Nyrstar Port Pirie 10 th GMUSG and SACOME Resource Industry Conference and Trade Expo September 2014 future 1 Our History Nyrstar Port Pirie Smelter - 125 Years of Operations 1880 1897 1988 2001 2002 2006 Nyrstar formally announces


slide-1
SLIDE 1

Nyrstar Port Pirie

10th GMUSG and SACOME Resource Industry Conference and Trade Expo

September 2014

future

1

slide-2
SLIDE 2

Nyrstar Port Pirie Smelter - 125 Years of Operations

2

2

1880 1897 1988 2001 2006 2002 Nyrstar formally announces major Redevelopment of the Port Pirie Smelter expected to cost $514M with commissioning in 2016. 05/14

Our History

slide-3
SLIDE 3

3

Our Business Model

slide-4
SLIDE 4

4

Nyrstar Operating Locations – Geographically diverse multi-asset footprint

Mines/Streaming Metals Processing Other Operations 1 Campo Morado, Mexico 11 Auby, France 18 Fohl (Interest 50%), China 2 Cotonga, Peru 12 Balen/Overpelt, Belgium 19 Genesis (Interest 50%), China 3 Coricancha, Peru 13 Budel, The Netherlands 4 El Mochito, Honduras 14 Clarkesville, USA Development 5 El Toqui, Chile 15 Hobart, Australia 20 Herencia (Interest 10.03%), Chile 6 Langlois, Canada 16 Hoyanger, Norway 21 Ironbark Zinc Ltd (Interest 26%), Greenland 7 Myra Falls, Canada 17 Port Pirie, Australia 8 Pucarrajo, Peru 9 Talvivaara (Streaming Agreement), Finland 10 Tennessee Mines (USA)

Where We Operate

slide-5
SLIDE 5

Our Markets - Worldwide

5

Our Markets

slide-6
SLIDE 6

6

Redeveloping Port Pirie for a Sustainable future

Fundamentally different business model for Port Pirie; transformed operation capable of processing a wider range

  • f high margin metal bearing feed materials

ABILITY TO PROCESS ALL INTERNALLY GENERATED RESIDUES, ALLOWING NYRSTAR TO CONTROL APPROXIMATELY 50% OF FEED MATERIAL REQUIREMENTS, DRIVES FINANCIAL RETURNS AND SIGNIFICANTLY REDUCES SUPPLY RISK

PRIMARY LEAD SMELTER POLY-METALLIC PROCESSING & RECOVERY CENTRE

Third party produced feed materials

PORT PIRIE

Hobart smelter residue Other material 3rd party lead concentrates

Nyrstar produced feed materials

Nyrstar Zinc Smelters residues

PORT PIRIE

Other material 3rd party lead concentrates Third party residues Complex waste streams E-waste Nyrstar mine concentrates

slide-7
SLIDE 7

Using best available and proven technology currently in operation at over 25 sites

7

Redeveloping Port Pirie for a Sustainable future

  • Transformation will replace out-dated

sinter plant with a state of the art

  • xygen enriched enclosed bath

smelting furnace technology and new sulphuric acid plant.

  • Technology is proven; same class of

core technology utilised at over 25 sites.

  • Independent of the Transformation,

Nyrstar is investigating the feasibility

  • f a series of small incremental

investments to capture additional metal streams.

EBS Oxidation Furnace (Top Submerged Lance)

slide-8
SLIDE 8

The application of fully enclosed bath smelting technology has a range of environmental benefits

8

Redeveloping Port Pirie for a Sustainable future

  • Step change reduction in airborne metal,

dust and sulphur dioxide emissions

  • Significant reduction in community lead

exposure risks

  • Reduced intermediate materials

movements on-site and therefore reduce

  • n-site dust generation and movement
  • Improved Blast Furnace environmental

performance

  • Improved hygiene conditions for workers

EXPECTED TO DELIVER A SIGNIFICANTLY IMPROVED ENVIRONMENTAL PERFORMANCE THROUGH REDUCED EMISSIONS

slide-9
SLIDE 9

Continued support for community exposure reduction programs

9

Redeveloping Port Pirie for a Sustainable future

A NEW TARGETED LEAD ABATEMENT PROGRAM WILL INITIATE AND MANAGE COMMUNITY LEAD EXPOSURE REDUCTION INITIATIVES

Nyrstar

  • AUD $5M initiation investment
  • AUD $3Mpa for up to 10 years

SA Government

  • AUD $1.5Mpa for up to 10 years
slide-10
SLIDE 10

10

Redeveloping Port Pirie for a Sustainable future OUTLINE PROJECT TIMEFRAME OUTLINE PROJECT STRUCTURE Senior VP Metals Processing & Chief Development Officer Michael Morley Vice President Metals Refining Bertus De Villiers General Manager Redevelopment Andrew Napier

‒ Running existing asset ‒ Ensure policies, procedures & standards compliance ‒ Joint responsibility to manage technology transition ‒ Project management and execution ‒ Functional reporting to Project Steering Committee ‒ Manage global engineering contractor ‒ Joint responsibility to manage technology transition

REDEVELOPMENT LED BY A DEDICATED GENERAL MANAGER, SUPPORTED BY A PROJECT TEAM COMPRISING EXPERIENCED AND HIGHLY SKILLED INTERNAL AND EXTERNAL RESOURCES

Project

  • verview
slide-11
SLIDE 11

How does my business get involved?

Port Pirie Transformation website ‒ http://www.portpirietransformation.com

 Transformation general queries email address

‒ info@portpirietransformation.com

Industry Capability Network, South Australia ‒ http://www.icn.org.au/sa_home

11

Redeveloping Port Pirie for a Sustainable future

slide-12
SLIDE 12

QUESTIONS