Barlby Road New Homes Consultation Round 1 Introduction Last year the Council held a series of discussions and workshops with local communities. Feedback from these events identified a number of key priorities, including new homes. The


slide-1
SLIDE 1

Barlby Road New Homes Consultation Round 1

slide-2
SLIDE 2

Introduction

Aims of today:

We want your views about what you would like to see on this site, in

  • rder to help us shape our proposals and ensure that we have

listened to the community. Last year the Council held a series of discussions and workshops with local

  • communities. Feedback from these

events identified a number of key priorities, including new homes. The Council has responded by announcing a programme for delivery of 600 new homes, including a minimum of 300 Council homes for rent. One of the sites that has been identified with potential to build new homes is at Barlby Road.

slide-3
SLIDE 3

First Stage Sites

The ‘First Stage’ sites aim to deliver a proportion of the overall

  • programme. It is proposed that a mix of different types of homes is

delivered including council homes to rent, and open market homes. Grant funding has been secured from the Mayor’s office to assist with the delivery of council homes to rent. One of the four sites, shown below, that have been announced is the Barlby Road site. The aim is to deliver as many council homes to rent as possible to meet the pressing need for genuinely affordable housing.

slide-4
SLIDE 4

Proposed Site

Location Plan: Aerial Photo:

slide-5
SLIDE 5

Background

The Council has previously consulted with you in relation to the new Barlby schools proposals, and also the related improvements and alterations to the adjacent children's playground and ball court area. The new schools are now under construction with a target completion date by early 2021. The land released on the opening of the new schools is indicated approximately in red above. The site has been identified as having potential for the delivery of new homes. We would like to obtain your thoughts before work is commenced on producing proposals for the Barlby Road site.

Indicative Plan of Barlby Road Site.

slide-6
SLIDE 6

New Barlby Schools

View of new Schools from Treverton Street View of new Schools from Treverton Estate Aerial view of new Barlby Schools

slide-7
SLIDE 7

Surroundings

Treverton Estate Local businesses Existing Barlby Primary School

slide-8
SLIDE 8

Initial ideas for new homes

  • n Barlby Road Site
  • New road and pavements to access proposed buildings linking with

Treverton Street.

  • Pedestrian linkage only from Barlby Road to Treverton Street.
  • New council homes to rent which including two and three bed homes as

well as one bed to meet needs in the borough.

  • One and two bed homes for open market rent or sale to support the new

council homes to rent.

  • Improvement and extension of existing community garden.
  • Enhance the landscaping and paving to Treverton Street.
  • Opportunity to provide additional accommodation for existing NHS

dentists on Ladbroke Grove as part of proposals. Tell us what you think on the next boards.

New Schools

Initial ideas for footprint of new homes.

slide-9
SLIDE 9

Ways you can feedback

Feedback form Email us Website Fill this in today at the welcome desk newhomesenquiries@rbkc.gov.uk www.rbkc.gov.uk/new-homes

slide-10
SLIDE 10

What happens next? We will…

  • review your feedback and comments
  • use your comments to prepare

proposals

  • post summary of feedback on

www.rbkc.gov.uk/new-homes

  • share these proposals with you at the

next event in September

Thank you for coming today!

slide-11
SLIDE 11

June

2020 2021 2019

Submit Planning Application Engagement with community Target Build Start

Construction

Indicative timeline for new homes at Barlby Road site

N.B. This timeline is indicative based on target programme for consultation, planning and construction

Design Proposals

2022 2023

Target completion

  • f new

homes