SPP Staff Proposal
- n TO Zonal Placement
April 20, 2017
on TO Zonal Placement April 20, 2017 Outline I. Background of the - - PowerPoint PPT Presentation
SPP Staff Proposal on TO Zonal Placement April 20, 2017 Outline I. Background of the Staffs Proposal Paul Suskie II. Examples of New TO additions Carl Monroe III. SPC Motion & Updated Staff Proposal Charles Locke
April 20, 2017
Background of the Staff’s Proposal – Paul Suskie
Examples of New TO additions – Carl Monroe
SPC Motion & Updated Staff Proposal– Charles Locke
. Staff’s Recommendation to Move Forward – Paul Suskie
. Q&A – All
Next Steps – Mike Wise
2
Paul Suskie
3
4
SPP Org Group Meetings
June 2016 – RTWG October 2016 – SPC January 2017 – SPC
Individual Stakeholder Outreach by SPP Staff
December 2016 – 2 calls with KCPL & MJMEUC January 2017 – 4 calls with KCPL; MJMEUC; and Gridliance February 2017 – 8 calls with: KPP; KCPL; Gridliance; OG+E; AEP; MJMEUC; NPPD; Basin
Ad Hoc Stakeholder Meetings
March 1, 2017 – 1st Draft March 10, 2017- 2nd Draft SPC Special Meeting March 21, 2017 – Staff Proposal Additional Stakeholder Outreach by SPP Staff April 3-10, 2017 – Contacts with OG+E; AEP; MJMEUC; Gridliance; NPPD; Basin; KPP; and KCP&L
5
Transmission Owner Changes
1.
ETEC in AEP (1/1/2007)
2.
ITC Great Plains in MKEC (8/18/2009)
3.
OMPA in AEP (1/1/2010)
4.
OMPA in OGE (1/1/2010)
5.
Transcos in AEP (7/1/2010)
6.
Prairie Wind (4/1/2011)
7.
Prairie Wind (4/1/2011)
8.
Kansas Power Pool in Westar (12/20/2011)
9.
Tri-County in SPS (4/1/2012)
10.
Coffeyville in AEP (7/1/2013)
11.
Transource MO (1/1/2014)
12.
Lea County in SPS (4/1/2014)
13.
CNPPD in NPPD (1/1/2015)
14.
City of Independence in KCPL (6/1/2015)
15.
Tri-State in NPPD (1/1/2016)
16.
AECC in AEP (7/1/2016)
17.
AECC in OGE (7/1/2016)
18.
Integrated System (10/1/2015)
6
1 2 3 4 5 7 6 8
12 16 15 14 13 9 11
Transmission Owner Placed in Tariff
10 16 17
Stars do not indicate exact placement of Facilities
18
7
19a Western-UGP 19b Basin Electric Power Cooperative 19c Heartland Consumers Power District 19d Missouri River Energy Services - Total 19d (i) Missouri River Energy Services 19d(ii) Moorhead Public Service 19d(iii) Orange City Municipal Utilities 19d(iv) City of Pierre, South Dakota 19d(v) City of Sioux Center, Iowa 19d(vi) Watertown Municipal Utility Department 19d(vii) Denison Municipal Utilities 19d(viii) Vermillion Light & Power 19e East River Electric Power Cooperative, Inc. 19f Corn Belt Power Cooperative 19g NorthWestern Corporation (South Dakota) 19h Northwest Iowa Power Cooperative 19i Harlan Municipal Utilities 19j Central Power Electric Cooperative
Upper Missouri Zone – Total
8
Number from Zonal Placement Changes Map Zone Number from Attachment H Transmission Owner Effective Date Resolution 16 19 Upper Missouri Zone – Total 16 19a Western-UGP 10/1/2015 As Filed 16 19b Basin Electric Power Cooperative 10/1/2015 Settled 16 19c Heartland Consumers Power District 10/1/2015 Settled 16 19d Missouri River Energy Services - Total 10/1/2015 Settled 16 19d (i) Missouri River Energy Services 10/1/2015 Settled 16 19d(ii) Moorhead Public Service 10/1/2015 Settled 16 19d(iii) Orange City Municipal Utilities 10/1/2015 Settled 16 19d(iv) City of Pierre, South Dakota 10/1/2015 Settled 16 19d(v) City of Sioux Center, Iowa 10/1/2015 Settled 16 19d(vi) Watertown Municipal Utility Department 10/1/2015 Settled 16 19d(vii) Denison Municipal Utilities 2/1/2107 In Settlement 16 19d(viii) Vermillion Light & Power 2/1/2017 In Settlement 16 19e East River Electric Power Cooperative, 10/1/2015 Settled 16 19f Corn Belt Power Cooperative 10/1/2015 In Settlement 16 19g NorthWestern Corporation (South Dakota) 10/1/2015 Settled 16 19h Northwest Iowa Power Cooperative 10/1/2015 Settled 16 19i Harlan Municipal Utilities 10/1/2015 As Filed 16 19j Central Power Electric Cooperative 10/1/2015 In Settlement
9
New Transmission Owner Information
New Transmission Owner (TO) & Docket Number Existing Zone Placement Effective Date Requested Zonal ATRR (Schedule 9) Existing Zonal ATRR Before New Transmission Owner % Increase
Requested Zonal ATRR to Zone FERC Approved Zonal ATRR (Schedule 9) % Increase from FREC Approved Zonal ATRR to the Zone Resolution 1 ETEC ER07-396 AEP 1/1/2007 3,750,884 $88,681,579 0.47% no change no change As Filed 2 ITC Great Plains ER10-45 MKEC 8/18/2009 $673,368 $5,947,002 11.32% no change no change As Filed 3 OMPA ER10-273 AEP 1/1/2010 $748,647 $150,913,384 0.50% no change no change As Filed 4 OMPA ER10-273 OGE 1/1/2010 $106,268 $81,045,221 0.13% no change no change As Filed 5 Transcos ER11-2198 AEP 7/1/2010 $6,400 $133,972,249 0.005% no change no change As Filed 6 Prairie Wind ER11-3455 Regional 4/1/2011 No Sch 9 N/A 0.00% No Sch 9 N/A As Filed 7 Prairie Wind ER11-3455 Regional 4/1/2011 No Sch 9 N/A 0.00% No Sch 9 N/A As Filed 8 Kansas Power Pool ER12-140 Westar 12/20/2011 $528,917 $122,022,353 0.43% $350,243 0.29% Settled 9 Tri-County ER012-959 SPS 4/1/2012 $1,982,840 $110,464,906 1.79% $0 0.00% Hearing 10 Coffeyville ER14-418 AEP 7/1/2013 $391,790 $183,137,376 0.21% no change no change As Filed 11 Transource MO ER14-236 Regional 1/1/2014 No Sch 9 N/A 0.00% No Sch 9 N/A As Filed 12 Lea County ER14-1225 SPS 4/1/2014 $462,556 $109,581,048 0.42% $388,000 0.35% Settled 13 CNPPID ER15-279 NPPD 1/1/2015 $536,767 $47,541,737 1.13% $450,000 0.95% Settled 14 City of Indepedence ER15-1499 KCPL 6/1/2015 $7,237,454 $35,262,529 20.52% $3,000,000 8.51% Settled-Phase In 1/1/2017 $38,973,963* $3,750,000 9.62% Settled-Phase In 1/1/2018 $38,973,963* $5,000,000 12.83% Settled-Phase In 15 Tri-State ER16-204 NPPD 1/1/2016 $8,127,996 $45,213,710 17.98% Pending ??? In Settlement 16 AECC ER16-1546 AEP 7/1/2016 $584,186 $218,568,931 0.27% Pending ??? In Settlement 17 AECC ER16-1546 OGE 7/1/2016 $433,586 $93,307,022 0.46% Pending ??? In Settlement
* The % increase is based on the Schedule 9 ATRR for the Existing Zone’s TO at the time of the Phased-In ATRR for the New TO
SPP Case: Tri-State/NPPD Case (Docket No. ER16-204): * FERC Administrative Law Judge’s order -- dated February 23, 2017. MISO Case: MISO/City of Rochester, MN/NPS-Xcel Case(Docket Nos. ER15- 277 & ER14-2134): * FERC order -- dated December 30, 2014; FERC conditionally approve a
request by MISO and the City of Rochester “to make proposed revisions to . . . the MISO [Tariff] … subject to refund” and set the issues/dockets for hearing and settlement judge procedures. FERC 206 Docket (Docket No. EL17-44): * In a rehearing Order in MISO/Rochester Docket – dated February 3, 2017, FERC “institute[d] a proceeding pursuant to section 206 of the Federal Power Act (FPA) to examine the Joint Pricing Zone Revenue Allocation Agreement (JPZ Agreement) for Zone 16 of the MISO Tariff.” * The first round of comments in the FERC investigation were due March 16th.
10
Carl Monroe
11
(1) New Transmission Owner is already taking
Network transmission service – Has Load in SPP.
(2) New Transmission Owner is not taking
Network transmission service – Adds New Load to SPP.
(3) New Transmission Owner that will take no
transmission service – Adds no load to SPP.
12
Scenario can include a municipality or cooperative that is a Network transmission customer of SPP and requests to place its transmission assets under SPP tariff. Cost impacts in the following slide assume that the transmission facilities are placed in an existing zone where the entity is already taking Network Service.
13
14
Before Transfer After Transfer Cost Shift Tariff Revenue Requirement Existing 100,000,000 $ 100,000,000 $ Transferring Facilities
4,000,000 $ Total 100,000,000 $ 104,000,000 $ Load Ratio Share Load of Existing TO 98% 98% Load of New TO 2% 2%
Load of Existing TO 98,000,000 $ 101,920,000 $ Load of New TO 2,000,000 $ 2,080,000 $ Total 100,000,000 $ 104,000,000 $ Total Costs Load of Existing TO - Sch. 9 98,000,000 $ 101,920,000 $ 3,920,000 $ Load of New TO
2,000,000 $ 2,080,000 $ Transferring Facilities 4,000,000 $
Total 6,000,000 $ 2,080,000 $ (3,920,000) $
Scenario can include a municipality or cooperative that is not a Network transmission customer of SPP and requests to place its transmission assets under SPP tariff. Cost impacts in the following slide assume that the transmission facilities are placed in an existing zone and the entity begins taking Network Service at the time of asset transfer.
15
16
Before Transfer After Transfer Cost Shift Tariff Revenue Requirement Existing 100,000,000 $ 100,000,000 $ Transferring Facilities
4,000,000 $ Total 100,000,000 $ 104,000,000 $ Load Ratio Share Load of Existing TO 100% 98% Load of New TO 0% 2%
Load of Existing TO 100,000,000 $ 101,920,000 $ Load of New TO
2,080,000 $ Total 100,000,000 $ 104,000,000 $ Total Costs Load of Existing TO - Sch. 9 100,000,000 $ 101,920,000 $ 1,920,000 $ Load of New TO
2,080,000 $ Transferring Facilities 4,000,000 $
Total 4,000,000 $ 2,080,000 $ (1,920,000) $
Scenario can include transmission only company (Transco) that requests to place its transmission assets under SPP tariff. This scenario assumes the facilities were not directed to be built by SPP. Cost impacts in the following slide assume that the transmission facilities are placed in an existing zone.
17
18
Before Transfer After Transfer Cost Shift Tariff Revenue Requirement Existing 100,000,000 $ 100,000,000 $ Transferring Facilities
4,000,000 $ Total 100,000,000 $ 104,000,000 $ Load Ratio Share Load of Existing TO 100% 100% Load of New TO 0% 0%
Load of Existing TO 100,000,000 $ 104,000,000 $ Load of New TO
Total 100,000,000 $ 104,000,000 $ Total Costs Load of Existing TO - Sch. 9 100,000,000 $ 104,000,000 $ 4,000,000 $ New TO
Transferring Facilities 4,000,000 $
Total 4,000,000 $
(4,000,000) $
Charles Locke
19
Staff to consider revising the proposal to address:
(1) Planning process review consistent with SPP Tariff Attachment AI; (2) A symmetrical cost/benefit analysis; and (3) A phase-in process for regulatory assets that evaluates the time value of money.
20
several stakeholder calls, Staff found no consensus regarding mitigation. (2) Addition of an arbitrator-set mitigation was not well supported.
new & separate stakeholder initiative to consider the application of criteria to Schedule 9 facilities added to SPP rates.
facilities does improve reliability of operations &
initiated by the Applicant Transmission Owner through its revenue requirement filing.
21
2) SPP Requests Data From ATO 3) SPP conducts Analysis
(A) Zonal Placement & (B) Cost Analysis
4) Negotiations – ATO & Zone 5) SPP’s Cost Mitigation Analysis 6) SPP files to revise Tariff
22
If New Zone, Go to Step 6 If Agreement Reached, Step 6 No Agreement File Mitigation
mitigation threshold methodology, SPP Staff proposes to retain Steps 1-4 and 6 of the current Staff Proposal in order to promote information flow and transparency.
23
Reflect use of the system and avoid free riders Protect small loads from disproportionate charges
Settlements, OASIS, Att. H, Att. M, Att. T, RCAR, RRR File
load in comparable manner
24
such as when the smaller cost increase applies to the zone with higher rates
approach
interconnectivity and location of load
Zonal rates Size of Zones
25
the cost shift issue. The issue is not the load’s customer status, which drives Sch. 11 charges
the ATO’s load is or will be taking Network
all zonal loads in the baseline assumption
with its share of Sch. 11 charges
distinction between cost categories that have been separated under the Tariff for allocation purposes
26
Paul Suskie
27
2) SPP Requests Data From ATO 3) SPP conducts Analysis
(A) Zonal Placement & (B) Cost Analysis
4) Negotiations – ATO & Zone 5) SPP’s Cost Mitigation Analysis 65) SPP files to revise Tariff
28
If New Zone, Go to Step 65 If Agreement Reached, Step 65 File default revenue requirement Consider Removing
Improve transparency Increase information sharing Enable the opportunity for a negotiated compromise NOT INCLUDIING Step 5 (Mitigation)
Tariff.
threshold from the Current Staff Proposal due to lack of consensus.
If no decision is made by stakeholders, the default is what SPP has done to date.
29
30
2) SPP Requests Data From ATO 3) SPP conducts Analysis
(A) Zonal Placement & (B) Cost Analysis
4) Negotiations – ATO & Zone 5) SPP’s Cost Mitigation Analysis 65) SPP files to revise Tariff
If New Zone, Go to Step 65 If Agreement Reached, Step 65 File default revenue requirement Consider Removing
31
In evaluating the zonal placement of existing facilities, SPP staff is to review the information provided by the ATO and apply the following criteria in determining whether to place the facilities in a new Zone:
benchmark, as described in the Zonal Placement Analysis Procedures (Appendix B);
and
transfer. If the facilities are not placed in a new Zone, SPP staff is to apply the following criteria in determining which existing Zone the facilities are to be placed in:
transfer.
consensus regarding mitigation.
well supported.
32
If approved, each element of the policy could be placed as follows:
Scope of the zonal placement policy Description of the steps in the process Zonal placement key criteria
Informational requirements Zonal placement analysis details Transferring facilities review Cost mitigation process, if approved
33
34