North T Nor h Tarrant Express rrant Express Pr Project Updat - - PowerPoint PPT Presentation

north t nor h tarrant express rrant express pr project
SMART_READER_LITE
LIVE PREVIEW

North T Nor h Tarrant Express rrant Express Pr Project Updat - - PowerPoint PPT Presentation

North T Nor h Tarrant Express rrant Express Pr Project Updat oject Update 35W Coalition Meeting 35W Coalition Meeting April 11, 2012 April 11, 2012 www.NorthTarrantExpress.com | 1-888-NTE-2015 The North Tarrant Express construction


slide-1
SLIDE 1

www.NorthTarrantExpress.com | 1-888-NTE-2015

35W Coalition Meeting 35W Coalition Meeting April 11, 2012 April 11, 2012 Nor North T h Tarrant Express rrant Express Pr Project Updat

  • ject Update
slide-2
SLIDE 2

www.NorthTarrantExpress.com | 1-888-NTE-2015

The North Tarrant Express construction project is on track!

West Segment East Segment

slide-3
SLIDE 3

www.NorthTarrantExpress.com | 1-888-NTE-2015

Project Overview

  • Construction period: Oct 2010 to mid-2015
  • Rebuilding existing general purpose lanes
  • Improving/expanding frontage lanes
  • Adding managed toll lanes
slide-4
SLIDE 4

www.NorthTarrantExpress.com | 1-888-NTE-2015

Project Overview: By the Numbers

  • 13

13.5- .5-mile corridor stretching from Fort Worth (IH 35W) to Euless

  • 18

18 cross-street bridges to be demolished and rebuilt

  • 50+

50+ on-ramps and off-ramps

  • 150,000

0,000 drivers per day

slide-5
SLIDE 5

www.NorthTarrantExpress.com | 1-888-NTE-2015

Project Overview: By the Numbers

  • 1.1 million

1 million man-hours to date

  • 900

900 workers in the corridor currently

  • 22%

22% of design and construction completed

  • 399

399 right-of-way parcels secured (100%)

  • $480 million

$480 million spent to date on design, ROW, construction

slide-6
SLIDE 6

www.NorthTarrantExpress.com | 1-888-NTE-2015

Project Overview: By the Numbers

  • 6.85 million

6.85 million pounds of rebar tied

  • 920,000

920,000 cubic yards of dirt moved

  • 50,000

50,000 linear feet of permanent pipe laid

  • 40,000

40,000 cubic yards of concrete poured

  • 40,000

40,000 tons of asphalt laid

slide-7
SLIDE 7

www.NorthTarrantExpress.com | 1-888-NTE-2015

IH 35W Northbound

slide-8
SLIDE 8

www.NorthTarrantExpress.com | 1-888-NTE-2015

IH 35W/IH 820 Interchange

slide-9
SLIDE 9

www.NorthTarrantExpress.com | 1-888-NTE-2015

IH 35W/IH 820 Interchange

Cap placement and the setting of beams at the IH 35W/ IH 820 split

slide-10
SLIDE 10

www.NorthTarrantExpress.com | 1-888-NTE-2015

IH 35W/IH 820 Interchange

Managed lane tie-ins from IH 35W to IH 820

slide-11
SLIDE 11

www.NorthTarrantExpress.com | 1-888-NTE-2015

West Segment

EB IH 820 frontage road near Denton Hwy 377 EB IH820 frontage road near Beach Street

slide-12
SLIDE 12

www.NorthTarrantExpress.com | 1-888-NTE-2015

West Segment

WB IH820 frontage road btwn Haltom Rd. and Denton Hwy 377 EB IH820 frontage road near Holiday Lane

slide-13
SLIDE 13

www.NorthTarrantExpress.com | 1-888-NTE-2015

East Segment

Making way for new lanes near Plainview Dr. Norwood Drive bridge demolition

slide-14
SLIDE 14

www.NorthTarrantExpress.com | 1-888-NTE-2015

East Segment

Construction of the new pedestrian bridge

slide-15
SLIDE 15

www.NorthTarrantExpress.com | 1-888-NTE-2015

East Segment

Bridge work in the SH 121/183 split

slide-16
SLIDE 16

www.NorthTarrantExpress.com | 1-888-NTE-2015

Major Construction Activity Upcoming West Segment

  • Overnight closures of Beach Street (Apr 16-19)

to place beams

  • Lane reductions at Beach Street and Denton

Hwy 377 (through April) for major utility work

  • Continued work on managed lane tie-ins from

IH 35W to IH 820

slide-17
SLIDE 17

www.NorthTarrantExpress.com | 1-888-NTE-2015

Major Construction Activity Upcoming East Segment

  • Closure/demolition of Hurstview bridge (mid-April)
  • Opening of pedestrian bridge in Hurst (mid-April)
  • Closure of Central Drive off-ramp from SH

121/183 (late April)

  • Major utility work between Norwood Drive and

Industrial Blvd. (mid-April; lasting 3 months)

slide-18
SLIDE 18

www.NorthTarrantExpress.com | 1-888-NTE-2015

Other Key Activities/Initiatives

  • Radio advertising campaign underway
  • National Work Zone Awareness Week (April 23-28);

press conference on April 24

  • Inaugural bridge walk and public open house at

pedestrian bridge (mid-May)

slide-19
SLIDE 19

www.NorthTarrantExpress.com | 1-888-NTE-2015

Inf Information Hotline rmation Hotline 1-888-NTE-20 1-888-NTE-2015 Inf Inform rmat ation ion Cent Center er 8713 Air Airpor

  • rt F

t Free eeway, Suit Suite 1 e 100 Nor North Richland Hills, T h Richland Hills, Texas 7 xas 76180 Pr Project W

  • ject Websit

bsite www.Nor .NorthT thTarrantE rrantExpre ress.com ss.com Fa Fan u us on Fa Facebook Follo llow us @NTExpress w us @NTExpress

Keeping You Informed