NDR Design: Preliminary Progress Report Timeline for NDR Task Due Month NDR Specifications 7 NDR Version 1 15 NDR Version 1.5 22 Report on NDR operational performance at the end of TOP1 23 NDR Version 2 (Final Version) 35 Report on


  1. NDR Design: Preliminary Progress Report

  2. Timeline for NDR Task Due Month NDR Specifications 7 NDR Version 1 15 NDR Version 1.5 22 Report on NDR operational performance at the end of TOP1 23 NDR Version 2 (Final Version) 35 Report on NDR operational performance at the end of TOP2 36

  3. NDR Manager Duties  Translate user request (via web interface) to OPeNDAP query  Identify DR that provides requested coverage  Send properly formatted request to OPeNDAP server for data  Transfer data to OSM server and initiate computations  Collect results from OSM server  Perform any required translations, gridding, etc.  Send OSM results to web interface for display  Cataloging of data

  4. NDR Version 1  Objective  Implementation, testing, and debugging of NDR Manager software, and modules (if any) for the OpenDAP server  Priorities  Fast turnaround on software development  Minimize the effect of external factors

  5. Version 1 Workflow PyDAP FTP/OPeNDAP or Python + Hyrax WCS SSH/(?)

  6. Months 7 to 15 tasks University of Cyprus OSM Partners   Develop NDR Manager Make OSM results to be   software version 1.0 compatible with data exchange specifications. Test with locally downloaded  data. Install and configure OSM  server for NDR access Advise/assist other partners  in installation and SSH, Python, …  configuration of OPeNDAP DR Partners servers.  Make DR data to be Collaborate with web   compatible with data interface developer on data exchange specifications. exchange. Install and configure local  OPeNDAP server.

  7. Versions 1.5 & 2 Workflow DR 1 DR 2 DR n

  8. NDR Version 1.5  Objective  Integration of NDR Manager with remote OPeNDAP servers  First TOP  Priorities  Testing of NDR integration

  9. NDR Version 2  Objective  Debugging of issues identified during TOP1  Second TOP  Priorities  Readiness for final deployment

  10. Months 15 to 35 tasks University of Cyprus OSM Partners   Develop NDR Manager Maintain and operate local   software version 1.5 OSM server. Test with remote OPeNDAP  DR Partners  servers Maintain and operate local  Advise/assist other partners  OPeNDAP server. in operation of remote OPeNDAP servers. First TOP  Improve version 1.5 based on  results on first TOP to produce version 2.0.

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.