MOBILITY UPDATE
N O RT H W E S T A U S T I N C O A L I T I O N F E B R U A RY 2 5 , 2 0 1 9
1
MOBILITY UPDATE N O RT H W E S T A U S T I N C O A L I T I O N F - - PowerPoint PPT Presentation
MOBILITY UPDATE N O RT H W E S T A U S T I N C O A L I T I O N F E B R U A RY 2 5 , 2 0 1 9 1 REGIONAL MOBILITY PROJECT UPDATES 2 ANDERSON MILL ROAD Final preliminary engineering report completed Sept. 2018 90% design by March
N O RT H W E S T A U S T I N C O A L I T I O N F E B R U A RY 2 5 , 2 0 1 9
1
2
report completed Sept. 2018
just over a year
take 6 months
construction would be summer 2020
3
alternative – 2 vehicle lanes each direction – raised median and left-turn bays – shared use path on both sides – new stormwater facilities
completed December 2018
underway
4
Project 1: RM 2222
(Bonaventure Dr to Ribelin Ranch Dr)
– Construction already underway – Anticipated completion: mid-2020 – Construction cost: $17.4 million Project 2: RM 620
(Steiner Ranch Blvd to RM 2222)
– Construction start: Fall 2019 – Anticipated completion: Winter 2020 – Construction cost: $10 million
5
Proposed Improvements – 3 lanes in each direction – Improve intersections and turn lanes – Dedicated bicycle/pedestrian path Project Development Timeline – Preliminary Design: 2019 – Final Design/Engineering: 2020 – Utility Relocation: 2021 – Estimated Construction Start: 2022
6
Regional Mobility: $101 million to address regional congestion and enhance safety Corridor Mobility: $482 million for corridor improvement projects Local Mobility: $137 million to local mobility projects, including:
– Sidewalks – Safe Routes to School – Urban Trails – Bikeways – Vision Zero – Sub-standard Streets
7
8
Final ASMP draft released on Feb. 22nd ASMP to be adopted later this spring Important Dates – Council Mobility Committee:
– Planning Commission:
– City Council
9
Plan in Spring 2019
– Commuter Service – Local Service
– Joint Meeting of the City Council and Capital Metro Board: March 4th
10
– Secured $13.7 million for Lakeline Blvd
– Add two additional travel lanes – Upgrade bicycle facilities and sidewalks
11
– Project 1: RM 2222 - Construction already underway – Project 2: RM 620 - Construction start: Fall 2019
– Study in progress
– Discussions on going for this segment
12
Working with City Staff to develop a Community PlacemakingToolkit
13
DISTRICT 6 NEWSLETTER
Get ongoing updates from the D6 office on community events and the latest from City Hall! Subscribe today by visiting: http://www.atxd6.org/contact/ subscribe/
14