oftos and round 3
play

OFTOs and Round 3 Chris Veal When to initiate OFTO appointment - PowerPoint PPT Presentation

OFTOs and Round 3 Chris Veal When to initiate OFTO appointment Options cover a spectrum but in general the OWF developer can: Seek for an early OFTO appointment Seek a late OFTO appointment (post-consents application) Would you


  1. OFTOs and Round 3 Chris Veal

  2. When to initiate OFTO appointment • Options cover a spectrum but in general the OWF developer can: – Seek for an early OFTO appointment – Seek a late OFTO appointment (post-consents application) Would you want to procure your round 3 offshore wind farm in the next 12 months on a fixed price basis? • Consequences of a late OFTO appointment is that the OWF developer will have to manage the development of the OFTO assets – but this is what you will have done in the past

  3. Benefits and issues of late OFTO appointment • A late OFTO appointment significantly reduces development timeline (by between 6 months and 2 years) • A late OFTO appointment will allow all forms of financing to be used, not just balance sheet • A late OFTO appointment will lead to significantly lower priced OFTO bids (as less risk for the OFTO) • Issues that will need to be addressed by Ofgem in enduring regime: – Recovery of development costs – Risk of OFTO variant bids that do not meet project timescales • Issues that will need to be addressed by OWF developers in their OFTO strategies: – Risk that few (and only the more expensive) OFTOs bid if development not done properly – Expertise and resourcing of OFTO asset development

  4. Zonal OFTOS versus project specific OFTOs • Zonal appointment means: – Appointment of OFTO up to 10 years prior to construction – Without design, consents, land rights available • This will lead to fewer bidders, more OFTO risk, higher priced bids • What are the benefits? • Co-ordinated development of the OFTO assets preferable (see later) but ... • Zonal grid connections will be modular and can be procured individually Source: National Grid/Econnect Round 3 Offshore Wind Farm Connection Study v 1.0

  5. Co-ordination issues - 1 • Onshore connection points & grid capacity • Cable routing • Land rights & consent acquisition • Interconnectivity & standards Source: National Grid/Econnect Round 3 Offshore Wind Farm Connection Study v 1.0

  6. Co-ordination issues - 2 Project 2 Unsuitable Project 1 area for • Onshore connection points & grid capacity cables • Cable routing Unsuitable • area for Land rights & consent acquisition cables • Interconnectivity & standards Project 2 Unsuitable Project 1 area for cables Unsuitable area for cables

  7. Co-ordination issues - 3 • Onshore connection points & grid capacity • Cable routing • Land rights & consent acquisition • Interconnectivity & standards OFTO 1 OFTO 2 TO OFTO 3

  8. Co-ordination issues - 4 • Onshore connection points & grid capacity • Cable routing • Land rights & consent acquisition • Interconnectivity & standards OFTO 1 OFTO 2 OFTO 3

  9. Recommendations • Seek a late OFTO appointment • Develop the OFTO assets yourself • Be aware of different OFTO financing options and their requirements • Get help from an experienced prospective OFTO or other advisers if necessary • Ensure enduring process takes account of development costs, project timescales and standards • Co-ordination for some zones/projects will be a key issue: – Understand the issues – Co-operate where possible – Standardise requirements – Lobby for the key bodies (NETSO & others) to take responsibility – Respond to the enduring offshore transmission regime consultation on these issues

  10. Contact details: Email: chris.veal@transmissioncapital.com Tel: 020 31787996 Mob: 07768 036613 Web: www.transmissioncapital.com

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend