mobility update
play

MOBILITY UPDATE N O RT H W E S T A U S T I N C O A L I T I O N F - PowerPoint PPT Presentation

MOBILITY UPDATE N O RT H W E S T A U S T I N C O A L I T I O N F E B R U A RY 2 5 , 2 0 1 9 1 REGIONAL MOBILITY PROJECT UPDATES 2 ANDERSON MILL ROAD Final preliminary engineering report completed Sept. 2018 90% design by March


  1. MOBILITY UPDATE N O RT H W E S T A U S T I N C O A L I T I O N F E B R U A RY 2 5 , 2 0 1 9 1

  2. REGIONAL MOBILITY PROJECT UPDATES 2

  3. ANDERSON MILL ROAD • Final preliminary engineering report completed Sept. 2018 • 90% design by March 2019 • Permitting process could last just over a year • Bid process anticipated to take 6 months • Earliest project could begin construction would be summer 2020 3

  4. SPICEWOOD SPRINGS ROAD • Alternative C selected as the build alternative – 2 vehicle lanes each direction – raised median and left-turn bays – shared use path on both sides – new stormwater facilities • Final preliminary engineering report completed December 2018 • Design phase of the project is now underway 4

  5. RM 2222/RM 620 BYPASS Project 1: RM 2222 (Bonaventure Dr to Ribelin Ranch Dr) – Construction already underway – Anticipated completion: mid-2020 – Construction cost: $17.4 million Project 2: RM 620 (Steiner Ranch Blvd to RM 2222) – Construction start: Fall 2019 – Anticipated completion: Winter 2020 – Construction cost: $10 million 5

  6. PARMER LANE Proposed Improvements – 3 lanes in each direction – Improve intersections and turn lanes – Dedicated bicycle/pedestrian path Project Development Timeline – Preliminary Design: 2019 – Final Design/Engineering: 2020 – Utility Relocation: 2021 – Estimated Construction Start: 2022 6

  7. 2016 MOBILITY BOND UPDATE Regional Mobility: $101 million to address regional congestion and enhance safety Corridor Mobility: $482 million for corridor improvement projects Local Mobility: $137 million to local mobility projects, including: – Sidewalks – Safe Routes to School – Urban Trails – Bikeways – Vision Zero – Sub-standard Streets 7

  8. MOBILITY PLANNING ACTIVATES 8

  9. AUSTIN STRATEGIC MOBILITY PLAN (ASMP) Final ASMP draft released on Feb. 22 nd ASMP to be adopted later this spring Important Dates – Council Mobility Committee: Feb. 28 th 1:00-3:00 pm – Planning Commission: • March 12 th 6:00 pm (Public Hearing) • March 26 th 6:00 pm – City Council • March 28 th (Public Hearing) 9

  10. PROJECT CONNECT • CapMetro to adopt Public Engagement Plan in Spring 2019 • High Capacity Transit • Service Type – Commuter Service – Local Service • Important Dates – Joint Meeting of the City Council and Capital Metro Board: March 4 th 10

  11. CAPITAL AREA METROPOLITAN PLANNING ORGANIZATION (CAMPO) • May 2018 adopted the 2019-2022 TIP – Secured $13.7 million for Lakeline Blvd • Project Improvements: – Add two additional travel lanes – Upgrade bicycle facilities and sidewalks 11

  12. RM 620 COLORADO RIVER TO US 183 • RM 2222/RM 620 Bypass Project – Project 1: RM 2222 - Construction already underway – Project 2: RM 620 - Construction start: Fall 2019 • RM 620/Anderson Mill Intersection – Study in progress • RM 620 - Anderson Mill Rd to US 183 – Discussions on going for this segment 12

  13. COMMUNITY PLACEMAKING TOOLKIT Working with City Staff to develop a Community PlacemakingToolkit 13

  14. DISTRICT 6 NEWSLETTER Get ongoing updates from the D6 office on community events and the latest from City Hall! Subscribe today by visiting: http://www.atxd6.org/contact/ subscribe/ 14

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend