Welcome to AIRAH WAs Division Event Mechanical Services Compliance Presented by David Cooley, Milestone Certifiers and Derek Olsen, M.AIRAH, Olsen Environment Sponsored by Upcoming events in WA AIRAH WA Annual Members Lunch Old


slide-1
SLIDE 1

Mechanical Services Compliance

Presented by David Cooley, Milestone Certifiers and Derek Olsen, M.AIRAH, Olsen Environment

Sponsored by

Welcome to AIRAH WA’s Division Event

slide-2
SLIDE 2

Upcoming events in WA

AIRAH WA Annual Members’ Lunch Old Brewery Thursday, October 13 AIRAH Smoke Control and Fire Dampers course City West Receptions Tuesday, October 25 AIRAH WA Division Event Curtin Campus central energy control systems upgrade Wednesday, November 16

slide-3
SLIDE 3

Upcoming national events

AIRAH National Awards Night November 10, Sydney Luna Park, Sydney Congratulations to all our Finalists!

slide-4
SLIDE 4

Presenting:

David Cooley, Milestone Certifiers

slide-5
SLIDE 5

Mechanical Works – When do you need a Building Permit?

Presenter – David Cooley Milestone Certifiers BCA Consultants www.milestonebc.com.au

slide-6
SLIDE 6

Mechanical Service Compliance

The Approval Process in Western Australia

– WA Building Act 2011 & WA Building Regulations 2012 – WA Building Act binds the Crown (i.e. Government) – Certain types of work exempt from requirement for a building permit

  • Key messages:

– BCA certification by registered building surveyors – “Complete” applications required before certification – WA Approvals system is a hybrid of Private & Public input – Local Government (and some State Government Agencies) become a Permit Authority – issue permits, enforcement, maintain records – More info go to https://www.commerce.wa.gov.au/building-commission/building-approvals

slide-7
SLIDE 7

What they set out to achieve:

slide-8
SLIDE 8

We ended up with:

In some peoples opinion..................................

slide-9
SLIDE 9

Building Commission

slide-10
SLIDE 10

Design - Certified

Engages Registered Building Surveyor to assess plans and issue a Certi rtifi ficat ate of Desi esign gn Compl pliance nce Submits Applica cati tion

  • n for

r Buil ilding ng Permit rmit to the permit authority with all plans, specifications, technical documents and fees Issues Buil ilding ng Permit rmit within 10 busi sines ness s days ys

  • r the application may be deemed refused

and permit fee refunded

Applicant

(owner/builder)

Local Government

Further information requested within 10 business days. Clock stops Clock starts again - within 10 days to issue Building Permit Further information supplied within 21 days

slide-11
SLIDE 11

Construction - Certified

Registered Building Surveyor inspects and issues Certi tifi fica cate te of Cons nstr truc ucti tion

  • n

Compli lianc

  • nce. Applicant applies to the

Permit Authority for an Occu ccupanc ncy y Perm rmit it Issues Occu cupanc ncy y Permi mit within 10 busi sines ness s days ys

  • r the application may be deemed refused

and permit fee refunded

Applicant

(owner/builder)

Permit Authority

Further information requested within 10 business days. Clock stops Clock starts again – within 10 business days to issue Occupancy Permit Further information supplied within 21 days

Provides Notic ice e of Complet letion ion to Permit Authority within 7 days ys of construction being completed

Builder

slide-12
SLIDE 12
  • Permit authority fee - varies on type of permit. Typically

certified Class 2 to 9 charges are 0.09% i.e. $30M project cost Council receives $27K (rather than an Administration fee as in other States)

  • State Fees – Building Services Levy 0.09% for projects

>$45K

  • State Fees - Construction Training Fund: 0.2% for projects

>$20K

  • BCA Certifiers Fee -
  • Negotiable & determined by market

Statutory Fees

slide-13
SLIDE 13

When is a Building Permit Required?

The WA Building Act (Sect. 3) defines “building work” as — (a) the construction, erection, assembly or placement of a building or an incidental structure; or (b) the renovation, alteration, extension, improvement or repair of a building or an incidental structure; or (c) the assembly, reassembly or securing of a relocated building or a relocated incidental structure; or (d) the changing of ground levels of land for the purposes of work of a kind mentioned in paragraph (a), (b) or (c) to an extent that could adversely affect land beyond its boundaries; or (e) site work on any land for the purposes of, or required because of, work of a kind mentioned in — (i) paragraph (a), (b), (c) or (d); or (ii) paragraph (a) or (b) of the definition of demolition work; or (f) other ‘prescribed work’, but does not include work of a kind prescribed for the purposes of this definition as not being building work

slide-14
SLIDE 14

When is a Building Permit Required?

The WA Building Regulations (Reg. 6A) further states that “Building work” defined in the Act can include: For the purposes of paragraph (f) of the definition of building work in section 3, the installation of a roof mounted evaporative cooling unit on a building or incidental structure is prescribed work. The intent of this requirement is to address bushfire risk in bushfire prone areas so that the overall building design can meet AS 3959 in terms of BAL 12.5 and above for non combustible covers or perforated sheet with openings no greater than 2mm

  • ver evaporative coolers. At BAL 40 no evaporative coolers permitted.
slide-15
SLIDE 15

Exemptions for a Building Permit

WA Building Regulations, Schedule 4 — Building work that does not require building permit (Remote Locations)

  • Includes remote areas in Western Australia such as Kent, Laverton, Meekatharra,

Menzies, Wiluna, Yilgarn etc; *It is also important to remember that whilst a Building Permit is not required in these remote areas (or any area), the buildings must however still meet the Building Code Part 5 of the WA Building Act Part 5 of the Building Act also provides for exemptions from the requirement to

  • btain certain permits under the building approval process for particular buildings

and incidental structures based on their level of risk. However these exemptions do not remove the requirement for approvals under other legislation if required, for example planning or health. To determine whether an exemption applies for your particular circumstance, contact the permit authority

slide-16
SLIDE 16

Exemptions for a Building Permit

  • Temporary buildings – no longer than 1 month *unless members of the public

would use;

  • Buildings incidental to infrastructure (proposed to be used in the construction,
  • peration and maintenance of road, rail, port, harbour, airport water, sewerage,

electricity, oil or gas - *unless it is residential, or members of the public would use;

  • Buildings incidental to shipping and boating facilities - *unless it is residential, or

members of the public would use;

  • Buildings incidental to mining operations - *unless it is residential, or members of

the public would use;

  • Buildings incidental to exploiting petroleum and other resources - *unless it is

residential, or members of the public would use;

  • Buildings incidental to industrial plant - *unless it is residential, or members of

the public would use

slide-17
SLIDE 17

Exemptions for a Building Permit

Other exemptions include:

Item Description of building work for which building permit is not required 1. Construction, erection, assembly or placement of a freestanding Class 10a building that — (a) has a floor area not exceeding 10 m

2; and

(b) is no more than 2.4 m in height; and (c) is not located in wind region C or D as defined in AS 1170.2. 2. Renovation, alteration, improvement, repair or maintenance of a building or incidental structure if the building work — (a) will not adversely affect the structural soundness of the building or incidental structure and does not include — (i) an increase or decrease in the floor area or height of the building or incidental structure; or (ii) underpinning or replacement of footings; or (iii) the removal or alteration of any element of the building or incidental structure that is contributing to the support of any other element of the building or incidental structure; and

slide-18
SLIDE 18

Exemptions for a Building Permit

Item Description of building work for which building permit is not required 2. (b) is done using materials commonly used for the same purpose as the material being replaced; and (c) will not change the use or classification of the building or incidental structure; and (d) will not adversely affect the safety and health of the occupants or other users of the building or incidental structure or of the public; and “(e) will not affect the way in which the building or incidental structure complies with each building standard that applies to the building or incidental structure”; and (f) is not work of a kind to which section 76, 77, 78 or 79 relates; and (g) is not subject to an order, agreement or permit under the Heritage Act. 3. Construction, erection, assembly or placement of a temporary office, shed or sanitary facility to be used by a builder in connection with building work carried out on the land

  • n which the office, shed or sanitary facility is, or is proposed to be, located.

4. Construction, erection, assembly or placement of a fence, screen or similar structure,

  • ther than a fence forming part of a barrier to a private swimming pool

…….. ……..

slide-19
SLIDE 19

Exemptions for a Building Permit

Item Description of building work for which building permit is not required 5. Construction, erection, assembly or placement of a mast, antenna or similar structure that — (a) is not located in wind region C or D as defined in AS 1170.2; (b) if attached to a building — (i) is no more than 2 m in height above the highest point of attachment to the building; (ii) … 6. Construction, erection, assembly or placement of a retaining wall that — (a) retains ground no more than 0.5 m in height; and (b) ……. 7. Construction, erection, assembly or placement of a pergola associated with a Class 1 building that — (a) is no more than 2.4 m in height; and (b) is not located in wind region C or D as defined in AS 1170.2; and (c) covers an area not exceeding 20 m2 8. Construction, erection, assembly or placement of a water storage tank with a capacity

  • f 5 000 L or less
slide-20
SLIDE 20

Exemptions for a Building Permit

Item Description of building work for which building permit is not required 9. Building work for a park home or annexe as those terms are defined in the Caravan Parks and Camping Grounds Act 1995 section 5(1). 10. Attachment of photovoltaic panels or solar hot water systems to the roof of a Class 1

  • r Class 10a building that is not located in wind region C or D as defined in AS 1170.2.

11. Building work for which a building licence was not required under the former provisions if, before commencement day — (a) the on-site building work had commenced; or (b) a contract to carry out the building work was entered into 12. Building work for buildings owned or occupied by, or under the control or management of the Crown in right of the State or a department, agency or instrumentality of the Crown in right of the State that — (a) commences before 30 June 2017; and (b) has, when it commences, an estimated value of less than $50 000

slide-21
SLIDE 21

Maintenance

What about maintenance and plant upgrades?

  • Changing like for like, and replacement of end of life mechanical plant

would not require a Building Permit;

  • Cosmetic upgrades do not require a Building Permit (new painting,

tiling etc) *If however the new mechanical plant ‘will affect the way in which the building or incidental structure complies with each building standard that applies to the building or incidental structure’, such as upgrading a new smoke exhaust system, or stairwell pressurisation system, or changes to a building that may affect any existing Fire Engineered Alternative Solutions

  • then a Building Permit is required;
slide-22
SLIDE 22
  • Mech. Upgrade - Example

A HVAC system upgrade to an existing shopping centre:

  • New works involve only the HVAC upgrade because of end of life of

the existing mechanical plant;

  • Existing building does not have smoke exhaust for tenancies &

interconnected malls larger than 2,000m2

  • The new HVAC system is to meet AS1668.2-2012 and Section J

implications for Energy Efficiency. Any new structural works also require certification – all IFC drawings forming part of a certified new Building Permit;

  • However there is no trigger to upgrade the non compliant smoke

exhaust as it will be assumed that the building complied with the applicable building legislation at the time of its original construction

  • Triggers for any upgrade to meet current Code are –

– Change in use, or the Permit Authority deems the building unsafe and serves an Order. Otherwise the ‘new works’ are considered in isolation

slide-23
SLIDE 23

Evidence of Compliance

What does the mechanical services designer need to certify?

  • Statement of design compliance to justify compliance with applicable

Australian Standard i.e. AS1668.2-2012, or AS/NZS 1668.1-2015 – the Standard adopted by the current Building Code;

  • If works would trigger compliance with the BCA Energy Efficiency

provisions – also Part J5;

  • Provide a full set of Issued for Construction drawings & Specification as

part of any certified package for Building Permit

slide-24
SLIDE 24

Registration of Engineers

Who is able to certify mechanical services?

  • Without licensing and registration of other Services disciplines in WA

(except contractors such as Builders, Plumbers & Painters), the BCA Certifier currently accepts accountability for their design i.e. Mechanical Engineers, Electrical Engineers. These industries are self regulated;

  • Victorian Building Authority – does have a registration system for all of

its Services Engineers as an example

slide-25
SLIDE 25

Registration of Engineers

slide-26
SLIDE 26

Maintenance of Essential Services

Does maintenance and fire testing need to be completed? – YES introduced late 2015

Division 2A — Maintenance

  • 48A. Maintenance of buildings

(1) In this regulation — relevant building standards, in relation to a part of a building, means — (a) if one or more building permits have been granted in respect of the part — the building standards in the edition of the Building Code identified in the applicable certificate of design compliance for the most recent of those building permits; or (b) if paragraph (a) does not apply but one or more building licences were issued under the Local Government (Miscellaneous Provisions) Act 1960 in respect of that part — (i) the building standards in the edition of the Building Code that applied at the time the most recent building licence was issued; or (ii) if no edition of the Building Code applied at the time the most recent building licence was issued — each requirement in relation to the technical aspects of the construction of the part applicable at that time;

  • r

(c) otherwise — each requirement in relation to the technical aspects of the construction of the part applicable to the part at the time of its construction; safety measures means measures relating to the following — (a) building fire integrity; (b) means of egress; (c) signs; (d) lighting;

slide-27
SLIDE 27

Maintenance of Essential Services

(e) fire fighting services and equipment; (f) air handing systems; (g) automatic fire detection and alarm; (h) occupant warning systems; (i) lifts; (j) standby power supply systems; (k) building clearance and fire appliances; (l) glazed assemblies, balconies, balustrades, refrigerated chambers, strong rooms, vaults; (m) bushfire protection measures; (n) building use and application. (2) The owner of an existing building that is a Class 2 to Class 9 building must ensure that — (a) the safety measures in each part of the building are capable of performing to a standard set out in the relevant building standards for the part; and (b) the mechanical ventilation, hot water, warm water and cooling water systems are adequately maintained to safeguard people from illness or injury; and (c) the building’s services in each part of the building continue to perform to a standard of energy efficiency that is equal to or greater than the standard in the relevant building standards for the part. Penalty: a fine of $5 000.

slide-28
SLIDE 28

What really happens

  • The Building Commission have set the Permit rules – albeit vague

when it comes to a mechanical services upgrade;

  • The Building Commission will refer you to the Local Permit Authority;
  • If asked, the Permit Authority will request a Building Permit in most

cases because they receive a fee;

  • For Building works over $20,000, the Building Permit Application Form

technically requires a registered builder to lodge the Form. There is currently no exemptions for Mechanical Contractors, as the exemptions only apply to incidental structure such as the installation of fire sprinklers, free standing partitioning, safety systems, timber decking and glazing.

slide-29
SLIDE 29

Registered Builders

slide-30
SLIDE 30

Registered Builders

slide-31
SLIDE 31

Mechanical Works – When do you need a Building Permit?

Presenter – David Cooley 0400 844 388 Milestone Certifiers BCA Consultants www.milestonebc.com.au

slide-32
SLIDE 32

Presenting:

Derek Olsen, M.AIRAH, Olsen Environment

slide-33
SLIDE 33

Stairwell Pressurisation and Smoke Control

Presenter – Derek Olsen M.AIRAH

slide-34
SLIDE 34

Agenda

  • Smoke Hazards
  • Smoke Management Systems
  • Stairwell Pressurisation Overview
  • Stairwell Pressurisation Validation Requirements
  • Testing and Validation Process
  • What Problems Do We Face?
  • Coordination & Roles and Responsibilities
slide-35
SLIDE 35

What is a smoke Hazard

The Consequences of fire – “The killing Fumes”

  • Most fire deaths are not caused by burns, but by smoke

inhalation

– Particles - Penetrate the respiratory system’s protective filters and lodge in the lungs – Vapors – Fog like droplets of liquid absorbed through the skin – Toxic Gases – Carbon Monoxide, Hydrogen Cyanide (Plastics), Phosgene (Vinyl) – Lack of Oxygen – Hot Air Kills

slide-36
SLIDE 36

Case Study

  • 1980
  • 85 deaths.
  • The fire was almost completely limited to the casino on the ground floor
  • 75 percent of the deaths were on upper floors because of smoke

inhalation.

slide-37
SLIDE 37

Smoke Management Systems

  • HVAC system automatic shutdown
  • Purge system (AHU / RAF)
  • Smoke exhaust (extraction) system
  • Opposed air flow method (Tunnels)
  • Smoke Containment
  • Pressurisation system
  • AS 1668 Part 1 : 1998
slide-38
SLIDE 38

Smoke Management Systems

Automatic Shutdown

  • ie Air Handlers
  • Dampers installed between all fire compartments

served automatically close on receipt of fire alarm

1

slide-39
SLIDE 39

Smoke Management Systems

Opposed Airflow

  • To push smoke in a desirable direction
  • Typically used in tunnel and atrium configurations

1

slide-40
SLIDE 40

Smoke Management Systems

Smoke Exhaust

  • To transport smoke out of enclosures
  • Mechanically assisted smoke exhaust system
  • Large open areas such as Lobby or Shopping Malls

1

slide-41
SLIDE 41

Smoke Management Systems

Purge System

  • Air flowing through all compartments without re-

circulation.

  • Smoke-spill air in each fire compartment is discharged to

atmosphere directly

  • Outdoor air supplied to all compartments at a rate less

than the smoke-spill air

1 2

slide-42
SLIDE 42

Smoke Management Systems

Purge System

slide-43
SLIDE 43

Smoke Management Systems

Purge System

slide-44
SLIDE 44

Smoke Management Systems

Pressurisation (Sandwich)

1 2 3 4 5

slide-45
SLIDE 45
slide-46
SLIDE 46
slide-47
SLIDE 47

SPF NFAF FAF NFAF SAF EX EGRESS 20Pa?

slide-48
SLIDE 48

Testing Procedures

slide-49
SLIDE 49

Validation Requirements

  • Inspection of the system Stairwell doors close and latch correctly.
  • Minimum Zone to Zone Pressure Differential
  • Door Opening Force
  • Minimum Door Air Velocity
  • Recovery Time
  • Noise levels.
  • Manual and automatic control start / stop.
  • Indication lights, fault, run, ready and display time.
  • Fan shut down on smoke intake and auto restart.
  • Documentation and sign off.
slide-50
SLIDE 50
slide-51
SLIDE 51
slide-52
SLIDE 52

Testing Pre-Start

slide-53
SLIDE 53

Testing Procedures – Door Force

slide-54
SLIDE 54

Testing Procedures – Door Force

slide-55
SLIDE 55

SPF NFAF FAF NFAF SAF EX EGRESS

slide-56
SLIDE 56

=> 1.0 m/s

Testing Procedures – Door Air Velocity

slide-57
SLIDE 57

SPF NFAF FAF NFAF SAF EX EGRESS

slide-58
SLIDE 58

Testing Procedures – Zone Press Diff

slide-59
SLIDE 59

Testing Procedures – Zone Press Diff Check above and below

=> 20Pa to <= 100 Pa

slide-60
SLIDE 60

Testing Procedures – Zone Press Diff

slide-61
SLIDE 61

Measurement

slide-62
SLIDE 62

Problems?

1. Building Preparedness

– External & Internal Envelopes – Penetrations – Floor to floor leakage

2. Controls point to point 3. Controls static pressure sensor

– Location (Internal or External) – Range – Dirty

4. FIP Point to point 5. Problematic Doors

– Under Seals – Latches – Door Closer

6. Tenants and Construction Personnel 7. After Hours 8. Building Tightness 9. No Floor Relief Dampers 10. Elevators – Service Shafts 11. Crazy Air – Stair Corridors 12. Weather Factors

– Egress Door – Static Pressure Sensors

slide-63
SLIDE 63

Coordination

  • TAB Contractor
  • Mechanical Contractor Supervisor
  • Mechanical Electrical Contractor
  • Controls Contractor
  • Fire Contractor
  • Builders Supervisor
  • Security Guards
  • Builders Tradesman
  • Property Manager
  • Owners Representative
  • ICA
  • Local Authority Representative
slide-64
SLIDE 64

Coordination

slide-65
SLIDE 65

Thankyou