montague water pollution control facility planning for
play

Montague Water Pollution Control Facility Planning for the Future - PowerPoint PPT Presentation

Montague Water Pollution Control Facility Planning for the Future Robert J. Trombley, Superintendent Changes in Day-to-Day Operations are Providing Huge Financial Savings FY 2015 compared to FY 2010: $700,000+ annual benefit due to new


  1. Montague Water Pollution Control Facility Planning for the Future Robert J. Trombley, Superintendent

  2. Changes in Day-to-Day Operations are Providing Huge Financial Savings FY 2015 compared to FY 2010: $700,000+ annual benefit due to new process Trucking Revenues & Expenses FY2010 to FY2015 Trucked-In Waste Trucked out sludge Trucked out Trucked $ Material in Waste 700,000 600,000 500,000 400,000 300,000 200,000 100,000 0 2009/10 2010/11 2011/12 2012/13 2013/14 2014/15

  3. Tetra Tech, Inc.

  4. This isn’t your grandmother’s waste water treatment plant ….4

  5. Planning for the Future: Keeping sewer rates as low as possible by Maximizing trucked-in revenues New Staffing Arrangement (Level Funding Plan) Equipment Repair, Replacement & Upgrade (Level Funding Plan)

  6. Hand out of text for each slide

  7. Current Staffing Superintendent Bob Trombley Wastewater Clerk / Lab Wastewater Adm. Assistant Operators Laborers Tina Tyler Kate Jones John Little Anthony Suprenant Tim Little John Rathbun Tim Peura Vacant

  8. Future Staffing Administrator Chief Operator Kate Jones John Little Lab Tech / Wastewater Wastewater Industrial Laborers Operators Pretreatment Anthony Tim Little Coordinator Suprenant Tim Peura Tina Tyler John Rathbun Vacant

  9. Planning for the Future: Keeping sewer rates as low as possible by Maximizing trucked-in revenues Equipment Repair, Replacement & Upgrade (Level Funding Plan)

  10. Montague Water Pollution Control Facility

  11. Capital Investment / Bonding Schedule 6-Year Plan (FY 2016 – FY 2021) $750,000 initial investment for new equipment to increase trucked-in waste $5.25 million for replacement and upgrade of existing equipment

  12. Level Funding Plan to Continue the Benefits of Trucked-In Revenues Maintain effective staffing by using retiring superintendent’s wages to: Establish Administrator position Establish Chief Operator position Expand Lab Tech position to include Industrial Pretreatment Coordination responsibilities Bring Wastewater Operator and Wastewater Laborer wages in line with industry standards Install new equipment to support 50% increase in trucked-in waste revenues. Repair, replace and upgrade existing equipment Next Steps: Formal establishment of Staffing Plan FY2017 budgeting of Capital Improvements Plan

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend