Multidisciplinary Senior Design (MSDI)
P18718: Preliminary Detailed Design Review
Nick Campagnola Matt Eisner Ryan Leeson Kyle Leung Alec Meta
Multidisciplinary Senior Design (MSDI) P18718: Preliminary Detailed - - PowerPoint PPT Presentation
Multidisciplinary Senior Design (MSDI) P18718: Preliminary Detailed Design Review Nick Campagnola Matt Eisner Ryan Leeson Kyle Leung Alec Meta Agenda Background Problem Statement Engineering/Customer Requirements Review
Multidisciplinary Senior Design (MSDI)
P18718: Preliminary Detailed Design Review
Nick Campagnola Matt Eisner Ryan Leeson Kyle Leung Alec Meta
○ Problem Statement ○ Engineering/Customer Requirements Review
○ Engineering Checklist ○ Change-Over Breakdown ○ 8 Wastes Identification ○ Fishbone Diagram
○ Test Plans ○ Risk Assessment Update ○ Project Plan
their production operations.
○ The first is a Dial Operation, the second is a Spooler Operation, and the final is a Packaging Operation.
reducing the setup times of the various processes and eliminating wastes.
○ Any reduction in setup time or identified wastes is considered a success. ○ Any additional changes to improve the department's processes is a plus.
Engineering Requirements Review
Engineering/Customer Requirements Review
1. T - Transportation 2. I - Inventory 3. M - Motion 4. W - Waiting 5. O - Over Processing 6. O - Overproduction 7. D - Defects 8. S - Skills
production area.
designated location.
placement of needed materials. ○ If the materials were placed closer to where they have to be used, it could reduce time spent moving to gather them.
ensure they are ready to receive new order.
various operations.
table into place during changeover. Two different people both did the same job unaware it had already been completed.
to process (blue jackets).
needed amount. ○ Not sure if it is for compensation of previous low periods, or if production numbers are always higher than necessary.
completing changeover procedures. ○ Possibly have the non-Kodak workers do changeovers ○ Make changeover easier to do
product/ process
non-Kodak employees ○ Color coding plugs more ○ Alignment arrows on plugs ○ Taping the floor for specific placement of equipment
Questions?