SLIDE 1 Orange County Public Schools
Cypress Park/Durrance Elementary School 40% Construction Community Meeting February 21, 2018
Superintendent Dr. Barbara Jenkins Chief Facilities Officer John Morris
Welcome! Please sign in
http://communitymeeting.ocps.net/
SLIDE 2 Orange County Public Schools Orange County Public Schools Cypress Park/ Durrance Elementary School 40% Construction Meeting Meeting Agenda
School Board Member Linda Kobert
Meeting Organizer Lauren Roth, OCPS Communications
Architect: Song + Associates, Inc. Contractor: Charles Perry Partners, Inc.
- Questions & Answers
- Adjournment
2
SLIDE 3 Orange County Public Schools
Regional Overview - Existing Cypress Park Site
3
N
- Feeder street is 4th Street
- Access street to school is 11th Ave.
SLIDE 4 Orange County Public Schools
Existing Site
4 Existing Loop Parking: Existing Bus Drop Off on 11th Avenue: Existing Grass & Service Parking: Existing Streetside Sidewalks: 32 Cars 2 Buses 20 Cars None
Existing School Data Existing School Data
Existing Site Area – 10 acres Current School Population – Approx. 280
SLIDE 5 Orange County Public Schools
Demolition Relocate Renovation Construction Fence
N
Demolition & Playground Construction Phase 2
Existing Classroom Buildings 11+12 (16 C.R.)
Retention Existing Covered Play Area
Existing Site
5 Existing Car Loop Queuing: ± 15 Existing Parking: ± 52
SLIDE 6 Orange County Public Schools
Click to edit Master title style
2/21/2018 6
Orange County Public Schools
Construction Zone Phase 1 Retention Phase 2 Summer Renovation Phase 1 Demolition Portables Phase 2 Outdoor Play area School Year 2017-2018 Construction Fence Renovation New Building
N
Phase 2 Summer Renovation
Preliminary Phasing
Parent drop off
Phase 2
SLIDE 7 Orange County Public Schools
Click to edit Master title style
2/21/2018 7
Orange County Public Schools
Perspective view
SLIDE 8 Orange County Public Schools
Click to edit Master title style
2/21/2018 8
Orange County Public Schools
Perspective view
SLIDE 9 Orange County Public Schools Orange County Public Schools
9
Schedule
- July 18, 2017: Start Construction Building 100
- February 21, 2018: Construction 40% Complete
- May 24, 2018: Finish Construction Building 100
PHASE 1 CONSTRUCTION – BUILDING 100
SLIDE 10 Orange County Public Schools Orange County Public Schools
10
Schedule
PHASE 2 Move Out Existing Buildings Move In New Building 100 PHASE 2 Demo of Old Building 100 Renovation of Buildings 200/300 Construction of Building 400 (PE) Construction of ESE Bus Loop August 13,2018 PHASE 3 - Site Conditions and Playfields Complete May 31, 2018 August 3,2018 June 8,2018 October 15, 2018 First Day of School
PHASE 2 & 3 CONSTRUCTION
BUILDINGS 200, 300, 400 & ESE BUS LOOP
SLIDE 11
Orange County Public Schools
Aerial Photo July 2017
Site Fence and Demo
SLIDE 12
Orange County Public Schools
Aerial Photo August 2017
Building Pad and Foundations
SLIDE 13
Orange County Public Schools
Aerial Photo September 2017
Concrete Slab and Walls
SLIDE 14
Orange County Public Schools
Concrete Tilt Walls and Sitework
Aerial Photo October 2017
SLIDE 15
Orange County Public Schools
Concrete Tilt Walls
Job Photo October 2017
SLIDE 16
Orange County Public Schools
Aerial Photo November 2017
Structural Steel
SLIDE 17
Orange County Public Schools
Aerial Photo December 2017
Roofing and Windows
SLIDE 18
Orange County Public Schools
Aerial Photo January 2018
Exterior Paint and Interior Framing
SLIDE 19
Orange County Public Schools
Walls and MEP Systems
Current Construction Photos
SLIDE 20
Orange County Public Schools
Thank You!
Questions?