North Star Pre-Construction Meeting Presentation Presented by: Gas - - PowerPoint PPT Presentation

north star
SMART_READER_LITE
LIVE PREVIEW

North Star Pre-Construction Meeting Presentation Presented by: Gas - - PowerPoint PPT Presentation

North Star Pre-Construction Meeting Presentation Presented by: Gas Engineering New Business March 16, 2017 1 Providing Natural Gas To North Star 2 North Star Project Overview Total Feet of Pipe Installed: approx. 12,255 of 2


slide-1
SLIDE 1

1

North Star

Pre-Construction Meeting Presentation

Presented by: Gas Engineering New Business March 16, 2017

slide-2
SLIDE 2

2

Providing Natural Gas To North Star

slide-3
SLIDE 3

3

North Star Project Overview

  • Total Feet of Pipe Installed:
  • approx. 12,255’ of 2”
  • approx. 750’ of 4”
  • approx. 465’ of 6”
  • approx. 8,135’ of 8”
  • Customers in project area:
  • 210 directly impacted
  • Customers signed up for gas service line:
  • 87 customers or 41% of neighborhood
  • We are in need of additional applicants based on project bids

received

  • Size of PY pipe to be installed:
  • 2” , 4”, 6” & 8”
slide-4
SLIDE 4

4

Preliminary Design – North Star

slide-5
SLIDE 5

5

North Star Construction Timeline

  • Construction Schedule:
  • Begin construction – Late March
  • Complete main installation – Late July
  • Complete final restoration – 10/31/2017
  • All work is weather dependent
  • Scope of work may change daily due

to unforeseen conditions

  • The intent is to complete final

restoration once all main and services are complete.

  • Temporary restoration will be done at the end of each task or

week.

slide-6
SLIDE 6

6

Natural Gas Expansion Project

  • Project scope involves:
  • Marking of utility lines – 8-1-1
  • Awarding bid contractor will test hole over main
  • Set up of the directional drill
  • Excavation of the receiving pits, etc.
  • Boring of the main
  • Gas main will be tied-in (energized)
  • Installation of service lines to applicable locations (bore)
  • Restoration will occur once all main and services are complete
slide-7
SLIDE 7

7

Installation of Natural Gas

  • Preliminary order of Gas Main installation by street for North Star

1. Polaris Dr 2. Meteor Ct 3. Mercury Rd 4. Jupiter Rd 5. Neptune Dr 6. North Star Rd 7. Beech Hill Dr 8. Mercury Rd 9. Mars Rd

  • 10. Meteor Ln
  • 11. Orbit Cir
  • 12. Saturn Dr
  • 13. Jupiter Rd
  • 14. Venus Dr
  • 15. Planet Rd
  • 16. Galaxy Dr
  • 17. Comet Lane
slide-8
SLIDE 8

8

Service Installations

  • Services will be installed to each applicant when the customer

is ready to start receiving natural gas

  • Each applicant will have an on-site meeting with the field

technician and during those on-site meetings it will be determined if the customer is ready to receive a natural gas service line during this project.

  • Applicants are refunded their $200 security deposit when

natural gas is flowing to the residence for a gas-fired appliance.

Customer Converts & Gas meter is installed Security deposit refunded

slide-9
SLIDE 9

9

Gas Conversion Projects: Staging of Material

  • Locations in

neighborhood that have been identified as low traveled areas are used for the staging of materials. Material is coned off for safety and kept to minimum level of encroachment into roadway.

slide-10
SLIDE 10

10

Gas Expansion Projects: Test Holes

  • Test holes may be performed prior to main installation by either

hand digging or possibly vacuum excavation

slide-11
SLIDE 11

11

Gas Conversion Projects: Test Holes

  • Left: Test hole areas left safe with proper coverage until

temporary restoration

  • Right: Completed temporary restoration with backfill
slide-12
SLIDE 12

12

Gas Conversion Project: Main Installation

  • Install new main throughout neighborhood in the state right-of-

way at the curb line utilizing a directional bore technique. Equipment may need to encroach on private property for perpendicular main alignments

slide-13
SLIDE 13

13

Gas Conversion Project: Main Installation

  • Right: temporary restoration on a driveway that was open cut

due to unforeseen underground conditions

  • Left: temporary restoration on large section of receiving pit for

main

slide-14
SLIDE 14

14

Gas Conversion Project: Main Installation Final Restoration On Driveway

slide-15
SLIDE 15

15

Gas Conversion Project: Main Installation - Temporary Restoration

  • Left: temporary restoration of test hole in roadway
  • Right: temporary restoration of disturbed area in right-of-way
slide-16
SLIDE 16

16

Service line, Riser, & Meter bar

  • When customer is ready to

convert to a gas-fired appliance, they must:

  • Hire a licensed contractor to

install fuel lines

  • Have NCCO inspect & tag

fuel line

  • Private contractor ties fuel

line into meter bar

  • Call Delmarva Power to

schedule meter install

slide-17
SLIDE 17

17

Meter Installation

  • Example of Inspection Tag
slide-18
SLIDE 18

18

North Star Gas Project Contact Sheet

  • Business Development Coordinator – Mike June
  • Email: michael.june@delmarva.com
  • Phone: (302) 429-3290
  • Field Technician – Brent Lobley
  • Email: Brent.Lobley@delmarva.com
  • Phone: (302) 650-3067
  • Project Engineer – Rob Rex
  • Email: robert.rex@delmarva.com
  • Phone: (302) 429-3222
slide-19
SLIDE 19

19

Questions?

  • Thanks for attending!