AEMC PAGE 1
Optional Firm Access: Access Pricing
13 November 2014 (Sydney) / 14 November 2014 (Melbourne)
AUSTRALIAN ENERGY MARKET COMMISSION
Stakeholder Workshop
Optional Firm Access: Access Pricing Stakeholder Workshop 13 - - PowerPoint PPT Presentation
Optional Firm Access: Access Pricing Stakeholder Workshop 13 November 2014 (Sydney) / 14 November 2014 (Melbourne) AUSTRALIAN ENERGY MARKET COMMISSION AEMC PAGE 1 Agenda Background to OFA and Objectives of workshop Access pricing
AEMC PAGE 1
13 November 2014 (Sydney) / 14 November 2014 (Melbourne)
AUSTRALIAN ENERGY MARKET COMMISSION
Stakeholder Workshop
AEMC PAGE 2
– Purpose – Development of model – How the model works – Results – Limitations
workshop setting
it
December
pricing model
AEMC PAGE 3
AEMC PAGE 4
Council, including: – Developing the OFA model further – Assessing the costs/benefits if the model were implemented
Energy Council in February 2015 and a final report mid-2015
OFA – it depends on where our assessment work ends up
AEMC PAGE 5
investment (including a market-led approach to transmission investment)
including changing demand and generation patterns
AEMC PAGE 6
AEMC PAGE 7
imposed on TNSPs – this tells generates how much cost their decision to locate in a particular spot creates for TNSP
generators having to negotiate with TNSPs for shared service
the life of the access
different locations
AEMC PAGE 8
contains: – It cannot completely reflect actual TNSP costs – since these are a forecast anyway – Assuming away the complexity results in more smooth and stable price outcomes – Provided it is not biased high or low it should work out evenly in the long run – But, need to have some confidence about how much it reflects TNSP costs, to know:
with access
AEMC PAGE 9
AEMC PAGE 10
and future incremental cost (NPV) of providing FAPS-compliant shared network
transmission network, considering each network element
– Reflects spare capacity on remote network elements – Discounts spare capacity on core network elements
AEMC PAGE 11
AEMC PAGE 12
Start spare capacity
AEMC PAGE 12
Forecast Flow Growth Forecast Capacity
Forecast expansion Forecast expansion
MW years
Base Year Expansion “Lump”
AEMC PAGE 13 AEMC PAGE 13 13
Baseline Flow Growth Baseline Capacity
Incremental Usage
Flow Growth plus Inc Usage
Baseline Expansion Baseline Expansion Adjusted Expansion Adjusted Expansion
Two Expansions Brought Forward
Adjusted Capacity
Requested Access Term
MW years
AEMC PAGE 14
understand: – how the LRIC method could be implemented in practice – strengths and weaknesses of using the LRIC method – potential access prices, and the extent which these are sensitive to input data and other assumptions
benefits of implementing optional firm access
comprehensive version of the model would be developed
AEMC PAGE 15
prototype
– A model of the NEM transmission network – Other input data – The program itself, which calculates LRIC prices
a length of time it wants access for, and an amount of access it wants – > an LRIC price is produced
AEMC PAGE 16
AEMC PAGE 17
Input Source Existing access AEMO’s transitional access allocation Forecast access AEMC assumptions, with generator entry based on 2013 NTNDP Short-medium term peak local demand For next 10 years: TNSP APRs Long-term peak line flow growth AEMC assumption Existing transmission network AEMO Cost of expansion Publically available data WACC 6.4 per cent real pre-tax WACC
baseline modelled network development scenario, and an adjusted modelled network development scenario which accommodates a firm access request.
are calculated via 6 simplified steps
AEMC PAGE 18
1. Calculation of forecast peak line flow
based on the physical characteristics of each of the lines, the forecast demand at each node, and the forecast firm access at each node
final year in which short term method was applied
AEMC PAGE 19
Forecast Flow Growth
MW years
Base Year
2. Prompting an expansion
the capacity of the line. Where peak line flow exceeds capacity, an expansion is prompted
AEMC PAGE 20
Start spare capacity
Forecast Flow Growth
Forecast expansion Forecast expansion
MW years
Base Year
3. The nature and size of the forecast expansion
lumpiness of an expansion
AEMC PAGE 21
Start spare capacity
Forecast Flow Growth
Forecast expansion Forecast expansion
MW years
Base Year Expansion “Lump”
4. Forecast cost of expansion
AEMC PAGE 22
5. Updating the capacity of the line based on the expansion
expansion, to reflect the expansion
flow exceeds the new, higher capacity
AEMC PAGE 23
Start spare capacity
Forecast Flow Growth Forecast Capacity
Forecast expansion Forecast expansion
MW years
Base Year Expansion “Lump”
6. Calculating the cost of each development scenario
lines which are forecast to be expanded
AEMC PAGE 24
pricing method observed. All other things equal: – nodes remote from RRN and
higher price (due to longer transmission lines) and – nodes where there is limited spare transmission capacity pay higher price (as expansions are prompted sooner)
AEMC PAGE 25
AEMC PAGE 26
400MW for 20 years
to the LRIC are marked (90% of LRIC)
largest contributor to LRIC
access between Keith and the RRN flows through Tailem Bend: 240MW directly, 160MW via South East
contributes to LRIC
(LRIC=$24M), we can see how the firm access request prompted an expansion, and hence cost:
AEMC PAGE 27
200 400 600 800 1000 1200 1400
2010 2015 2020 2025 2030 2035 2040 MW
base cap adj cap baseflow adjflow
Expansion in future (existing spare capacity not exhausted by FA request) Baseline also expands – LRIC is difference between baseline and adjusted As a 275kV line, the cost per MW of expansion is relatively low ($650/MW/km)
(LRIC=$155M), we can see how the firm access request resulted in higher cost associated with this line:
AEMC PAGE 28
200 400 600 800 1000 1200 1400
2010 2015 2020 2025 2030 2035 2040 MW
base cap adj cap baseflow adjflow
200 400 600 800 1000 1200 1400 2010 2015 2020 2025 2030 2035 2040 MW base cap adj cap baseflow adjflow Baseline not prompted to expand to the level of the adjusted expansion plan. Full cost, not just the bring forward cost of the adjusted expansions, contribute to the LRIC As a 132kV line, the cost per MW
relatively high ($3200/MW/km) Expansion prompted immediately and
spare capacity exhausted)
consider the most material of these are likely to be that: – the model includes augmentation costs but not replacement costs – the model does not accommodate non-thermal constraints (such as stability) – capacity is always provided by replicating lines along the same route; – the quality of the cost input data is limited.
discussed in more detail in appendix C of the Pricing report
AEMC PAGE 29
AEMC PAGE 30
incremental TNSP costs – prices can’t yet be used as a guide to how much generators would pay if the model was implemented
AEMC PAGE 31
in February 2015
December 2014
AEMC PAGE 32
AEMC PAGE 33