NIUPOWER UPDATE & FORWARD PLAN PNG Petroleum & Energy Summit - - PowerPoint PPT Presentation

niupower update forward plan png petroleum energy summit
SMART_READER_LITE
LIVE PREVIEW

NIUPOWER UPDATE & FORWARD PLAN PNG Petroleum & Energy Summit - - PowerPoint PPT Presentation

NIUPOWER UPDATE & FORWARD PLAN PNG Petroleum & Energy Summit 20 th March 2019 CONTENTS Port Moresby Power Station Status Project Reflections Positioning for the Future NiuPower Update & Forward Plan | NiuPower Limited


slide-1
SLIDE 1

NIUPOWER UPDATE & FORWARD PLAN PNG Petroleum & Energy Summit 20th March 2019

slide-2
SLIDE 2

CONTENTS

NiuPower Update & Forward Plan | NiuPower Limited | Page 1

  • Port Moresby Power Station Status
  • Project Reflections
  • Positioning for the Future
slide-3
SLIDE 3

CONTENTS

NiuPower Update & Forward Plan | NiuPower Limited | Page 2

  • Port Moresby Power Station Status
  • Project Reflections
  • Positioning for the Future
slide-4
SLIDE 4

PORT MORESBY POWER STATION

NiuPower Update & Forward Plan | NiuPower Limited | Page 3

slide-5
SLIDE 5

POM POWER STATION STATUS

  • Commissioning commenced early January
  • The control system is now fully functioning and the power circuits

are live – partially back fed from the PPL grid

  • First engine start occurred last Friday
  • The other five engines are being started and run tested in turn
  • Power station performance testing will commence early April
  • Commercial Operations Date (COD) currently forecast for the third

week of April

NiuPower Update & Forward Plan | NiuPower Limited | Page 4

slide-6
SLIDE 6

CONTENTS

NiuPower Update & Forward Plan | NiuPower Limited | Page 5

  • Port Moresby Power Station Status
  • Project Reflections
  • Positioning for the Future
slide-7
SLIDE 7

PROJECT REFLECTIONS

  • NiuPower were committed from the start to ensure we provided

the power station that PPL and PNG needed

  • The focus was on maximum efficiency and flexibility
  • Thus we choose to use six high efficiency reciprocating gas

engine generator sets:

  • Higher capital cost per MW than open cycle gas turbines but also;
  • Much higher thermal efficiency leading to ~US$5 million/year less gas

required leading to;

  • A lower Levelised Cost of Electricity (LCOE) over the project life
  • Able to efficiently deliver any output from 6MW to 58MW and

thus exactly match PPL’s load at any time

NiuPower Update & Forward Plan | NiuPower Limited | Page 6

slide-8
SLIDE 8

PROJECT REFLECTIONS (Con’t)

NiuPower Update & Forward Plan | NiuPower Limited | Page 7

  • NiuPower were also very focused on maximising the PNG Local

Content

  • Capital cost is ~US$100 million
  • ~US$40 million was spent with local PNG subcontractors
  • ~US8 million in income tax paid by to the PNG Gov’t by workers
  • Average site labour force of ~300 people for over 12 months –

93% were PNG citizens

  • All CEPA environmental approvals and requirements were

secured as required and fully complied with The project has now passed 1 million work hours with zero recordable incidents – An absolutely world class performance

slide-9
SLIDE 9

NiuPower Update & Forward Plan | NiuPower Limited | Page 8

  • Port Moresby Power Station Status
  • Project Reflections
  • Positioning for the Future

CONTENTS

slide-10
SLIDE 10

NIUPOWER’S FUTURE ROLE

NiuPower Update & Forward Plan | NiuPower Limited | Page 9

  • The successful development of the Port Moresby Power Station

has demonstrated private sector investment in gas-fired generation can provide a very cost efficient solution

  • Large centralised power stations only make sense where there is

a large load within the region

  • Much of PNG is sparsely populated and thus small decentralized

renewable generation will have a significant role to play

  • The State, through PPL, need to be setting the policy and

strategy – IPPs like NiuPower are here to support this with capital and expertise

  • NiuPower are also keen to engage with major industrial &/or

resource developers who are looking for an off Balance Sheet power solution

slide-11
SLIDE 11

QUESTIONS

richard.robinson@niupower.com.pg

NiuPower Update & Forward Plan | NiuPower Limited | Page 10