Maharashtra State Load Despatch Centre 25 th FOLD Meeting 07 th - - PowerPoint PPT Presentation

maharashtra state load despatch centre
SMART_READER_LITE
LIVE PREVIEW

Maharashtra State Load Despatch Centre 25 th FOLD Meeting 07 th - - PowerPoint PPT Presentation

Maharashtra State Load Despatch Centre 25 th FOLD Meeting 07 th August 2018 1 State Load Despatch Centre Organization Structure within MSETCL Chairman & Managing Director MS Electricity Transmission Co. Ltd. Director (Operations) MS


slide-1
SLIDE 1

1

25thFOLD Meeting 07th August 2018

Maharashtra State Load Despatch Centre

slide-2
SLIDE 2

Director (Operations) MS Electricity Transmission Co. Ltd. Chief Engineer (LD) MSLDC Superintending Engineer Operation Department ( OP ) Superintending Engineer

Energy Accounting (EA)

Superintending Engineer

(SCADA-ADM- IT )

Superintending Engineer

(ALDC Nagpur

Ambazari)

Executive Engineer

(Mumbai Sub-LDC)

2

State Load Despatch Centre Organization Structure within MSETCL

Chairman & Managing Director MS Electricity Transmission Co. Ltd.

slide-3
SLIDE 3

State functional over view

Maharashtra State Load Despatch Centre ( MSLDC) Intra State Generating Stations

  • MS Power Generation Co.
  • Tata Power Co. – (G)
  • Reliance Infra ltd. – (G)
  • IPPs : APML,WPCL,JSWEL,

RPL ,VIPL, IEPL

  • All Captive Power Plants,
  • NCE ( Wind, Solar, bio-mass

etc.) Intra State Transmission Licensees

  • MS Electricity Transmission Co. (MSETCL)
  • Tata Power Co. – (T)
  • Reliance Infrastructure ltd. – (T)
  • Jaigad Trans. Co. (JPTL)
  • Adani Transmission India ltd. (ATIL)
  • Amravati Power Transmission Co. Ltd.(APTCL)
  • Sinnar Power Transmision Co. Ltd.(SPTCL)
  • Maharashtra Eastern Grid Power Transmission
  • Co. Ltd.( MEGPTCL)
  • Vidarbha Industries Pvt.Ltd. (VIPL)

Intra State Distribution Licensees

  • M.S. Electricity Distribution Co.
  • Tata Power Co. – (D)
  • Reliance Infrastructures ltd. – (D)
  • BEST
  • Central Railway (Maharashtra)
  • MADC (SEZ)
  • Mindspace Properties (SEZ)
  • Giigaplex (SEZ)

Sub LDC Ambazari,( Nagpur) Sub LDC Trombay (Mumbai)

slide-4
SLIDE 4

4

OPERATION WING SCADA / IT / ADMINISTRATION WING ENERGY ACCOUNTING WING

slide-5
SLIDE 5

5

Outline

  • 1. State of Maharashtra-Map
  • 2. Transmission Infrastructure.
  • 3. State Installed Capacity and Demand.
  • 4. System Operation and Highlights
  • 5. Energy Accounting
  • 6. SCADA
slide-6
SLIDE 6

6 Legend

Wind + Solar Karad Zone – 3335 MW Nashik Zone – 1815 MW

slide-7
SLIDE 7

7 Legend

Installed Capacity Thermal – 26369 MW Hydro – 3386 MW Gas – 3143 MW Nuclear – 755 MW Non-Conventional Energy- 8476 MW Total- 42129 MW Area- 307,713 km2 Population- 112,372,972 Major Distribution Licensees-4

Discom-wise Electricity Consumers MSEDCL – 2,54,21,107 R-Infra D -30,10,000 TPC-D – 6,80,000 BEST- 10,02,299

Total – 3,01,13,406

slide-8
SLIDE 8

765kV substations in Maharashtra

There are 12 no’s of 765/400 KV sub-stations in the Maharashtra constructed under CERC and MERC transmission license.

  • Sub-station Under CERC transmission license
  • 1) 765/400 KV Pune GIS (Shikrapur) (PG)
  • 2) 765/400 KV Aurangabad (PG)
  • 3) 765/400 KV Wardha (PG)
  • 4) 765/400 KV Solapur (PG)
  • 5) 765/400 KV Padghe GIS (PG)
  • 6)765/400 KV New Parli (PG)
  • 7)765/400 KV Warora (PG)
  • 8) 765/400 KV Dhule (BDTCL)
  • Sub-station Under MERC transmission license
  • 1) 765/400 KV Tiroda (Adani)-For Generation Evacuation
  • 2) 765/400 KV Akola-2 (Adani)
  • 3) 765/400 KV Koradi-3 (Adani)
  • 4) 765/400 KV Ektuni (MSETCL)

8

slide-9
SLIDE 9

State Grid Infrastructure

As on 31st Mar. 2018

MSETCL :- Mumbai Transmission System :

1 220 9 5030 418.825 2 110 24 3900 743.936 33 8930 1162.761 RIL 1 220 8 3000 536.076 TPCL Total TPCL

Voltage Level EHV Substation Transformation Capacity (MVA) EHV LINES (CKT KM.) 765kV 1 3000 500 KV HVDC 2 3582 1504 400 KV 31 30045 8415.497 220 KV 223 53185 17788.427 132KV 322 28779.5 15454.409 110 KV 36 2330 1759.365 100 KV 38 2798 701.403 66 KV 7 127 594.8 Total 660 123846.5 46217.901

slide-10
SLIDE 10

10

Jaigad Power Transmission Co. Ltd

SN Voltage (KV)

  • No. of EHV S/s
  • No. of lines

EHV Lines Ckm 1 400 1 4 330

Adani Transmission India Ltd. (ATIL)

SN Voltage (KV)

  • No. of EHV S/s
  • No. of lines

EHV Lines Ckm 1 765 2 400 2 436

Amravati Power Transmission Co. ltd.

SN Voltage (KV)

  • No. of EHV S/s
  • No. of lines

EHV Lines Ckm 1 400 1 4 220

Sinner Power Transmission Co. ltd.

SN Voltage (KV)

  • No. of EHV S/s
  • No. of lines

EHV Lines Ckm 1 400 1 2 104

Maharashtra Eastern Grid Power Transmission Co. ltd.

SN Voltage (KV)

  • No. of EHV S/s
  • No. of lines

EHV Lines Ckm 1 765 3 6 1160 2 400 2 60 ( MEGPTCL Transformation capacity is 3*1500 MVA)

Vidarbha Industries Pvt. Ltd

SN Voltage (KV)

  • No. of EHV S/s
  • No. of lines

EHV Lines Ckm 1 220 1 4 6

State Total

SN

  • No. of EHV S/s

MVA EHV Lines Ckm 1 708 140276.5 50232.738

slide-11
SLIDE 11

(as on 31.03.2018)

Maharashtra System Peak Installed De-rated Capacity along with its CS Share Particulars Hydro Thermal Gas Nuclear NCE Total MSPGCL 2450 10170 672 180 13472 TPCL 447 1250 180 205 2082 REL 500 93 593 IPP / CPP 44 9125 388 7998 17555 CS(MS) 445 5323 1903 (*) 755 8426 Total 3386 26369 3143 755 8476 42129

(*) RGPPL 95 % capacity to MSEDCL, Not availed.

Maharashtra State Installed Capacity

slide-12
SLIDE 12

Power supply to Megacities

  • Mumbai- “One of the ancient world heritage”
  • Financial Hub of India and Capital of Maharashtra.
  • Important loads-RBI, Stock Exchange, Imp Foreign Embassies

Suburban/Mainline Railways, H.Q of Banking Institutions etc.

  • Maximum demand met 3670 MW with internal installed

capacity of 1877 MW on 31/05/2018

  • Mumbai Transmission network mostly at 220kV and 110 kV by

TPC-T & R-infra -T

  • Interconnecting Network- MSETCL (400kV+220kV+110kV)

feeding from north side as rest area surrounded by sea shore

  • Distribution co.-TPC-D,R-infra-D,BEST , Railway, MSEDCL

12

slide-13
SLIDE 13
  • Pune- “Cultural and educational Capital”
  • Automobile/IT/Industrial Hub of India & agricultural

dominated area in Maharashtra.

  • 5 Nos 400kV Substations located periphery supplying power

to Pune & cluster area.

  • 400/220kV Lonikand 1 (945 MVA)
  • 400/220kV Lonikand 2 (1000 MVA)
  • 400/220kV Jejuri (1500 MVA)
  • 400/220kV Talegaon (945 MVA)
  • 400/220kV Chakan (630 MVA)
  • Total Load 3000MW

13

slide-14
SLIDE 14

14

FY 2012-13 FY 2013-14 FY 2014-15 FY 2015-16 FY 2016-17 FY 2017-18 FY 2018-19 (as on June18) State Catered Demand 124001 125942 138997 144899 147879 154215 43366 MSEDCL 104585 106461 118774 123870 127220 132953 37367 MUMBAI 19416 19481 20223 21029 20658 21261 6000

Energy Catered in Mus

FY 2012-13 FY 2013-14 FY 2014-15 FY 2015-16 FY 2016-17 FY 2017-18 FY 2018-19 (as on June 18 ) State Unrestricted Demand 18268 19635 20795 21414 23055 22994 23755 State CATERED Demand 17268 18803 20424 21064 22517 22994 23755 MSEDCL Demand 15261 17158 17694 18046 19745 19688 20340 MUMBAI Demand 3153 3217 3365 3368 3310 3592 3670

Peak Demand in MW

slide-15
SLIDE 15

15

FY 2012-13 FY 2013-14 FY 2014-15 FY 2015-16 FY 2016-17 FY 2017-18 FY 2018-19 18268 19635 20795 21414 23055 22994 23755 15261 17158 17694 18046 19745 19688 20340 3153 3217 3365 3368 3310 3592 3670

Peak Demand in MW

State Unrestricted Demand MSEDCL Demand MUMBAI Demand FY 2012-13 FY 2013-14 FY 2014-15 FY 2015-16 FY 2016-17 FY 2017-18 FY 2018-19 124001 125942 138997 144899 147879 154215 43366 104585 106461 118774 123870 127220 133158 37367 19416 19481 20223 21029 20658 21057 6000

Energy Requirement in MUs

State Catered Demand MSEDCL MUMBAI

slide-16
SLIDE 16
slide-17
SLIDE 17

2.3 Monthly Maharashtra State Max Demand For the Period April- 2015 to June-2018

slide-18
SLIDE 18

18

Monthly Maharashtra State Average Energy Req. For the Period Apr-2015 to June-2018

slide-19
SLIDE 19

Load Curve for Peak Day in FY 2018-19

5000 10000 15000 20000 25000 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 TIME_SRNO MSEB_T MSEB_H MSEB_G WIND CS_RECE IPP Mumbai Generation SOLAR LOAD_SHEDDING

MSPGCL Hydro

Wind

CS Receipt IPP

Mumbai Generation Solar

MSPGCL GAS

MSPGCL THERMAL

Highest Peak on dt.30.05.2018 – 23755 MW

slide-20
SLIDE 20

System Operation & Control

20

FUNCTIONS:

  • Operational planning
  • Demand Estimation
  • Generation Scheduling
  • Real-time dispatch monitoring and Control
  • Grid Security Analysis
  • Outage and contingency planning
  • Generation-Load balance and control
  • Congestion Management
  • Coordination with RLDC and ALDCs
  • Open Access and bilateral scheduling
  • Issue of clearances for STOA / IEX
  • System performance Report(daily/monthly)
slide-21
SLIDE 21

21

  • Certification of availability of transmission Cos. on monthly

basis

  • Certification of Availability & PLF for Gencos on Annual basis.
  • Certification of backing down – monthly basis.

Keeping track of regulatory matters related to system

  • peration (MERC/ CERC correspondence)
  • Network enhancement proposals to STU on quarterly basis
  • Data base handling, Management information periodic

report preparation (Daily / Weekly / Monthly).

  • WRPC Meetings

Operation Coordination Committee Protection Committee Commercial Committee

  • State Grid Co-ordination committee meeting (GCCM)
slide-22
SLIDE 22

Highlights

– Web based outage Management program – Web based scheduling based on State level MoD – Large scale integration of Renewable Energy along with availability of about

95% of RE data at SLDC.

– MERC notified (Forecasting, Scheduling and Deviation Settlement for Solar

and Wind Generation) Regulations, 2018 Dt. 20th Jul 2018

– Tied up with NIWE for wind forecasting – Black Start Mock drills carried out regularly. – Quick restoration practices review taken regularly.

22

slide-23
SLIDE 23

Functions of Energy Accounting:-

 Deviation Settlement Mechanism  Monthly InSTS Loss computation  RECs in Maharashtra  Open Access  Other Miscellaneous Work

23

slide-24
SLIDE 24

 MERC issued another order for implementation of Intra-State ABT in Maharashtra in Case 42 of 2006 dated 17 May 2007.

  • Rates of settlement are not linked to frequency.
  • Rates of settlement are as per Weighted Average System

Marginal Price (WASMP).  MSLDC implemented FBSM from 1st Aug 2011 with state

  • MOD. (4 Discoms and 6 Merchant generator). At present,

there are 9 Discoms and 9 generators  Maharashtra is the first state to implement 15 mins Intra- State ABT in India.

Deviation Settlement Mechanism

slide-25
SLIDE 25

Metering inputs for FBSM Billing

slide-26
SLIDE 26

 The calculation of State Grid Transmission (InSTS) Losses is as

per the methodology prescribed by the MERC in its order in Case No. 31 of year 2006.

 InSTS Losses were calculated as per data received from

MSETCL, TATA, R-Infra, BEST, MSPGCL and WRPC by conventional method i.e. manually prepared vide excel sheets.

 MSETCL had developed Energy Accounting System module

from ERP software and from 1st November 2016, InSTS loss has been computed in ERP-EAS system.

Monthly InSTS Loss Computation

slide-27
SLIDE 27

InSTS Loss Of June-2018

slide-28
SLIDE 28
slide-29
SLIDE 29

3.78 3.64 3.51 3.36 3.10 3.38 3.32 3.53 3.01 2.85 3.21 3.22 3.35 3.05 3.02 2.87 0.00 0.50 1.00 1.50 2.00 2.50 3.00 3.50 4.00 0.00 2000.00 4000.00 6000.00 8000.00 10000.00 12000.00 14000.00 16000.00 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Total State Import Total Export Total RE Gen State Loss

InSTS Loss & RE Import for 2017-18

slide-30
SLIDE 30

RECs in Maharashtra

  • Maharashtra has the largest number of registered

generators for REC.

  • At present total number of 375 generators with 990

MW capacity are registered under REC in the state as

  • n March-2018.
  • MSLDC has been issuing EIRs for REC generators since

2010 well within time frames.

slide-31
SLIDE 31

Renewable Energy Certificate - software

slide-32
SLIDE 32

32

Open Access….

  • STOA as per Hon. MERC TOA/DOA Regulation 2016
  • SLDC

is Nodal Agency for granting

  • pen

access for EHV transmission system users

  • OA consumers connected to 33kV and below voltage level

respective DISCOM is the nodal agency for granting Open Access.

  • Around 250-300 applications per month were processed manually.
  • MSLDC being the first Load Dispatch Center to develop Web

based STOA software on cloud platform.

  • Applications are processed through Web Based STOA Software.
slide-33
SLIDE 33

FY Advance/FCFS Day Ahead/Same Day Power Total No of Applications Total Quantum (MUs) 2014-15 1227 1506 2733 18458 2015-16 2392 1575 3967 18193 2016-17 3152 4837 7989* 18866 2017-18 2127 2021 4148 15069

33

Grant of STOA and synchronization permission

slide-34
SLIDE 34

34

  • 1. Grant of Synchronization Permissions
  • 2. Issuance of Power Evacuation Certificates

to RE generators

  • 3. Deals with the Legal Cases under the

jurisdiction of Hon. CERC, MERC, HC, SC & APTEL

slide-35
SLIDE 35

SCADA, ADMINISTRATION & IT

slide-36
SLIDE 36

SCADA/EMS System at Maharashtra

SLDC Kalwa Main Control Centre ALDC Ambazari Back-up Control Centre

RTU

  • -

RTU RTU

  • -

RTU RTU

  • -

RTU

DC

RTU

  • -

RTU

MPLS network

IEC 104, 256 Kbps

DC DC DC

MPLS network

X-Terminals

2 MBPS LINK IEC 104, 128 Kbps

IEC 104, 256 Kbps IEC 104, 256 Kbps

WRLDC TPC REL

PRIMARY 10 MBPS LINK FOR MULTISITE BACKUP 10 MBPS LINK FOR MULTISITE

36

slide-37
SLIDE 37

SCADA System Configuration

slide-38
SLIDE 38

SCADA System highlights

Data Points Analog, Digital, Protection alarms and diagnostic alarms Sensor Intelligent Electronic Devices(IEDs) for each EHV Bay Protocol with SLDC Internationally accepted IEC-104 protocol, Vendor independent Input Protocols IEC 60870-5-104 RTU reset and diagnostics Possible Reporting Simultaneously to both SLDC and ALDC Architecture Simultaneous data acquisition with Main Back-up Configuration Hardware SUN Microsystems SUN T4-1, SUN NETRA 240 and Ultra-25 servers Monitors 24" LCD Operating System Solaris-10 Application Software Sinaut Spectrum latest version 4.5.1 Additional functionalities Intelligent Alarm Processor, State Estimator, Network management System, Contingency Evaluation and Bus Scheduler Software packages Database Administration JAVA based user friendly database administration Database Modifications Centralised database modifications Video Projection system BARCO 67" 4x2 Video Projection Cubes

slide-39
SLIDE 39

S.No. Details Quantity in Nos.

1 MSETCL RTUs 142 * 2 MSETCL SAS 20 3 Wind Farms 74 4 Solar Farms 39 5 Major IPP Stations 11 6 Bagasse (SSK- Sugar Factories) 89 6 Small IPP / CPP Stations 26 7 Tata Power Company Ltd. – RTUs (over ICCP) 27 8 R-Infra – RTUs (over ICCP) 7

Total 435

Abstract of RTUs /SAS in Maharashtra (As on 31-07-2018) * 220 kV level sub-station 80 nos. RTU and 50 nos. SAS integration work in progress Generation and Demand Overview, ICT / Line Loadings, Wind, Solar, Bagasse and Small CPP/IPP real time generation are available in public domain on SLDC website.

slide-40
SLIDE 40

Cyber Security - Existing Network Architecture

 Separate Network for SCADA and Other Applications.  Intrusion Prevention.  Web Content Filtering & Application Control.  Anti-Virus, Anti Spam, Anti-Malware.  Web Application Firewall (WAF).  VPN  Logging and Reporting.  Port Blocking.  Redundant Firewall / Router for MPLS SCADA Communication.  Prevention from DOS and DDOS Attack.  Country Based Blocking

slide-41
SLIDE 41

Cyber Security - Proposed IT Security Solution Architecture

 Integrated advanced threat protection solution.  Next Generation Firewall.  Anti-APT (Advanced Persistent Threat).  Zero-day Protection.  Network with DMZ.  High availability.  Deep packet inspection (DPI).  User & Application Control.  SandBox for file inspection.  Anti-Bot, Anti-Malware  Anti-ransomware for end- point protection.  Centralized Monitoring & Reporting.

slide-42
SLIDE 42

SLDC Finance and Accouting Human Resource  SLDC man power 140 Nos.

 Additional 41 nos. sanctioned by MSETCL Board in 2017 and 15 nos. posted.  Chief Engineer (SLDC) has been given powers for deputing its employees for training, workshops and seminar etc.  Any transfer/posting to/from SLDC is effected only after consent of Chief Engineer(SLDC) as MSETCL Board Resolution.  Certificate linked incentive is granted to SLDC as per Task Force under Pradhan Committee Report. (40 nos. Basic Level & 15 nos. Specialist Level Certified)  Every Employee Birthday is celebrated in SLDC

 SLDC finance and Accounting is separated within MSETCL

 Operating and Non-Operating accounts are independently operated by SLDC  Chief Engineer has been given financial power at par Executive Director  SLDC is filing its ARR petition to MERC since 2007  SLDC Fees and Charges approved by MERC are paid by DISCOM utilities

slide-43
SLIDE 43

Summary ARR (FY 2015-16 to FY 2019-20)

43

Particulars FY 2015-16 Approved Petition Total Expense MSLDC 3,636.36 3,794.44 Revenue 4,310.24 4,967.43 Revenue Gap/(Surplus) (673.88) (1,172.99) Impact of Truing Up (499.09)

Particulars FY 2016-17 FY 2017-18 FY 2018-19 FY 2019-20 Approved Petition Approved Petition Approved Petition Approved Petition Annual Fixed Charges (incl. NTI & Op. Income) 1484.17 686.72 1879.60 2332.15 1925.19 3124.97 1944.36 3665.04 Revenue 1484.17 1698.50 1879.60 1879.60 1925.19 3124.97 1944.36 3665.04 Revenue Gap/(Surplus) (1011.78) 452.55 Past period Truing up impact (1,058.33) Amortization of Surplus (529.16) (529.16) Net revised AFC 2,595.80 3,135.88

(Rs. Lakhs) (Rs. Lakhs)

Income from Annual SLDC Fees 675.72 Income from Monthly SLDC Operating Charges 1,884.54 SLDC Scheduling Charges 2,140.00 Rescheduling Charges 163.20 Other receipts 104.88 Total

4,967.43

(Rs. Lakhs)

slide-44
SLIDE 44

 22/0.44 kV indoor Sub-station capacity 2 x 500 kVA capacity  Gas Insulated SF6 HT Switchgear.  Charged with 2 nos. 22 kV incomer from different 220 kV sub-stations for redundancy and reliability.  2 x 250 kVA capacity Diesel Generator procurement in progress.

Auxiliary A.C. Supply

slide-45
SLIDE 45

 Modular Static transformer less Uninterruptable Power Supply.  Capable of providing clean and continuous Sine wave power supply upto 90kVA load.  Scalable according the connected load.  Energy efficient, silent operation, redundant, parallel operation, etc.

Uninterrupted Power supply

slide-46
SLIDE 46

 Network based CCTV system.  Complete monitoring of the periphery.  Also monitoring done by Commissioner of Police Navi Mumbai Control Room for City Surveillance  Electronic Access control system in SLDC premises

Security and Surveillance

slide-47
SLIDE 47

 Fire alarm and automatic water spray fire fighting system for office floor.  Automatic Fire/Gas Suppression System for equipment floor  Complete suppression of any type of fire/gas within maximum 1.5 minutes without any human interference.  Monitored by VESDA system and Fire/Gas controlled by Novec 1230 Gas agent which clean and eco friendly.

Fire Safety

slide-48
SLIDE 48

 Motorised Road Blocker installed as security measure citing the sensitivity to wards act of terrorism.

Security and Surveillance

Thank You

slide-49
SLIDE 49
slide-50
SLIDE 50

Summary of EIR For The FY 2017-18:

slide-51
SLIDE 51

51

slide-52
SLIDE 52

Issuance of Synchronization Permission to new generators (in MW) for FY 2017-2018

52

slide-53
SLIDE 53

53

Thank You