 18 kV distribution system (loops, antenna distribution with redundancy, direct feeders to big loads) 6.3 kV Local system from Diesel generators 3.3 kV Local 3.3 kV system for big motors (compressors) and Diesel generators
October 24th, 2012 Review of the Project for the Consolidation and Upgrade of the CERN Electrical Distribution System François Duval - 9
EDF/RTE
400MVA
SIG/Alpiq
60MVA Emergency source
The evolution
Sharing between the two sources until 1995, For cost reasons and the limited available power the relegation of
the SIG source to a back-up source to be used only in case of
October 24th, 2012 Review of the Project for the Consolidation and Upgrade of the CERN Electrical Distribution System François Duval - 10
The quality of the energy delivered at CERN is
Internal
High level of Harmonics from power converters Voltage drops from short circuits Lack of selectivity
External
Harmonics 2 from Power transformers energizing through
October 24th, 2012 Review of the Project for the Consolidation and Upgrade of the CERN Electrical Distribution System François Duval - 11
Voltage drops due to faults on the grid (mainly lightning)
This topic was specified for the LHC project (EDMS 113154 Main parameters of the LHC 400/230 V distribution system)
October 24th, 2012 Review of the Project for the Consolidation and Upgrade of the CERN Electrical Distribution System François Duval - 12
October 24th, 2012 Review of the Project for the Consolidation and Upgrade of the CERN Electrical Distribution System François Duval - 13
October 24th, 2012 Review of the Project for the Consolidation and Upgrade of the CERN Electrical Distribution System François Duval - 14
The 66 kV network of the LHC Sites and the General Services for the the LHC, the SPS and its North Experimental Area
▶
EHT4 and EHT5 110MVA 400/66 kV, identical and
▶
EHT7 70 MVA 66/18 kV feeds the General Services of the Prevessin Site, the SPS and the LHC
▶
The LHC is fed, without any redundancy, from LHC points
1 EHT102 70 MVA 66/18
kV
2, 4, 6 & 8, EHT102/103
38 MVA 66/18 kV
October 24th, 2012 Review of the Project for the Consolidation and Upgrade of the CERN Electrical Distribution System François Duval - 15
The 18 kV pulsed network
the SPS and its North Experimental Area
▶
From the BE substation which is made of 3 busbars, each one fed from a 400/18 kV 90 MVA transformer, each busbar is connected to an SVC system of 120/150 MVAR
▶
2 busbars out of 3 are necessary to
▶
The high capacitive current generated by the SVC is higher than the performance of the 18 kV CB, therefore the busbar protection is supported by the 18 kV incomers with the risk of high capacitive currents to be cut.
October 24th, 2012 Review of the Project for the Consolidation and Upgrade of the CERN Electrical Distribution System François Duval - 16
The Meyrin Site
▶
All the Meyrin site is fed from the main substation in LHC Point 1 through the MP5 link (60 MVA)
▶
There is no separation between General Services network and the facilities (accelerators, experimental areas, computer centre, etc.)
October 24th, 2012 Review of the Project for the Consolidation and Upgrade of the CERN Electrical Distribution System François Duval - 17
Autotransfert
▶
There is an automatic reconfiguration of the general services network called AUTOTRANSFERT managed by PLCs.
▶
It is based on the presence of voltage on the following busbars: BE9, ME9 and SEM12
With the present consumption (LHC at 4 TeV)
a transformer (400/66 kV or 66/18 kV) or an 18 kV site inter-site link.
In the event of such a failure, the 18 kV network
See EDMS document no. 1079852
October 24th, 2012 Review of the Project for the Consolidation and Upgrade of the CERN Electrical Distribution System François Duval - 18
Outage of
The load is taken
October 24th, 2012 Review of the Project for the Consolidation and Upgrade of the CERN Electrical Distribution System François Duval - 19
Outage of
The load is taken
October 24th, 2012 Review of the Project for the Consolidation and Upgrade of the CERN Electrical Distribution System François Duval - 20
Outage of
The load is taken
October 24th, 2012 Review of the Project for the Consolidation and Upgrade of the CERN Electrical Distribution System François Duval - 21
Outage of
No redundancy !
(only spares: one week to repair)
October 24th, 2012 Review of the Project for the Consolidation and Upgrade of the CERN Electrical Distribution System François Duval - 22
Outage of
The load is taken
October 24th, 2012 Review of the Project for the Consolidation and Upgrade of the CERN Electrical Distribution System François Duval - 23
Outage of
The load is taken
October 24th, 2012 Review of the Project for the Consolidation and Upgrade of the CERN Electrical Distribution System François Duval - 24
The network has a number of weak
operational capability, availability, maintainability, economy, reliability and safety.
There are components
the failure of which would have a long-term
have
October 24th, 2012 Review of the Project for the Consolidation and Upgrade of the CERN Electrical Distribution System François Duval - 25
The Meyrin site is fed only by one substation (ME9
SIG/Alpiq (Switzerland) through ME10 EDF (France) through LHC Point 1
Operation with a single 400/66 kV 110 MVA
The network does not allow reconfigurations to
October 24th, 2012 Review of the Project for the Consolidation and Upgrade of the CERN Electrical Distribution System François Duval - 26
The 18 kV substation (ME43) for the computer centre
The inter-site links (MP6 & MP7, today limited to 30
The mixing in some substations (BE9 and ME59) of
October 24th, 2012 Review of the Project for the Consolidation and Upgrade of the CERN Electrical Distribution System François Duval - 27
The diversity of technologies used for the switchgears
The complexity of the HV grid, The numerous possibilities for reconfiguration and The need for very rapid fault-clearing
No separation between the General Services Network
October 24th, 2012 Review of the Project for the Consolidation and Upgrade of the CERN Electrical Distribution System François Duval - 28
The yearly tests of the AUTOTRANSFERT system,
During the maintenance of the 400 kV substation,
October 24th, 2012 Review of the Project for the Consolidation and Upgrade of the CERN Electrical Distribution System François Duval - 29
The power cables of SPS are close to their end of life.
The 400 kV busbars and auxiliary connections require
October 24th, 2012 Review of the Project for the Consolidation and Upgrade of the CERN Electrical Distribution System François Duval - 30
A single OHL connects the 400 kV source to CERN The 66 kV distribution for the LHC is made of 5
The power demand of the CERN Control Centre has
October 24th, 2012 Review of the Project for the Consolidation and Upgrade of the CERN Electrical Distribution System François Duval - 31
Most of the equipment (cubicles and cables) of Meyrin,
The 400 kV substation at BE lacks protection (such as
The Diesel safety network of the SPS cannot meet
October 24th, 2012 Review of the Project for the Consolidation and Upgrade of the CERN Electrical Distribution System François Duval - 32
With the present power consumption, the failure of
October 24th, 2012 Review of the Project for the Consolidation and Upgrade of the CERN Electrical Distribution System François Duval - 33
The High Voltage grid Sources of Energy at CERN Normal operation Degraded Operating Modes Critical Points Present Power Consumption Estimates at the HL-LHC Horizon Methodology Power Requirements
October 24th, 2012 Review of the Project for the Consolidation and Upgrade of the CERN Electrical Distribution System François Duval - 34
The Status of the CERN Distribution Network Present Consumption and Future Estimates
Present power consumption was measured in July
The
A particular attention is required on the
October 24th, 2012 Review of the Project for the Consolidation and Upgrade of the CERN Electrical Distribution System François Duval - 35
Measured in July 2012
October 24th, 2012 Review of the Project for the Consolidation and Upgrade of the CERN Electrical Distribution System François Duval - 36
October 24th, 2012 Review of the Project for the Consolidation and Upgrade of the CERN Electrical Distribution System François Duval - 37
The inventory 1.
LHC operation at 7 TeV per beam HL-LHC project Upgrades of the LHC experiments Planned upgrades and consolidation of the accelerators Planned increase of the capacity of the Computer Centre.
2.
3.
CCC consolidation, New Building 107, Consolidation Building 867 and Additional needs of the various laboratories and test areas.
October 24th, 2012 Review of the Project for the Consolidation and Upgrade of the CERN Electrical Distribution System François Duval - 38
Methodology
The estimated active and reactive power figures set
The drop in consumption during long shutdowns are
Power forecasts on 400/66 et 66/18 kV transformers
October 24th, 2012 Review of the Project for the Consolidation and Upgrade of the CERN Electrical Distribution System François Duval - 39
LHC at 7 TeV
October 24th, 2012 Review of the Project for the Consolidation and Upgrade of the CERN Electrical Distribution System François Duval - 40
HL-LHC
October 24th, 2012 Review of the Project for the Consolidation and Upgrade of the CERN Electrical Distribution System François Duval - 41