SLIDE 7 Material Cost Reduction - Cuts Financing Needs
Rettler’s Concept Estimates; Added Bridge Finance, Concessions Upgrade Below
ESTIMATED PROJECT EXPENSES SUBTOTAL % Earthwork, Demolition, Geotech, Utilities 334,000 $ 14.1
- Synth. Turf & Base, Varsity Field (#1)
622,000 $ 26.3
- Synth. Turf & Base, Practice Field (#2)
880,000 $ 37.2 Fencing, Gates, Concessions Allowance 93,000 $ 3.9 Construction Contingency (ca. 10%) 190,000 $ 8.0 Project Soft Cost, Management 175,000 $ 7.4 Fiscal Sponsor, Bridge Finance, Fundraising 71,000 $ 3.0 TOTAL PROJECT EXPENSES 2,365,000 $ 100.0 PROPOSED SOURCES OF FUNDING SUBTOTAL % MC United (Cash Commitment) 25,000 $ 1.1 User Groups, Field Rental Fees 50,000 $ 2.1 CFNCW, Donor Advised Funds 140,000 $ 5.9 Private Foundations 2,000,000 $ 84.6
- Corp. Sector, Sponsors & Private
150,000 $ 6.3 TOTAL PROJECT FUNDING 2,365,000 $ 100.0
$2,140,000 , 91% $150,000 , 6% $75,000 , 3%
Proposed Sources of Funding
(excl. DCE’s material in-kind contributions)
PF, CF & DAF Corp & Private MCU, DCE & Users PF – Private Foundations, CF – Community Foundation, DAF – Donor Advised Funds, MCU – MC United, DCE – DC Everest School District