Optimising Optimising the Gas the Gas Netw Networ
- rk
Helen Fitzgerald – Wales & West Utilities
Optimising Optimising the Gas the Gas Netw Networ ork Helen - - PowerPoint PPT Presentation
Optimising Optimising the Gas the Gas Netw Networ ork Helen Fitzgerald Wales & West Utilities Contents A bit about Wales & West Utilities Project Background What are we doing? Why are we doing it? Project
Helen Fitzgerald – Wales & West Utilities
We are the Gas DSO & Designer for Wales & south west England We supply c.2,000 micro generation sites (CHPs) We have 37 power stations connected with 1.76 GW total capacity We have 1.7 TWh green gas connected to our network (19 AD sites) We flexibly deploy 58 GWh of storage each day (UK 210 TWh seasonally) We’re investing in our future low cost and green gas/H2-ready network Our network is resilient to severe weather and climate change projections
Green Gas Key Stats 19 Connected sites: 184 MWh 9 Potential sites: 74 MWh Power Generation Key Stats 35 Connected sites: 1762 MW output >60 Potential sites: >600 MW output Doing All We Can 20 pressure adjustments to WWU sites Re-negotiated CSEP pressures Combined & re-configured low and medium pressure systems
Not Enough!…Something else is needed to facilitate green gas and changing exit demands
Looking at proving new applications of existing technology through field trials to primarily facilitate additional green gas into the network:
demand in distribution networks whilst maintaining security of supply
additional demand on the distribution network
types available?
gas network to solve real green gas entry issues.
constrained/ saturated distribution networks.
Lead Gas Distribution Network Supporting Gas Distribution Network Project management, control development Data analysis Compressor design
SWINDON HONITON
IP/MP DG Honiton to Swindon MP Discreet MP Networks HP/MP PRI Connected Bio Site Not Connected Bio Site
SCADA
Supervisory Control & Data Acquisition
Controllable Site 2 Controllable Site 1
\
Green Gas Site
Key
WWU Pressure Reduction Site
Equipment
Monitoring & Control
Control Example
inject, extremity ok = controllable site pressure reduces
Extremity Site
Progress
SCADA
cases written
Training Centre ready to test, see pic
communications unit Immediate Challenges
panels/batteries required at off grid sites
Equipment
Controllable Site 1
Pressure Monitoring & Control
Control Example
pressures still increasing = compressor switches on so green gas can inject
SWINDON HONITON
IP/MP DG HP/MP PRI
Extremity Site
Controllable Site 2 Controllable Site 1
\
Green Gas Site SCADA
Supervisory Control & Data Acquisition
Immediate Next Steps
Study required to confirm suitability of chosen location
Progress
complete to select best site for the compressor…has to be in the right place for the green gas
power supply upgrade at selected sites
Now to August 2019 Testing & Installation at Sites August 2019 to July 2020 Network Trial Jan 2021 to April 2021 Interim & Final Reports
Now to September 2019 FEED Study & Design August 2019 to April 2020 Purchase, Install & Commission April 2020 to March 2021 Network Trial Jan 2021 to April 2021 Interim & Final Reports
2 Years and 6 Months ‘Flagship’ Project for WWU Control of distribution networks 132 km geographical area ‘as the crow flies’ NIA Approved Project £2.4 M 4 sites connected and 2 potential Over 679 km MP Network Enabler for green gas targets