Melbourne Metro EES

Business Impact Assessment Expert Evidence

Terry Rawnsley National Leader Economic and Social Analysis

slide-2
SLIDE 2

Outline

  • Scoping requirments
  • Key Business Impact Assessment inputs
  • Key issues identified in the Business Impact Assessment
  • Summary of estimated impact
  • Summary of key issues raised in the submissions. The

statement of evidence details all of the issues raised.

  • EES EPRs
  • Suggested changes to EPRs

2

slide-3
SLIDE 3

PAGE 3

Scoping Requirements

slide-4
SLIDE 4

Key inputs

4

  • Precinct Context and Construction Impact.
slide-5
SLIDE 5

Key inputs

5

  • Melbourne Metro Rail Project Transport Impact Assessment

(April 2016) (Technical Appendix A).

slide-6
SLIDE 6

Key inputs

6

  • Melbourne Metro Rail Project Noise and Vibration Impact

Assessment (April 2016) (Technical Appendix I).

slide-7
SLIDE 7

Key inputs

7

  • Other inputs to understand the impacts
slide-8
SLIDE 8

Key inputs

8

  • Other inputs to understand the impacts

AM Peak Lunch Time

slide-9
SLIDE 9

Impact Assessment

  • For non‐acquired Retail and Food Services businesses

9

Access Amenity Perception Pedestrian Flows Business Impacts

slide-10
SLIDE 10

Previous projects

  • Victorian Comprehensive Cancer Centre (2012 – 2016)
  • Swanston Street Redevelopment (2012 – 2014)
  • Myer Emporium Development (2012 – 2014)
  • RMIT Swanston Academic Building (2010 – 2012)
  • RMIT Capital Works Program (2007 – 2016)
  • Tram Super Stops (2011 – 2012)
  • State Library of Victoria (six major stages 1986 – 2006)
  • Southern Cross Station (2002 – 2007)
  • Melbourne Central (2000 – 2003)
  • Fitzroy Gardens Storm Harvesting System (2013)

10

slide-11
SLIDE 11

Previous projects

  • Tram Super Stops 2011‐ 2012

11

slide-12
SLIDE 12

Previous projects

  • Tram Super Stops 2011‐ 2012

12

slide-13
SLIDE 13

Previous projects

13

Victorian Comprehensive Cancer Centre (2012 – 2016) Myer Emporium Development (2012 – 2014) Fitzroy Gardens Storm Harvesting System (2013) Southern Cross Station (2002 – 2007)

slide-14
SLIDE 14

Key issues from BIA

  • Disruption to business activity from the acquisition or

displacement of commercial land and businesses

  • Construction activity disrupting business operations,

particularly for hospitals and research institutions with specialist and highly sensitive equipment

  • Construction activity adversely affecting the surrounding

amenity disrupting business activity, particularly for retail, food and beverage and accommodation businesses

  • Construction activity impacting access to businesses thereby

disrupting their trade, particularly impacting businesses that rely on passing trade

14

slide-15
SLIDE 15

Summary of estimated impacts

15

Precincts

Acquisition / temporary

  • ccupation impact

Non‐ acquisition impact Total Impact ($m) % ($m) % ($m) % Tunnels ‐0.3 0.0% ‐12.4 ‐0.5% ‐12.7 ‐0.5% Western Portal ‐23.0 ‐34.3% 0.0% ‐23.0 ‐34.3% Arden Station ‐17.0 ‐24.3% ‐0.4 ‐0.6% ‐17.4 ‐24.9% Parkville Station ‐4.7 ‐0.3% ‐12.4 ‐0.8% ‐17.1 ‐1.1% CBD North Station ‐60.0 ‐6.5% ‐11.4 ‐1.2% ‐71.4 ‐7.7% CBD South Station ‐24.0 ‐3.3% ‐11.2 ‐1.5% ‐35.2 ‐4.8% Domain Station 0.0% ‐0.8 ‐1.1% ‐0.8 ‐1.1% Eastern Portal 0.0% ‐1.1 ‐4.4% ‐1.1 ‐4.4% Western Turnback (West Footscray) 0.0% 0.0% 0.0%

slide-16
SLIDE 16
  • Acquisition or displacement disrupting business operations
  • Access changes impacting business operations
  • Increased traffic and parking demand impacting access for

staff, customers and deliveries/pick up

  • Amenity changes impacting business operations
  • Impacts to sensitive equipment and processes
  • Disruption to business activity from disruptions to utilities
  • Impact on events

16

Key issues raised in submissions

slide-17
SLIDE 17
  • Technical Note 045 provides guidelines for non‐acquired

business (excluding health and education) which may be impacted by the project.

  • Prior to construction undertake interviews to better

understand the likely impact on businesses.

  • Focused on engagement, communication and marketing for

impacted businesses.

  • This would cover the vast bulk of impacts but may lack detail

for unique impacts.

PAGE 17

Support Guidelines

slide-18
SLIDE 18
  • The EPRs proposed in the exhibited EES would likely manage

the majority of impacts from the Melbourne Metro Rail Project. BUT

  • They may not manage unique impacts

AS

  • Business types and construction impacts varies across

precincts

  • In reviewing other expert evidence statements, the majority
  • f changes suggested involve adding detail to the existing

EPRs to manage unique impacts

PAGE 18

EPRs

slide-19
SLIDE 19
  • Current EPRs would manage the bulk of business impacts.
  • Refinements to the EPRs will provide a more detailed

framework for managing the impacts for business types that are likely to be at risk of being impacted in a unique manner by the project.

PAGE 19

Refinements to EPRs

slide-20
SLIDE 20
  • The impacts of the project should be able to be managed to

minimise the impact on the vast majority of businesses which may be adversely impacted.

PAGE 20

Conclusion