New MTT - Approaches 20 Marine Raker Pile Installation New MTT - - - PDF document

new mtt approaches
SMART_READER_LITE
LIVE PREVIEW

New MTT - Approaches 20 Marine Raker Pile Installation New MTT - - - PDF document

19 New MTT - Approaches 20 Marine Raker Pile Installation New MTT - Approaches Excavation of Approach following installation of SOE and concrete piles Struts and Walers to brace excavation Placement of Inverts, Walls, Roofs


slide-1
SLIDE 1

New MTT - Approaches

19

slide-2
SLIDE 2

20

Marine – Raker Pile Installation

slide-3
SLIDE 3

New MTT - Approaches

21

 Excavation of Approach following installation of SOE and concrete piles  Struts and Walers to brace excavation  Placement of Inverts, Walls, Roofs

slide-4
SLIDE 4

New MTT - Approaches

22

 Excavation of Approach following installation of SOE and concrete piles  Struts and Walers to brace excavation  Placement of Inverts, Walls, Roofs

slide-5
SLIDE 5

Existing Tunnel Rehab and Upgrades

23

 Three existing tubes — Downtown Tunnel West Bound — Downtown Tunnel East Bound — Midtown Tunnel  Scope of repair similar

slide-6
SLIDE 6

Existing Tunnel Rehab and Upgrades

24

 Scope — Goal is to extend the useful life of existing assets — Structural repairs — Delaminated and spalled concrete — Goal to meet NFPA 502 — (100 Megawatt fire) — Ventilation upgrades — ITS system — Lighting Upgrades

slide-7
SLIDE 7

Schedule – Project Wide

25

slide-8
SLIDE 8

 Project Manager – MLK Extension  Skanska USA Civil Southeast —Past Projects —Huguenot Bridge, Richmond, VA (Project Manager) —Bridge of Lions, St. Augustine, FL (Project Manager) —Route 5 Bridge over Chickahominy River, James City County, VA (Project Manager) —APM Terminals Interchange, Portsmouth, VA (Project Engineer) —Pinner’s Point Interchange, Portsmouth, VA (Assistant Project Manager)

26

SKW Constructors – Brent Hunt

slide-9
SLIDE 9

MLK Extension – Project Wide

27

slide-10
SLIDE 10

28

MLK Extension – Project Wide

Proposed MLK I-264 London Blvd.

slide-11
SLIDE 11

 Technical Requirements – Final Design Criteria MLK Extension —Designed to meet VDOT and AASHTO requirements —Standard VDOT project with few exceptions —Design-Build —Design Exception required at London Blvd Ramp —Proceed with existing ramp geometry (substandard) —DB Scope includes ROW Acquisition

29

MLK Extension

slide-12
SLIDE 12

 Construction through populated area  Railroad Coordination —CSX —NPBL  Historically significant sites —Mount Calvary Cemetery Complex —Potter’s Field site —Unmarked graves —Protect from construction equipment

30

MLK Extension – Design Considerations

slide-13
SLIDE 13

MLK Extension – Design Considerations

31

 Calvary Baptist Church — Preconstruction surveys — Seismic Monitoring during construction

slide-14
SLIDE 14

 Right of Way Acquisition —Acquire property on behalf of the Commonwealth —69 Parcels —34 Structures to demolish —Private Residential Homes —Relocate residents —Inspect homes, abate as necessary, then demolish —Businesses —Similar process to residential properties —Additional work to coordinate movement of businesses —Vulcan Materials —Old Dominion Demolition

32

MLK Extension – Design Considerations

slide-15
SLIDE 15

 General Information —1 mile of controlled access freeway —1.4 miles of elevate structure of varying width (1 to 3 lanes in each direction) —Retaining Walls —MSE Wall —Geofoam —Other —SWM Ponds —BMP Planting

33

MLK Extension – Mainline US-58

slide-16
SLIDE 16

 General Information —200 + Utility Relocations —Water, Sewer, Cox, Dominion, Verizon, Virginia Natural Gas —Modifications to existing 20” water line —Primary water system feeder to downtown Portsmouth —Ground Improvements —Surcharges —Pile Supported Embankments

34

MLK Extension – Mainline US-58

slide-17
SLIDE 17

 I-264 Interchange —New construction of 4 ramps between US-58 and I-264 —Roadway Widening of I-264 EB and WB —Des Moines Avenue overpass —Bridge over N&PBL —ITS Relocation – overhead sign structure replacement

35

MLK Extension – Interchanges

slide-18
SLIDE 18

 I-264 Interchange —Reconstruction of Frederick Blvd off ramp —Permanent closure of Des Moines Exit and South Street on ramp —Pedestrian Bridge Replacement

36

MLK Extension – Interchanges