MUDDY RIVER FLOOD RISK MANAGEMENT PHASE II Jennifer Flanagan - - PowerPoint PPT Presentation

muddy river flood risk management phase ii
SMART_READER_LITE
LIVE PREVIEW

MUDDY RIVER FLOOD RISK MANAGEMENT PHASE II Jennifer Flanagan - - PowerPoint PPT Presentation

MUDDY RIVER FLOOD RISK MANAGEMENT PHASE II Jennifer Flanagan Project Manager New England District/PPMD Date: 30 June 2020 2 MUDDY RIVER THE HEART OF OLMSTED PARK 1894 The park was designed by Fredrick Law Olmsted & completed


slide-1
SLIDE 1

MUDDY RIVER FLOOD RISK MANAGEMENT – PHASE II

Jennifer Flanagan Project Manager New England District/PPMD Date: 30 June 2020

slide-2
SLIDE 2

2

MUDDY RIVER THE HEART OF OLMSTED PARK

  • The park was designed by Fredrick Law Olmsted &

completed in the 1890’s

  • Olmsted designed some of America’s greatest city parks
  • “The Necklace” is the oldest remaining linear park in the

United States

1894

Images from http://www.muddyrivermmoc.org/restoring-olmsteds-vision/

slide-3
SLIDE 3

3

MUDDY RIVER – 1996 FLOODING

Boston received 10.8 inches of rain A month’s worth in one day

  • Extensive damage to MBTA in

Kenmore Square

  • Over $60M in damages to MBTA
slide-4
SLIDE 4

4

MUDDY RIVER – ADDITIONAL FLOODING EVENTS

  • June 1998, March 2001, March 2010 (6” over 2 days with water levels 2.5 feet

higher than normal)

slide-5
SLIDE 5

5

MUDDY RIVER – COMPREHENSIVE PLAN

  • A comprehensive plan was developed to

address

  • Flooding
  • Accumulated sediment
  • Reduced aquatic habitat quality (high

SOD, low DO)

  • Contaminated sediments (metals,

PCBs, PAHs)

  • Invasive species (Phragmites)

impacting biodiversity & reduction of

  • pen water
  • Corps completed Decision Document

and Environmental Assessment

  • Muddy River Flood Control and

Ecosystem Restoration, September 2003

Sedimentation Flooding

  • Undersized culverts
  • Restrictions
slide-6
SLIDE 6

6

MUDDY RIVER – COMPREHENSIVE PLAN

  • Decision Document approved

– Director’s Report December 2003

  • Review by ASA office – costs
  • f ecosystem restoration

features are prohibitive on a per acre basis.

  • OMB concurs with ASA

recommendation NOT to fund ecosystem restoration components.

Recommended Plan

slide-7
SLIDE 7

7

MUDDY RIVER – FLOOD RISK MANAGEMENT PLAN

slide-8
SLIDE 8

8

2001 2019

slide-9
SLIDE 9

9

  • Looking upstream from new UFP culvert
slide-10
SLIDE 10

10

MUDDY RIVER – PHASE 2

Work Areas 1 – 12

EXCAVATION

  • Excavate the sandbar and island at

Leverett Pond

  • Excavate five stretches of areas of

constriction in the Riverway section of the river

  • Excavate the river in the Back Bay

Fens area to create a continuous channel

  • Excavate deepened channel sections

to delay need for maintenance dredging

slide-11
SLIDE 11

11

MUDDY RIVER – PHASE 2

Work Areas 13

  • Provide additional flood proofing at the Boston Fire Department

Building in the Back Bay Fens.

slide-12
SLIDE 12

12

PHASE 2 WHAT TO EXPECT – DURING CONSTUCTION

In the Wet Construction

https://www.youtube.com/watch?v=nXN__c_dwVI

Barge Mounted Excavator Long Reach Excavator

In the Dry Construction

slide-13
SLIDE 13

13

PHASE 2 WHAT TO EXPECT – DURING CONSTUCTION

Stockpile, Direct Loading & Transport

slide-14
SLIDE 14

14

PHASE 2 WHAT TO EXPECT – DURING CONSTUCTION

Tree Protection – Critical Element of Work

slide-15
SLIDE 15

15

PHASE 2 WHAT TO EXPECT – DURING CONSTUCTION

Some Tree Removal

Work Area 2 – the river on both banks have lots of vegetation and trees. These various trees need to be removed for access as well as the new channel slope will cut into the existing tree root system. Work Area 7 – both trees are within area of phragmites to be excavated 18” deep. Concern for the tree root system and trees are not healthy.

slide-16
SLIDE 16

16

MUDDY RIVER – PHASE 2 – RESTORATION EFFORTS

  • Remove Phragmites in the Back Bay Fens and Riverway areas where necessary to create flood risk management channel

and provide ancillary benefits of ecological habitat improvements.

  • Restore wetland vegetation in dredged areas by seeding or planting appropriate wet meadow and emergent wetland plants.
  • Restore riparian vegetation in upland areas where Phragmites or oriental knotweed are removed by planting grass, trees,

and shrubs.

slide-17
SLIDE 17

17

MUDDY RIVER – PHASE 2 – RESTORATION EFFORTS

  • Work Area #6:
  • Wetland shelves
  • Wet meadow
  • Trees
  • Shrubs
  • Restored lawn
slide-18
SLIDE 18

18

PHASE 2 WHAT TO EXPECT – AFTER COMPLETION

Primary Project Goal

  • Improved water

conveyance

  • Charles River will still strongly

influence the Muddy River water level

  • Water will move through the

system faster

  • Designed for 20-year’ storm
slide-19
SLIDE 19

19

PHASE 2 WHAT TO EXPECT – AFTER COMPLETION

Ancillary Project Benefit - Restored River Bank

  • Stabilized river bank

reducing erosion and improving water clarity

  • Removal of poor quality

sediment

  • Increased aquatic habitat

quantity and quality

  • Increased plant diversity
  • Partial restoration of

Olmsted’s vision

slide-20
SLIDE 20

20

Contact

Wendy Gendron, Civil Works Program Manager wendy.c.gendron@usace.army.mil Jennifer Flanagan, Project Manager jennifer.w.flanagan@usace.army.mil