muddy river flood damage reduction phase 2
play

Muddy River Flood Damage Reduction Phase 2 Summer 2020 Construction - PowerPoint PPT Presentation

June 30, 2020 Muddy River Flood Damage Reduction Phase 2 Summer 2020 Construction Preview Presentation Agenda Project Overview Key Project Personnel Charter Contracting Company LLC Project Site Area Layout Public Detours


  1. June 30, 2020 Muddy River Flood Damage Reduction Phase 2 Summer 2020 Construction Preview

  2. Presentation Agenda ➢ Project Overview ➢ Key Project Personnel – Charter Contracting Company LLC ➢ Project Site Area Layout – Public Detours • Pedestrian and Traffic Detours ➢ Schedule Overview for 2020 • Fencing • Tree Removal • Access • Excavation June 2020

  3. Project Overview ➢ 13 Work Areas – From Leverett Pond to Boylston Street Bridge • Areas 1 – 12 includes 90,000CY of sediment removal • Areas 1, 2, 4, & 6- 12 Excavate “In -the- Wet” – Allow free flow conditions at all times • Areas 3 & 5 – Excavate “In -the- Dry” – Divert river using natural topography, and allow free flow conditions at all times • Charter’s approach disturbs 1,409SF less wetlands than originally contemplated during the project design phase • Area 13 includes flood protection wall at Boston Fire Department Fire Control Center • Eradicate phragmites in Backbay Fens and Riverway areas • Plant emergent wetland/upland plants, shrubs and trees • Installing wildlife habitats • Protection of existing vegetation and trees is high priority June 2020

  4. Key Project Personnel ➢ Key Project Personnel – Charter Contracting Company LLC • Project Manager – Kyle Merkosky • Clarkson University • 14 Years Experience in the Heavy Civil and Environmental Construction Field • Site Superintendent – Matthew Sweeney • Northeastern University • 29 Years Experience in the Heavy Civil and Environmental Construction Field • Assistant Project Manager & Environmental Monitor – Shane Gray • Northeastern University • 8 Years of Experience in the Environmental Construction Field • Site Safety and Health Officer – Timothy Bullock • 30+ Years of Experience in the Construction Industry, 19 of those years as an SSHO • Quality Control System Manager – Kevin Hallion • Wentworth Institute of Technology • 14 Years of Experience in the Construction Industry June 2020

  5. Area 1 – Site Layout & Detours • A Temporary Path will be created to provide access to pedestrian traffic • A flagger will be present at the vehicle gate when construction traffic is active for safety. • Signage on pedestrian walkways will be present to direct foot traffic. • The southern side of the parking area will remain accessible for vehicles. June 2020

  6. Area 2 – Site Layout & Detours • A flagger will be present at the vehicle gate when construction traffic is active for safety. • Signage on pedestrian walkways will be present to direct foot traffic. • Pedestrian access will be maintained along the currently active pathway June 2020

  7. Area 3 – Site Layout & Detours • A flagger will be present at the vehicle gate(s) when construction traffic is active for safety. • Signage on pedestrian walkways will be present to direct foot traffic. • Foot traffic will be diverted from the Boston side of the River to the Brookline side of the river for safety and to allow construction vehicle access. June 2020

  8. Area 4 – Site Layout & Detours • A flagger will be present at the vehicle gate when construction traffic is active for safety. • Signage on pedestrian walkways will be present to direct foot traffic. • A Temporary Path will be created to provide access to pedestrian traffic June 2020

  9. Area 5 – Site Layout & Detours • Signage on pedestrian walkways will be present to direct foot traffic. • Foot traffic will be diverted from the Boston side of the River to the Brookline side of the river for safety and to allow construction vehicle access. June 2020

  10. Area 6 – Site Layout & Detours • A flagger will be present at the vehicle gate(s) when construction traffic is active for safety. • A Temporary Path will be created to provide access to pedestrian traffic • Signage on pedestrian walkways will be present to direct foot traffic. • Foot traffic will be diverted from the Boston side of the River to the Brookline side of the river for safety and to allow construction vehicle access. June 2020

  11. Area 7 – Site Layout & Detours • Signage on pedestrian walkways will be present to direct foot traffic. • The current pathway closest to the river will be utilized as a construction vehicle access road and will not be open to foot traffic June 2020

  12. Area 8 – Site Layout & Detours • Signage on pedestrian walkways will be present to direct foot traffic. • The current pathway closest to the river will be utilized as a construction vehicle access road and will not be open to foot traffic • A flagger will be present at the vehicle gate(s) when construction traffic is active for safety near Louis Prang St intersection. Anticipated use is minimal. June 2020

  13. Area 9 – Site Layout & Detours • Signage on pedestrian walkways will be present to direct foot traffic. • The current pathway closest to the river will be utilized as a construction vehicle access road and will not be open to foot traffic • A flagger will be present at the Clement Field bridge when construction traffic is active in Areas 7 & 8. At this time all foot traffic will be diverted from the War Memorial bridge to allow safe passage at 1 location. June 2020

  14. Area 10 – Site Layout & Detours • Signage on pedestrian walkways will be present to direct foot traffic. • The current pathway closest to the river will be utilized as a construction vehicle access road and will not be open to foot traffic • A flagger will be present at the War Memorial bridge when construction traffic is active in Area 9. • At this time the Clement Field Bridge will be open without limitations June 2020

  15. Area 11 – Site Layout & Detours • Signage on pedestrian walkways will be present to direct foot traffic. • The Northern sidewalk on Agassiz Rd will be closed for the duration of the project, the Southern sidewalk will remain open for pedestrians. • A flagger will be present at Agassiz Rd Vehicle Gates when Construction truck traffic is active • Agassiz Rd will be closed to public vehicle traffic during the day once excavation begins and as needed during project site setup. June 2020

  16. Area 12 – Site Layout & Detours • Signage on pedestrian walkways will be present to direct foot traffic. • Pedestrian and Emergency Vehicle access will be maintained adjacent to the Victory Gardens. • A flagger will be present at the vehicle gate(s) when construction traffic is active for safety. June 2020

  17. Total Wetland Impact Summary June 2020

  18. Schedule Overview – 2020 into 2021 ➢ General Sequencing July 2020 ➢ • Areas 1 -6 will be completed stages with multiple crews • Site Mobilization and Staging Area Setup • Example: While Charter is excavating in Area 2, • Tree Clearing Areas 1 – 12 - Approved Trees Charter will be preparing/setting up Area 3 and larger than 4”, grubbing will occur after fence is in place in each area, prior to or Landscaping in Area 1 creating a “train”. Upon during excavation. completion of Excavation in Area 2 the “train” will • Fence Area 1 move up to the next work area. • Temporary Fence will be taken down in each area • Fence Areas 7 – 11 – South of Victory Gardens as restoration is complete. On going maintenance will occur for 2 years after completion of each October 2020 ➢ area. • Fence Areas 2 & 11 • Completion in Areas 1 through 6 is expected by the • Excavation of Areas 1 and 7 end of 2021 – less landscaping due to timing and January 2021 planting windows. ➢ • Areas 7-13 are continuous and mostly will be occupied • Fence Areas 3 & 4 from 2020 until 2023. Same as Areas 1-6, temporary March 2021 ➢ fence will be removed from Areas 7-13 to the greatest • Fence Areas 5, 6, 12 & 13 extent possible as areas are complete to minimize impacts to the public. • Operations in Areas 1-6 will happen concurrently with *Dates are subject to change Areas 7-13 June 2020

  19. Summer 2020 Construction Preview Questions?

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend