Montano De El Dorado Phase I and II Master Plan Draft EIR El Dorado County Planning Commission Meeting June 25, 2020 20-0786 E 1 of 19 Overview of Presentation Provide an overview of the proposed Montano De El Dorado Phase I and II Master


  1. Montano De El Dorado Phase I and II Master Plan Draft EIR El Dorado County Planning Commission Meeting June 25, 2020 20-0786 E 1 of 19

  2. Overview of Presentation Provide an overview of the proposed Montano De El Dorado Phase I and II Master Plan and its environmental review process Summary of Draft Environmental Impact Report (EIR) Receive comments on the adequacy of the Draft EIR No consideration or action on the project will occur at today’s meeting. Draft EIR Presentation 2 20-0786 E 2 of 19

  3. Overview of Montano De EL Dorado Phase I and II Master Plan Draft EIR Presentation 3 20-0786 E 3 of 19

  4. Project Site and Existing Conditions Located at the southeast corner of the Latrobe Road and White Rock Road Intersection Montano De El Dorado Phase I is developed and consists of 68,500 square feet of commercial uses Phase II (16.8 acres) would be located south of Phase I and is zoned Regional Commercial Footer Text Here 4 20-0786 E 4 of 19

  5. Proposed Development 10 commercial and office buildings consisting of approximately 75,400 square feet in Phase II (143,900 total square feet for entire Montano De El Dorado Center) Building/architectural feature heights ranging from 24 to 70 feet above finished grade On-site amphitheater New signalized intersection for new project driveway on Latrobe Road Wall/landscape treatments to buffer from existing residents Off-site wastewater improvements Draft EIR Presentation 5 20-0786 E 5 of 19

  6. Site Plan Footer Text Here 6 20-0786 E 6 of 19

  7. Architectural Renderings Draft EIR Presentation 7 20-0786 E 7 of 19

  8. Architectural Renderings Draft EIR Presentation 8 20-0786 E 8 of 19

  9. Proposed Entitlements Rezone to Regional Commercial-Planned Development Commercial Tentative Parcel Map to create 12 lots Planned Development Permit Conditional Use Permit for outdoor special events in Phase I and Phase II and office uses Draft EIR Presentation 9 20-0786 E 9 of 19

  10. Environmental Review Process Draft EIR Presentation 10 20-0786 E 10 of 19

  11. What is CEQA? California Environmental Quality Act (CEQA) Public disclosure process Public participation is essential Avoid or mitigate for environmental impacts Certification of EIR does not indicate approval of project Draft EIR Presentation 11 20-0786 E 11 of 19

  12. What is an EIR? An informational document • Discloses information about the effects a proposed project could have on the environment • Identifies mitigation measures • Describes feasible alternatives to the proposed project • Provides opportunity for public comment  Must be certified prior to project approval Draft EIR Presentation 12 20-0786 E 12 of 19

  13. What is an EIR? (cont.) What an EIR Does… Analyzes the environmental effects of the project Discloses information about the effects a project could have on the environment Identifies mitigation measures Describes feasible alternatives to the proposed project Solicits agency and public input throughout process Draft EIR Presentation 13 20-0786 E 13 of 19

  14. What is an EIR? (cont.) What an EIR Does Not Do… Does not require mitigation for existing environmental conditions Does not advocate for the project under evaluation Does not require project denial due to significant environmental impacts Does not address economic and social issues (e.g., property values) Draft EIR Presentation 14 20-0786 E 14 of 19

  15. Environmental Issues Evaluated in the Draft EIR Aesthetics Hazards and Hazardous Materials Air Quality Hydrology/Water Quality Biological Resources Land Use and Planning Cultural and Tribal Cultural Resources Noise and Vibration Energy Public Services Geology and Soils Traffic and Circulation Greenhouse Gases Utilities and Service Systems Cumulative Impacts Draft EIR Presentation 15 20-0786 E 15 of 19

  16. Significant and Unavoidable Impacts in the Draft EIR Construction noise (Impact 3.10-1) Construction vibration (Impact 3.10-2) Increases in vehicle miles traveled under project conditions (Impact 3.12-1) Increases in vehicle miles traveled under cumulative conditions (Impact 4-14) Draft EIR Presentation 16 20-0786 E 16 of 19

  17. Alternatives Considered in the Draft EIR Alternative 1: No Project – No Development Alternative Alternative 2: Modification of Special Events Alternative Alternative 3: Reduced Development Alternative Draft EIR Presentation 17 20-0786 E 17 of 19

  18. Submittal of Comments on the Draft EIR Direct Written Comments to: El Dorado County Planning and Building Department Planning Division Attn: Tom Purciel 2850 Fairlane Court Placerville, CA 95667 Or e-mail to: montano@edcgov.us Draft EIR comment period ends on Monday July 13, 2020 at 5:00 p.m. Draft EIR Presentation 18 20-0786 E 18 of 19

  19. Next Steps in Process Preparation and release of the Final EIR (Fall 2020) Planning Commission Hearing on Final EIR and project (Late 2020/Early 2021) • Make recommendation to Board of Supervisors (Board) on both project and project Final EIR Board Hearing (Late 2020/Early 2021) • Certify Final EIR • Take action on the project Draft EIR Presentation 19 20-0786 E 19 of 19

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.