Our Journey Back and Looking Ahead Mark Crawley Chief Executive - - PowerPoint PPT Presentation

our journey back and looking ahead
SMART_READER_LITE
LIVE PREVIEW

Our Journey Back and Looking Ahead Mark Crawley Chief Executive - - PowerPoint PPT Presentation

Charters Towers Regional Council Our Journey Back and Looking Ahead Mark Crawley Chief Executive Officer Charters Towers Regional Council 68,366.9 sq kms 12,491 persons (annual growth rate 0.6%) 4,235 km road network Road Network


slide-1
SLIDE 1

Our Journey Back and Looking Ahead

Mark Crawley Chief Executive Officer

Charters Towers Regional Council

slide-2
SLIDE 2

Charters Towers Regional Council

  • 68,366.9 sq kms
  • 12,491 persons (annual growth rate 0.6%)
  • 4,235 km road network
slide-3
SLIDE 3

Road Network

slide-4
SLIDE 4

History

  • Dalrymple Shire – Road Builders for many years
  • We dropped the Ball and Transport and Main

Roads reduced the amount of sole invitee works

  • We missed out on work for many years
  • This hurt
slide-5
SLIDE 5

Funding

  • Reduced funding from DTMR for contract

works

Department Main Roads Program Actuals Actuals Actuals Actuals Actuals Actuals 08/09 09/10 10/11 11/12 12/13 13/14 TIDS Subsidy Received 405,712 910,158 349,295 1,416,383 708,365 439,558 RPC Subsidy Received 6,171,500 9,611,417 7,166,757 1,873,647 2,363,567 3,688,892 RMPC Sudsidy Received 3,804,788 2,040,126 4,273,346 5,698,042 3,034,838 2,408,400 10,382,000 12,561,701 11,789,399 8,988,072 6,106,770 6,536,850

slide-6
SLIDE 6

We needed to change, do things

  • different. Not whinge.
  • We needed to fix our WH&S
  • We needed to fix our Environmental Practices
  • We needed to fix our Quality Assurance
  • In general we needed to fix all our paperwork,

processes and procedures

slide-7
SLIDE 7

So we turned a disaster into

  • pportunity
  • NDRRA – nothing like a couple of disasters to

shine some light on things

  • Opportunity to use the Day Labour Trials to

improve practices at CTRC

  • Better Quality Assurance
  • Better Work Practices
slide-8
SLIDE 8

Rainfall 2010 & 2011

slide-9
SLIDE 9

Rainfall 2012

slide-10
SLIDE 10

QRA

  • State Entity to control NDRRA works
  • Constantly developing and evolving

procedures and guidelines

  • Assessment and approvals
  • Day Labour Model
slide-11
SLIDE 11

QRA

  • Responsible for

– Approval – Compliance – Value for Money

  • Auditing

– Physical works – Compliance – Value for Money

slide-12
SLIDE 12

Benefits of using Councils for Roadworks – CTRC example

Financial

  • Don’t always have to pay for accommodation (it is a big

region) & when council does have to camp out they have existing facilities at Greenvale etc.

  • Greater efficiencies due to reduced travel times
  • Already have local agreements in place for gravel and water
  • Councils have assets available locally to undertake the works

also have their own workshop for breakdown, servicing etc.

  • Council is the major employer in the area
  • Non Tangible -
slide-13
SLIDE 13

Non-Tangible

  • Stewardship role
  • Value Add.
  • Challenge and skills development
  • Councils are the training ground for the road

construction and maintenance industry

  • Local people put back into the local

community

slide-14
SLIDE 14

Council’s share of the NDRRA Works

slide-15
SLIDE 15

NDRRA Works

  • 30 Contracts for NDRRA works completed
  • Council Road Network

– 4,235 km of sealed and unsealed roads – NDRRA worked on 294 roads covering 3,795 km (90%) of the network – Contract Duration – Average 17 weeks

slide-16
SLIDE 16

NDRRA Works

  • 530 km of Surface Formation Grading,
  • 620 km of Gravel Resheeting
  • Approximately 30% of road Network was

brought back to pre disaster standard

slide-17
SLIDE 17

Safety

  • Five Safety Incidents were reported and recorded
  • Truck hit Grid Post, No LTI (Bruslee)
  • Wheel blew up while being inflated, Squashed hand,

No LTI (Valley of Lagoons)

  • Wheel came off Water Truck, No LTI (Valley of Lagoons)
  • Dog Trailer Fell Over, No LTI (Jessie Springs)
  • Roller hit gate and post, No LTI (Herveys Range)
  • Significant achievement to have no LTI on project of

this size

slide-18
SLIDE 18

The Outcomes

  • Improved capability in the CTRC Contracting

Market

– For the Contractors – For the CTRC workforce

slide-19
SLIDE 19

Improved Contract Management

  • Contractors

– Are aware of legal requirements and responsibilities – Now have and use Project Safety Plans – Now have Traffic Management Plans and people to implement them

slide-20
SLIDE 20

Council Benefits

  • CTRC Employees are now more attuned to the

need to be competitive in relation to Road Construction

slide-21
SLIDE 21

Fleet

  • We are now “right sizing the organisation
  • And when we need gear (plant) we will hire it

like most others do

  • Not sustainable to have plant depreciating in

the yard and not being used

slide-22
SLIDE 22

Community Benefits

  • Money spent locally
  • Asset restoration
  • Public awareness of NDRRA works
  • Complementary works
slide-23
SLIDE 23

The Result

  • Leveraged new skills to attain DTMR work on

Gregory Development Road

  • Meetings with Main Roads to

– Job Estimates – $4 million plus a variation of $2 million due to changes in pavement design – Construction Period April – October 2013

slide-24
SLIDE 24

The way forward from a CTRC Perspective

  • Work together to realise funding
  • pportunities through Strong Choices
  • Partnership with DTMR to reach pre-

qualification standards

slide-25
SLIDE 25

Questions