K A R A C H I T R A N S P O R T I M P R O V E M E N T P R O J E C T
IN THE NAME OF ALMIGHTY ALLAH, THE MOST BENEFICENT, THE MOST MERCIFUL
MOST BENEFICENT, THE MOST MERCIFUL K A R A C H I T R A N S P O R T - - PowerPoint PPT Presentation
IN THE NAME OF ALMIGHTY ALLAH, THE MOST BENEFICENT, THE MOST MERCIFUL K A R A C H I T R A N S P O R T I M P R O V E M E N T P R O J E C T GREEN LINE BUS RAPID TRANSIT SYSTEM (Updated as of 16 th August, 2016) (From KESC Power House Surjani
K A R A C H I T R A N S P O R T I M P R O V E M E N T P R O J E C T
IN THE NAME OF ALMIGHTY ALLAH, THE MOST BENEFICENT, THE MOST MERCIFUL
GREEN LINE BUS RAPID TRANSIT SYSTEM (Updated as of 16th August, 2016)
(From KESC Power House Surjani Town To Municipal Park + CBD Extension M.A. Jinnah Road)
K A R A C H I T R A N S P O R T I M P R O V E M E N T P R O J E C T
K A R A C H I T R A N S P O R T I M P R O V E M E N T P R O J E C T
GROWTH IN URBAN TRANSPORT DEMAND
POPULATION INCREASES
GEOGRAPHICAL DECONCENTRATION AVAILABILITY OF MOTORIZED TRANSPORT INCREASES IN HOUSE HOLD INCOME INCREASES IN COMMMERCIAL AND INDUSTRIAL ACTIVITY
Karachi and Urban Resilience
economic, social and environmental change(s)
– Population – Lack of Integrated Planning – Non Inclusive Growth – Pollution – Encroachment – Enforcement – Irregular Development
K A R A C H I T R A N S P O R T I M P R O V E M E N T P R O J E C T
1982 TRANSPORT COMMISSION (Justice Ajmal Mian)
COMMITTEE NO.1 SHORT TERM AND LONG TERM COMMITTEE NO.2 TRAFFIC SAFETY AND PREVENTION SPECIAL COMMITTEE CONSTITUTION OF METROPOLITAN TRANSPORT AUTHORITY
TRANSPORT PLANS
KARACHI TRANSPORT (MERZ RENDELL) 1951 – 52 KDA MASTER PLAN 1974 – 1985 RAPID TRANSIT CELL MASS TRANSIT SYSTEM PLAN 1977 COMMISSION OF ENQUIRY IN KARACHI AFFAIRS (MASOOD UZ ZAMAN) 1985 KARACHI MASS TRANSIT PLAN 1990 KARACHI MASTER PLAN 2020 2005 KARACHI TRANSPORT IMPROVEMENT PLAN 2013
Background
6
Vehicles carry 42% of Total Persons Traveling in the City.
Vehicular Traffic carries only 21% of
Occupancy.
there is still deficiency of Public Transport availability on all Major Routes in the city.
Existing Public Transport System
5 10 15 20 25 30 35 40
Population (Millions)
Karachi Now Karachi in 2030
composition of Public Transport Vehicles carry 42% of Total Passengers
are36.5% of Total Vehicular Traffic carries
Passengers.
Mansehra Colony Tower Mauripur Gulbai Shershah Board Office Municipal Park Regal Chowk Model Colony Numaish Nagan Chowrangi
UNIVERSITY ROAD UNIVERSITY ROADPlanned BRTS Corridors - KTIP
(Karachi Transportation Improvement Project)
Mansehra Colony Singer Chowrangi Maymar More Tower Mauripur Gulbai Shershah Nishan-e-Haider Chowk Board Office Surjani Municipal Park Regal Chowk Model Colony Numaish Nagan Chowrangi
Yellow Line
GoS - Public Private Partnership Model Bid Submitted by Dec 18, 2014 Construction may start by Jan,2016
Blue Line
By a Private Developer In Detail Design Stage Construction may start by 2016
Red Line
Under discussion with ADB
Green Line
21.7 km to be executed by KIDCL under Ministry
Orange Line
To be executed by Government of Sind
M10 / RCD Highway Junction
Green line Blue line Red line Yellow line Merging Point
K A R A C H I T R A N S P O R T I M P R O V E M E N T P R O J E C T
Green Line BRTS
Company Ltd. (KIDCL)
with Stations and Depot (Infrastructure)
KESC Power House, Surjani Town.
M.A Jinnah Road
Approved by ECNEC @ Rs. 16,085.1 M under the Prime Minister’s Initiaitive.
Board of Directors, KIDCL
K A R A C H I T R A N S P O R T I M P R O V E M E N T P R O J E C T
Objectives of Green Line
Service,
manner with exclusive right-of-way for a significant portion of their route length, and
transport mode.
K A R A C H I T R A N S P O R T I M P R O V E M E N T P R O J E C T
Elevated Rail Underground
K A R A C H I T R A N S P O R T I M P R O V E M E N T P R O J E C T
Peak throughput (passengers/hr/direction)
12,000
System passenger-trips per day 300,000 Highest peak hour boarding & alighting at a single station 4,500 Highest full-day boarding at a single station 50,000 Location of busway lanes
Centre of Roadway
Number of BRT stations 25 Number of corridors 1 Number of BRT terminals 2 Number of BRT depot 1 Total length of dedicated busway (Up to Municipal Park) 21.7 km Length including mixed traffic portions 0 km Average distance between stations 800 m Signal Priority or Grade Separation at Interchange Grade Separation
Salient Features Green Line BRTS
BRT GREEN LINE
Corridor Length 21.70 km Elevated 11.70 km At grade 10.00 km
Project Start Congested Corridor
Nagan Chowrangi UP Mor Intersection Road 2400 Power House Chowrangi Road 4200 Two Minute Chowrangi Surjani Chowrangi KDA Chowrangi Surjani Town KESC Power House Karimi ChowrangiLegend
At Grade Elevated Station
CONTRACT PACKAGE# KAR/BRTS/GL/01
LOCATION FROM NAZIMABAD CHOWRANGI TO GURU MANDIR CONTRACTOR CRFG-MATRACON JOINT VENTURE CONTRACT VALUE 1845.43 MILLION DATE OF START JANUARY 28TH 2016 PROJECT LENGTH ELEVATED RAMP AT GRADE 2510 M 562 M 374 M
(CIVIL WORKS ONLY)
4 NOS
TOTAL COMPLETED REMAINING REMARKS PILE LOAD TEST 02 DONE Completed PILES 436 349 87 IN PROGRESS PILES CAP 86 52 34 IN PROGRESS PIER SHAFT 82 10 72 IN PROGRESS GIRDER 206 7 199 IN PROGRESS ABUTMENTS 4 1 POUR 3 IN PROGRESS
CONTRACT PACKAGE# KAR/BRTS/GL/02
LOCATION FROM NAGAN CHOWRANGI TO NAZIMABAD CHOWRANGI CONTRACTOR
M/S. CH. A. LATIF & SONS PVT. LIMITED
CONTRACT VALUE 1084.717 MILLION DATE OF START
MARCH 25TH 2016
PROJECT LENGTH ELEVATED RAMP AT GRADE
930 M 1023 M 5797 M
(CIVIL WORKS ONLY)
7 NOS
TOTAL COMPLETED REMAINING REMARKS PILE LOAD TEST 03 3 DONE PILES 160 160 DONE PILES CAP 34 34 IN PROGRESS PIER SHAFT 28 21 7 IN PROGRESS ABUTMENT 6 4 2 IN PROGRESS TRANSOMS 28 8 20 IN PROGRESS GIRDER FORM WORK IS IN PROGRESS
CONTRACT PACKAGE# KAR/BRTS/GL/03
LOCATION
CONSTRUCTION OF BOARD OFFICE INTERCHANGE
CONTRACTOR
M/S AGHA CONSTRUCTION COMPANY
CONTRACT VALUE
785.867 MILLION
DATE OF START
MARCH 5TH , 2016
PROJECT LENGTH ELEVATED RAMP 314.25 M 625 M
(CIVIL WORKS ONLY)
NONE
TOTAL COMPLETED REMAINING REMARKS PILE LOAD TEST 01 DONE Completed PILES 128 118 10 IN PROGRESS PILES CAP 17 13 4 IN PROGRESS PIER SHAFT & TRANSOM 24 14 10 IN PROGRESS ABUTMENTS 3 3 Completed GIRDER CAST IN PLACE
CONTRACT PACKAGE# KAR/BRTS/GL/UT-01
LOCATION
CONSTRUCTION OF WATER TRUNK (DIA1200MM FROM NAGAN CHOWRANGI TO SAKHI HASAN & RELOCATION OF PUMPING STATION NEAR KDA CHOWRANGI.
CONTRACTOR
M/S. MUHAMMAD HASNI BUILDER
CONTRACT VALUE
145.70 MILLION
DATE OF START
DECEMBER 03RD 2015
PROJECT LENGTH 2100 M
K A R A C H I T R A N S P O R T I M P R O V E M E N T P R O J E C T
Functions of Depot
K A R A C H I T R A N S P O R T I M P R O V E M E N T P R O J E C T
ITS
– Maximize commuter transit – Provide secure reliable & cost effective BRT – How ITS makes it possible
29
Integrated Intelligent Transportation System All Lines (KTIP)
Feasibility & Technical Study
Development of RFP: (Green & Orange) a) Technical Documents b) BOQs c) Specifications d) Cost Estimates e) Concessions
Procurement of IITS Design-Built Vendor
Data Communication Highway AVM / Fleet Management Central Command & Control Automatic Fare Collection (AFC) Passenger Information System Security & Surveillance Bus Depot and Bus Docking System
Assist Green & Orange Lines during Civil Infrastructure
Financial Integration Legal Integration and Enabling Laws Supervision Services
Environment & Landscape
construction phase.
Monitoring Consultant for HSE & EIA Compliance
Plantation (7,321 being removed / 19,500 Re-planted)
Offices
LANDSAPE STRATEGY BRT ROUTE IS LOCATED ALONG THE MEDIAN FROM GURUMANDIR TO POWERHOUSE , 22 KM
PLANTED AS COMPENSATORY PLANTING
ENVIROMENT FRIENDLY
TRANSPORT SYSTEM IN PAKISTAN TRANSPLANTATION OF TREES OF THIS SCALE IS GOING TO TAKE PLACE
SITE PLAN BRT ROUTE
TRANSPLANTATION DEMO
LIGNUM VITAE AZADIRACHTA INDICA 4.TRANSPLANTED 2.PRUNE,SECURE AND LIFT
3.TRANSPORT TO NEW SITE TRANSPLANTED
PROPOSED TREES
ALLISTONIA SCHOLARIS CASSIA FISTULA CRATEVA RELIGIOSA LIGNUM VITAE DELONIX REGIA ADDITION OF LOCAL TREES WILL REVIVE THE STREET CHARACTER THAT WAS ONCE PREVALENT IN KARACHI AZADIRACHTA INDICA
Linkages with Civil Society, Architects & Stakeholders
S TAT I O N T Y P E S
K A R A C H I T R A N S P O R T I M P R O V E M E N T P R O J E C T
GOALS AND OBJECTIVES
SITE ELEMENTS, INCLUDING LIGHTING, RAILINGS, SIGNAGE, FURNITURE ETC.
SENIOR CITIZENS
FINDING & REAL-TIME ARRIVAL INFORMATION
FLOOR HEIGHT AND USING PRECISION DOCKING
REFURBISH; BE PROVEN VANDAL-RESISTANT;
GL-02 AT GRADE STATIONS; (Station Count = 07)
STATION TYPES
GL-04 ELEVATED STATIONS; (Station Count = 10)
TYPICAL STATIONS
STATION TYPES – TOTAL 21 STATIONS (18.4Kms
Corridor)
GL-01 ELEVATED STATIONS; (Station Count = 04)
PROPOSAL 1
PROPOSAL 1
PROPOSAL
PROPOSAL
K A R A C H I T R A N S P O R T I M P R O V E M E N T P R O J E C T
EA Consulting