Task Due Month NDR Specifications 7 NDR Version 1 15 NDR Version 1.5 22 Report on NDR operational performance at the end of TOP1 23 NDR Version 2 (Final Version) 35 Report on NDR operational performance at the end of TOP2 36
NDR Manager Duties
Translate user request (via web interface) to OPeNDAP
query
Identify DR that provides requested coverage Send properly formatted request to OPeNDAP server for data
Transfer data to OSM server and initiate computations Collect results from OSM server Perform any required translations, gridding, etc. Send OSM results to web interface for display Cataloging of data
NDR Version 1
Objective
Implementation, testing, and debugging of NDR Manager
software, and modules (if any) for the OpenDAP server Priorities
Fast turnaround on software development Minimize the effect of external factors
Version 1 Workflow
PyDAP
- r
Python + Hyrax WCS FTP/OPeNDAP SSH/(?)
Months 7 to 15 tasks
University of Cyprus
Develop NDR Manager software version 1.0
Test with locally downloaded data.
Advise/assist other partners in installation and configuration of OPeNDAP servers.
Collaborate with web interface developer on data exchange.
OSM Partners
Make OSM results to be compatible with data exchange specifications.
Install and configure OSM server for NDR access
SSH, Python, …
DR Partners
Make DR data to be compatible with data exchange specifications.
Install and configure local OPeNDAP server.
Versions 1.5 & 2 Workflow
DR 1 DR 2 DR n
NDR Version 1.5
Objective
Integration of NDR Manager with remote OPeNDAP servers First TOP
Priorities
Testing of NDR integration
NDR Version 2
Objective
Debugging of issues identified during TOP1 Second TOP
Priorities
Readiness for final deployment
Months 15 to 35 tasks
University of Cyprus
Develop NDR Manager software version 1.5
Test with remote OPeNDAP servers
Advise/assist other partners in operation of remote OPeNDAP servers.
First TOP
Improve version 1.5 based on results on first TOP to produce version 2.0.
OSM Partners
Maintain and operate local OSM server.
DR Partners
Maintain and operate local OPeNDAP server.