North Shore Wastewater Treatment Plant PROJECT UPDATE Joan Liu Tom - - PowerPoint PPT Presentation

north shore wastewater treatment plant
SMART_READER_LITE
LIVE PREVIEW

North Shore Wastewater Treatment Plant PROJECT UPDATE Joan Liu Tom - - PowerPoint PPT Presentation

North Shore Wastewater Treatment Plant PROJECT UPDATE Joan Liu Tom Sadleir SENIOR PROJECT ENGINEER POLICY COORDINATOR, PUBLIC INVOLVEMENT North Shore Waterfront Liaison Committee, September 14, 2017 Lions Gate Secondary Wastewater Treatment


slide-1
SLIDE 1

North Shore Wastewater Treatment Plant

PROJECT UPDATE

Joan Liu

SENIOR PROJECT ENGINEER

Tom Sadleir

POLICY COORDINATOR, PUBLIC INVOLVEMENT

North Shore Waterfront Liaison Committee, September 14, 2017

slide-2
SLIDE 2

North Shore Waterfront Liaison Committee October 22,2015

Lions Gate Secondary Wastewater Treatment Plant

PROJECT UPDATE

Andrea Winkler, Program Manager, Public Involvement Paul Dufault, P.Eng., Project Manager

slide-3
SLIDE 3

3

Regulatory Driven

  • Integrated Liquid Waste and

Resource Management Plan - 2011

  • Wastewater Systems Effluent

Regulations – 2012

  • Secondary Treatment by

December 31, 2020

slide-4
SLIDE 4

4

North Shore Wastewater Treatment Program

3 Components: mponents:

  • North Shore WWTP
  • New Conveyance

(Pump Station + Pipes)

  • Decommissioning of existing

LGWWTP

slide-5
SLIDE 5

5

  • Acciona Infrastructure Canada
  • Operating in Canada since 2001
  • Head Office in Vancouver
  • 9 Major Infrastructure Projects in

Canada including 5 P3 Projects worth

  • ver $ 4.3 Billion
  • Acciona Agua S.A.
  • Design, Build, Finance and Operation
  • f Water and Wastewater Plants
  • Over 300 WWTPs
  • 35 P3 Type water sector projects

ADApT Consortium

slide-6
SLIDE 6

6

slide-7
SLIDE 7

7

Remediation

slide-8
SLIDE 8

8

Stone Column

slide-9
SLIDE 9

9

NSWWTP Project Schedule

slide-10
SLIDE 10

10

Conveyance

slide-11
SLIDE 11

11

Pump Station

slide-12
SLIDE 12

12

Pipes

slide-13
SLIDE 13

13

Request for Qualification

  • The purpose is to invite interested parties to submit responses

indicating their interest in, and qualifications for the Project.

  • Based on the responses a shortlist of up to 3 Proponents will

be invited to participate in the Request for Proposals stage

Closing

Aug 17

2017

slide-14
SLIDE 14

14

Request for Proposals

  • Shortlisted Respondents from the RFQ stage will be invited to submit

proposals that will include technical and financial aspects of the project.

  • RFP Process is to include collaborative discussion relating to technical and

commercial matters.

  • The objective is to select the Preferred Proponent who may be offered the
  • pportunity to enter in to the Project Agreement

Sep 27

2017

slide-15
SLIDE 15

Activity

NSWWTP Design Build Finance RFP NSWWTP Design Build Secondary Effluent NSWWTP Commissioning and Handover Conveyance Indicative Design Property Acquisition Conveyance Design Build RFQ Conveyance Design Build RFP Pump Station Design/Construction Pipeline Design/Construction Conveyance System Commissioning Decommissioning Existing Lions Gate WWTP

2020 2021 2016 2017 2018 2019 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3

Overall Program Schedule

slide-16
SLIDE 16

Consultation and Communications

North Shore Wastewater Treatment Plant Metro Vancouver activity since October 2015

  • Dec 2015 Education Workshop
  • Feb 2016 Norgate Open House – Project Update
  • Dec 2016 Newsletter – Project Update
  • Apr 2017 Letters to First Nations

Lions Gate Public Advisory Committee – Phase 2

  • 6 meetings to April 2017 (plant design and opportunities; tour of US facility;

construction mitigation, traffic management)

slide-17
SLIDE 17

Consultation and Communications

North Shore Wastewater Treatment Plant (continued) April 2017: Project Agreement with ACCIONA

  • ACCIONA assumes responsibility for communications planning,

community relations, consultation ACCIONA

  • Introduced at final LGPAC meeting
  • May 18, 2017 Open House – Public Impact Mitigation Plan
  • June 21, 2017 Open House – DNV Development Permit process
  • Pre-construction activity notification
  • Ongoing communications
slide-18
SLIDE 18

18

Pump Station + Pipes

slide-19
SLIDE 19

Questions