DU DUNDEE DEE PRECIOUS METALS INC. . TSX - DPM Namibia Custom Smelters www.dundeeprecious.com The Transaction Chelopech concentrate to NCS since 2007 Smelter uniquely positioned and engineered to accept chelo con Recognised


slide-1
SLIDE 1

Namibia Custom Smelters

DU DUNDEE DEE

PRECIOUS METALS INC.. TSX - DPM www.dundeeprecious.com

slide-2
SLIDE 2

The Transaction

DUNDEE

PRECIOUS METALS INC.

  • Chelopech concentrate to NCS since

2007

  • Smelter uniquely positioned and

engineered to accept chelo con

  • Recognised potential risks to Chelopech

while smelter not in DPM ownership

  • Smelter acquired March 24, 2010
  • $33M cash and shares and settled $17M

in third party obligations

  • Secures Chelopech future with respect to

concentrate processing

slide-3
SLIDE 3

The Operation

DUNDEE

PRECIOUS METALS INC.

  • Combined Ausmelt and Reverb furnace technology
  • 3 Pierce Smith Convertors
  • Supplementary oxygen added to Ausmelt
  • Significant potential capacity in Ausmelt with more
  • xygen
  • Off-gas cooling and capture of dust and particulate

metals

  • Blister copper product shipped to European refineries
  • Arsenic trioxide by-product manufacturing plant
  • As2O3 shipped to SA and SE Asia
slide-4
SLIDE 4

The Operation

DUNDEE

PRECIOUS METALS INC.

  • 190 tpd oxygen plant
  • Waste heat power generation plus connection to national

grid

  • Slag mill for slag recovery of metal in slag
  • Licensed best practice hazardous waste disposal facility
  • Ownership of historic tailings and smelter wastes

– Govt. granted legal limitation of historic liability – Rehabilitation work started – Some potential opportunity in residual metal values?

  • Namibian infrastructure generally good
slide-5
SLIDE 5

Production and Capex

DUNDEE

PRECIOUS METALS INC.

  • 36,000 tonnes primary concentrate processed Q3 2010

(inc. 17k Chelo)

  • Capex YTD USD 5M
  • Expected 2010 Capex USD 8M
  • Expected Capex 2011 USD 20M
slide-6
SLIDE 6

2010 Focus

DUNDEE

PRECIOUS METALS INC.

  • Under previous ownership

– Facility undercapitalized – Deferred maintenance and environmental controls upgrade – Social license to operate somewhat neglected

  • 2010 activity since DPM acquisition

– Improved community and government relationships – Increased focus on safety, health, environment – Capital into maintenance and urgent environmental improvements

  • materials handling
  • gas cooling (additional gas coolers)
  • dust capture (ongoing bag house upgrades)
  • Haz waste site

– Additional resources applied in operations management and projects – ESIA in preparation – Develop future strategy and project plan

slide-7
SLIDE 7

Future Focus 2011/2012

DUNDEE

PRECIOUS METALS INC.

  • Secure the future
  • Implement “project” strategy to meet production and HSE

targets

  • Best Practice controls on particulate emissions
  • Reduced fugitive emissions
  • Increased environmental surveillance and management
  • Take commercial opportunities and address any risks
  • Reduce costs and incrementally improve availability and

reliability

  • Increase reliance on Ausmelt technology
  • Complete sulfur capture and acid production study
  • Further improvements in community engagement