Metro Transit C Line Downtown Minneapolis Neighborhood Associations Land Use Committee June 7, 2016 C Terrence Anderson Community Outreach Coordinator, Metro Transit 1 1 What is the C Line? Rapid Bus! Limited stops Frequent


  1. Metro Transit C Line Downtown Minneapolis Neighborhood Association’s Land Use Committee June 7, 2016 C Terrence Anderson Community Outreach Coordinator, Metro Transit 1 1

  2. What is the C Line? • Rapid Bus! – Limited stops – Frequent – Off-board payment – Articulated buses – Enhanced waiting areas • A package of improvements that makes service faster and more comfortable • Second in series of rapid bus lines starting with the A Line 2

  3. C Line Station Plan & Public Engagement • Outreach and engagement – Open houses – Neighborhood meetings – Transit rider outreach on buses and at stops • Agency coordination – Hennepin County – City of Minneapolis – City of Brooklyn Center Brooklyn Center Transit Center – Minneapolis Park and Recreation Board – Three Rivers Park District Minneapolis Central Library Route 19 4

  4. Finalized Station Locations • Finalized by Metropolitan Council Spring 2016 • C Line will open on Olson Highway with temporary stations, but Olson/Glenwood process will determine long-term alignment by end of 2016 5

  5. Downtown Stations 6

  6. 8 th Street Stations • City of Minneapolis plans to reconstruct 8 th Street from Hennepin Avenue to Chicago Avenue in 2019-2020 • Temporary operations prior to reconstruction; permanent stations built after reconstruction • Street configuration, station design/location will be finalized in 8 th Street Reconstruction final design and engineering 7

  7. Revised C Line project timeline 2015 2016 2017 2018 2019 Planning Metropolitan Council Station Plan Approval Design / Engineering Construction Pending Full Project Funding Open C Line Opening date to be determined in construction phase • Shift construction from 2017 to 2018 – Full funding not identified for 2017 – Initiate design mid-2016; 12-18 months of plan preparation – Potential for better coordination with other corridor construction projects 8

  8. Glenwood Avenue Possibility Current Opening Year Plan Penn Avenue Transit System Expansion Potential Long-Term Realignment Olson Memorial Highway Temporary C Line stations planned for Olson due to Blue Line Extension construction Not shown: Potential bus network modifications related to Green Line Extension & Blue Line Extension. Plans TBD as implementation nears. 9

  9. For more information visit C Line wepage: www.metrotransit.org/c-line-project C Terrence Anderson Community Outreach Coordinator, Metro Transit cterrence.anderson@metrotransit.org 612-349-7309 10

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.