Mt. Rainier Affordable Housing Group University of Washington - - PowerPoint PPT Presentation

mt rainier affordable housing group university of
SMART_READER_LITE
LIVE PREVIEW

Mt. Rainier Affordable Housing Group University of Washington - - PowerPoint PPT Presentation

Mt. Rainier Affordable Housing Group University of Washington Project Goals Provide affordable family housing Encourage equitable transit-oriented development Explore how to achieve cost efficiencies Rainier Beach, Seattle Rainier


slide-1
SLIDE 1
  • Mt. Rainier Affordable Housing Group

University of Washington

slide-2
SLIDE 2

Project Goals

  • Provide affordable family housing
  • Encourage equitable transit-oriented

development

  • Explore how to achieve cost efficiencies
slide-3
SLIDE 3

Rainier Beach, Seattle

slide-4
SLIDE 4

Rainier Beach Demographics

3+ People 38%

Family Size

Earn Below 40% AMI 29%

Household Income

Rent Burden ed 83%

Rent Burden of Families

slide-5
SLIDE 5

4849 Henderson: The Site

Rainier Beach Community Center

Link Light Rail

slide-6
SLIDE 6

Design

slide-7
SLIDE 7

Advantages of Modular Construction

  • Controllable Costs
  • Consistent and replicable quality
  • Labor savings
  • Reduces schedule from eleven to eight

months

slide-8
SLIDE 8

Modular Construction Costs

40,000 Apartments in pipeline Modular costs holding as traditional costs rise in Seattle

Modular ¡Costs ¡ Tradi.onal ¡Costs ¡

TODAY ¡

slide-9
SLIDE 9

Creating Scalable Seattle Solution

  • Allows for buildings on

narrow infill lots typical in Seattle

  • Makes staging of materials

easier

  • Less impacts on community

¡ ¡

slide-10
SLIDE 10

Funding Resources

slide-11
SLIDE 11

Providing 8 HUD Subsidized Units = $67,306 additional income for services

slide-12
SLIDE 12

Development Timeline

Construction

5/2014 4/2017

Permitting

Predevelopment Loan (7/2014) Permits (10/2015)

Financing

1st Application (1/2015) Closing (2/2016) Construction starts (5/2016) Construction completes (1/2017)