OFTOs and Round 3

Chris Veal

slide-2
SLIDE 2

When to initiate OFTO appointment

  • Options cover a spectrum but in general the OWF developer can:

– Seek for an early OFTO appointment – Seek a late OFTO appointment (post-consents application)

Would you want to procure your round 3 offshore wind farm in the next 12 months on a fixed price basis?

  • Consequences of a late OFTO appointment is that the OWF developer will have to manage

the development of the OFTO assets – but this is what you will have done in the past

slide-3
SLIDE 3

Benefits and issues of late OFTO appointment

  • A late OFTO appointment significantly reduces development timeline (by between 6

months and 2 years)

  • A late OFTO appointment will allow all forms of financing to be used, not just balance sheet
  • A late OFTO appointment will lead to significantly lower priced OFTO bids (as less risk for

the OFTO)

  • Issues that will need to be addressed by Ofgem in enduring regime:

– Recovery of development costs – Risk of OFTO variant bids that do not meet project timescales

  • Issues that will need to be addressed by OWF developers in their OFTO strategies:

– Risk that few (and only the more expensive) OFTOs bid if development not done properly – Expertise and resourcing of OFTO asset development

slide-4
SLIDE 4

Zonal OFTOS versus project specific OFTOs

  • Zonal appointment means:

– Appointment of OFTO up to 10 years prior to construction – Without design, consents, land rights available

  • This will lead to fewer

bidders, more OFTO risk, higher priced bids

  • What are the benefits?
  • Co-ordinated development
  • f the OFTO assets

preferable (see later) but ...

  • Zonal grid connections will

be modular and can be procured individually

Source: National Grid/Econnect Round 3 Offshore Wind Farm Connection Study v 1.0

slide-5
SLIDE 5

Co-ordination issues - 1

  • Onshore connection points & grid capacity
  • Cable routing
  • Land rights & consent acquisition
  • Interconnectivity & standards

Source: National Grid/Econnect Round 3 Offshore Wind Farm Connection Study v 1.0

slide-6
SLIDE 6

Co-ordination issues - 2

  • Onshore connection points & grid capacity
  • Cable routing
  • Land rights & consent acquisition
  • Interconnectivity & standards

Project 1 Project 2 Project 1 Project 2 Unsuitable area for cables Unsuitable area for cables Unsuitable area for cables Unsuitable area for cables

slide-7
SLIDE 7

Co-ordination issues - 3

  • Onshore connection points & grid capacity
  • Cable routing
  • Land rights & consent acquisition
  • Interconnectivity & standards

OFTO 1 OFTO 2 OFTO 3 TO

slide-8
SLIDE 8

Co-ordination issues - 4

  • Onshore connection points & grid capacity
  • Cable routing
  • Land rights & consent acquisition
  • Interconnectivity & standards

OFTO 1 OFTO 2 OFTO 3

slide-9
SLIDE 9

Recommendations

  • Seek a late OFTO appointment
  • Develop the OFTO assets yourself
  • Be aware of different OFTO financing options and their requirements
  • Get help from an experienced prospective OFTO or other advisers if necessary
  • Ensure enduring process takes account of development costs, project timescales and

standards

  • Co-ordination for some zones/projects will be a key issue:

– Understand the issues – Co-operate where possible – Standardise requirements – Lobby for the key bodies (NETSO & others) to take responsibility – Respond to the enduring offshore transmission regime consultation on these issues