measure a
play

Measure A Pedestrian & Bicycle Program Update April 4, 2019 - PowerPoint PPT Presentation

Measure A Pedestrian & Bicycle Program Update April 4, 2019 Board of Directors Agenda Item #10 (b) Overview Program background Program allocations & delivery status Feature Project: California Drive Roundabout


  1. Measure A Pedestrian & Bicycle Program Update April 4, 2019 Board of Directors Agenda Item #10 (b)

  2. Overview • Program background • Program allocations & delivery status • Feature Project: California Drive Roundabout (Burlingame) 2

  3. Program Background • 3% of Measure A Program • Purpose: to fund capital projects that encourage and improve walking and bicycling conditions • 2004 Transportation Expenditure Plan includes a list of bikeways and overcrossings but other projects can be considered • Funding awarded on a discretionary Call for Projects process 3

  4. Project Allocations Award Award Number of Cycle Date Amount Projects Special 2010/2011 $0.7M 2 Circumstances First July 2011 $4.5M 16 Second April 2014 $5.9M 11 Third March 2016 $5.0M 10 Fourth March 2018 $5.7M 10 TOTAL $21.8M 49 4

  5. Program Delivery Status Number of Project Status Projects Planning/Preliminary Engineering/ 3 Environmental 14 Final Design 6 Construction 24 Awarded project scopes complete 2 Sponsor rescinded projects 49 TOTAL  Sponsors submit quarterly progress reports on project status.  To date, 12 awarded projects needed time extensions. 5

  6. Distribution of Project Awards Total: $21.8M County Funding North County: $3.9M Sub-area Awards North 10 County Mid County: $8.5M Mid County 17 Coastside: $1.9M South 17 County South County: $7.5M Coastside 5 Total 49 6

  7. California Drive Roundabout Overview • Existing Conditions • Project Goals • Funding • Schedule • Construction Staging • Challenges • Lessons Learned 7

  8. Project Location California 8

  9. Existing Conditions Major through movements on California Drive needs to Conflicting movements creates be accommodated. confusing conditions for pedestrians and cyclists. Four-lane mid-block crosswalk with flashing beacon. Stopped vehicles impact traffic on the Bellevue and Lorton approaches . Weaving, merge and diverge movements create a confusing situation. 9

  10. Project Goals Improve the California Drive, Bellevue Avenue and Lorton Avenue intersection by: • Improving safety and flow of all modes (pedestrians, bicyclists, and vehicles) • Incorporating Green Streets and Complete Streets components • Enhancing bicycle and pedestrian access • Minimizing construction and parking impacts 10

  11. Project Funding Project Funding - Design 2015: Burlingame received $1.0M (Design Contract: $293 K) Measure A Ped/Bike Program allocation, matched with $200k of City funds. 40% Total original project budget: $1.2M. Total project cost upon completion in 60% 2019: $4.3M. Measure A City of Burlingame Project Funding - Construction (Construction Contract: $2.9 MIL) Rationale for added costs: • Added design elements from project outreach & increase in 28% construction costs - $2.9M • Construction admin. & 72% Measure A management - $900K City of Burlingame • Upgrade of utilities/facilities in roundabout vicinity - $500K

  12. Conceptual Design

  13. Project Schedule DESIGN PHASE October May October January Jan/Feb May 2018 2015 2016 2016 2017 2018 • Begin Construction • 1 st public • 2 nd public • 3 rd public • Design • Advertise outreach outreach outreach Process project for meeting meeting meeting construction • City bids Council 13

  14. Project Schedule CONSTRUCTION PHASE September October 2018 January March 2019 May 2018 Feb 2019 2018 2019 • Stage 3 • Stage 4 • Begin • Stage 4 Construction • Approx. 3 month • Temperatures • Stage 2 • Completing • Postponed • Stage 1 duration above 50 Stage 3 due to rain • Approx. 1 degrees • Major work and freezing • Approx. 4 month • Landscaping, month suspended temperatures duration electrical, duration between Holidays lighting 14

  15. Construction Stage 1 15

  16. Construction Stage 2 16

  17. Construction Stage 3 17

  18. Construction Photos

  19. Completed Project Photos

  20. Construction Challenges • Maintaining access on California Drive • Impacts to adjacent businesses • Educating community during construction, especially when portions of the new alignment opened up in different stages • Weather, as final stage was anticipated during winter • Utility improvements 20

  21. Lessons Learned/Closing Thoughts • Conform roadway grades • Existing Utilities • Construction Manager/Outreach • Constant Communication/Notification 21

  22. Roundabout Informational Video Click to start video

  23. Questions/Comments 23

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend