1
25thFOLD Meeting 07th August 2018
Maharashtra State Load Despatch Centre 25 th FOLD Meeting 07 th - - PowerPoint PPT Presentation
Maharashtra State Load Despatch Centre 25 th FOLD Meeting 07 th August 2018 1 State Load Despatch Centre Organization Structure within MSETCL Chairman & Managing Director MS Electricity Transmission Co. Ltd. Director (Operations) MS
1
25thFOLD Meeting 07th August 2018
Director (Operations) MS Electricity Transmission Co. Ltd. Chief Engineer (LD) MSLDC Superintending Engineer Operation Department ( OP ) Superintending Engineer
Energy Accounting (EA)
Superintending Engineer
(SCADA-ADM- IT )
Superintending Engineer
(ALDC Nagpur
Ambazari)
Executive Engineer
(Mumbai Sub-LDC)
2
Chairman & Managing Director MS Electricity Transmission Co. Ltd.
Maharashtra State Load Despatch Centre ( MSLDC) Intra State Generating Stations
RPL ,VIPL, IEPL
etc.) Intra State Transmission Licensees
Intra State Distribution Licensees
Sub LDC Ambazari,( Nagpur) Sub LDC Trombay (Mumbai)
4
OPERATION WING SCADA / IT / ADMINISTRATION WING ENERGY ACCOUNTING WING
5
6 Legend
Wind + Solar Karad Zone – 3335 MW Nashik Zone – 1815 MW
7 Legend
Installed Capacity Thermal – 26369 MW Hydro – 3386 MW Gas – 3143 MW Nuclear – 755 MW Non-Conventional Energy- 8476 MW Total- 42129 MW Area- 307,713 km2 Population- 112,372,972 Major Distribution Licensees-4
Discom-wise Electricity Consumers MSEDCL – 2,54,21,107 R-Infra D -30,10,000 TPC-D – 6,80,000 BEST- 10,02,299
Total – 3,01,13,406
There are 12 no’s of 765/400 KV sub-stations in the Maharashtra constructed under CERC and MERC transmission license.
8
As on 31st Mar. 2018
MSETCL :- Mumbai Transmission System :
1 220 9 5030 418.825 2 110 24 3900 743.936 33 8930 1162.761 RIL 1 220 8 3000 536.076 TPCL Total TPCL
Voltage Level EHV Substation Transformation Capacity (MVA) EHV LINES (CKT KM.) 765kV 1 3000 500 KV HVDC 2 3582 1504 400 KV 31 30045 8415.497 220 KV 223 53185 17788.427 132KV 322 28779.5 15454.409 110 KV 36 2330 1759.365 100 KV 38 2798 701.403 66 KV 7 127 594.8 Total 660 123846.5 46217.901
10
Jaigad Power Transmission Co. Ltd
SN Voltage (KV)
EHV Lines Ckm 1 400 1 4 330
Adani Transmission India Ltd. (ATIL)
SN Voltage (KV)
EHV Lines Ckm 1 765 2 400 2 436
Amravati Power Transmission Co. ltd.
SN Voltage (KV)
EHV Lines Ckm 1 400 1 4 220
Sinner Power Transmission Co. ltd.
SN Voltage (KV)
EHV Lines Ckm 1 400 1 2 104
Maharashtra Eastern Grid Power Transmission Co. ltd.
SN Voltage (KV)
EHV Lines Ckm 1 765 3 6 1160 2 400 2 60 ( MEGPTCL Transformation capacity is 3*1500 MVA)
Vidarbha Industries Pvt. Ltd
SN Voltage (KV)
EHV Lines Ckm 1 220 1 4 6
State Total
SN
MVA EHV Lines Ckm 1 708 140276.5 50232.738
(as on 31.03.2018)
Maharashtra System Peak Installed De-rated Capacity along with its CS Share Particulars Hydro Thermal Gas Nuclear NCE Total MSPGCL 2450 10170 672 180 13472 TPCL 447 1250 180 205 2082 REL 500 93 593 IPP / CPP 44 9125 388 7998 17555 CS(MS) 445 5323 1903 (*) 755 8426 Total 3386 26369 3143 755 8476 42129
(*) RGPPL 95 % capacity to MSEDCL, Not availed.
12
13
14
FY 2012-13 FY 2013-14 FY 2014-15 FY 2015-16 FY 2016-17 FY 2017-18 FY 2018-19 (as on June18) State Catered Demand 124001 125942 138997 144899 147879 154215 43366 MSEDCL 104585 106461 118774 123870 127220 132953 37367 MUMBAI 19416 19481 20223 21029 20658 21261 6000
FY 2012-13 FY 2013-14 FY 2014-15 FY 2015-16 FY 2016-17 FY 2017-18 FY 2018-19 (as on June 18 ) State Unrestricted Demand 18268 19635 20795 21414 23055 22994 23755 State CATERED Demand 17268 18803 20424 21064 22517 22994 23755 MSEDCL Demand 15261 17158 17694 18046 19745 19688 20340 MUMBAI Demand 3153 3217 3365 3368 3310 3592 3670
15
FY 2012-13 FY 2013-14 FY 2014-15 FY 2015-16 FY 2016-17 FY 2017-18 FY 2018-19 18268 19635 20795 21414 23055 22994 23755 15261 17158 17694 18046 19745 19688 20340 3153 3217 3365 3368 3310 3592 3670
Peak Demand in MW
State Unrestricted Demand MSEDCL Demand MUMBAI Demand FY 2012-13 FY 2013-14 FY 2014-15 FY 2015-16 FY 2016-17 FY 2017-18 FY 2018-19 124001 125942 138997 144899 147879 154215 43366 104585 106461 118774 123870 127220 133158 37367 19416 19481 20223 21029 20658 21057 6000
Energy Requirement in MUs
State Catered Demand MSEDCL MUMBAI
2.3 Monthly Maharashtra State Max Demand For the Period April- 2015 to June-2018
18
Monthly Maharashtra State Average Energy Req. For the Period Apr-2015 to June-2018
Load Curve for Peak Day in FY 2018-19
5000 10000 15000 20000 25000 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 TIME_SRNO MSEB_T MSEB_H MSEB_G WIND CS_RECE IPP Mumbai Generation SOLAR LOAD_SHEDDING
MSPGCL Hydro
Wind
CS Receipt IPP
Mumbai Generation Solar
MSPGCL GAS
MSPGCL THERMAL
Highest Peak on dt.30.05.2018 – 23755 MW
20
21
– Web based outage Management program – Web based scheduling based on State level MoD – Large scale integration of Renewable Energy along with availability of about
95% of RE data at SLDC.
– MERC notified (Forecasting, Scheduling and Deviation Settlement for Solar
and Wind Generation) Regulations, 2018 Dt. 20th Jul 2018
– Tied up with NIWE for wind forecasting – Black Start Mock drills carried out regularly. – Quick restoration practices review taken regularly.
22
23
The calculation of State Grid Transmission (InSTS) Losses is as
InSTS Losses were calculated as per data received from
MSETCL had developed Energy Accounting System module
3.78 3.64 3.51 3.36 3.10 3.38 3.32 3.53 3.01 2.85 3.21 3.22 3.35 3.05 3.02 2.87 0.00 0.50 1.00 1.50 2.00 2.50 3.00 3.50 4.00 0.00 2000.00 4000.00 6000.00 8000.00 10000.00 12000.00 14000.00 16000.00 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Total State Import Total Export Total RE Gen State Loss
32
FY Advance/FCFS Day Ahead/Same Day Power Total No of Applications Total Quantum (MUs) 2014-15 1227 1506 2733 18458 2015-16 2392 1575 3967 18193 2016-17 3152 4837 7989* 18866 2017-18 2127 2021 4148 15069
33
34
SCADA/EMS System at Maharashtra
SLDC Kalwa Main Control Centre ALDC Ambazari Back-up Control Centre
RTU
RTU RTU
RTU RTU
RTU
DC
RTU
RTU
MPLS network
IEC 104, 256 Kbps
DC DC DC
MPLS network
X-Terminals
2 MBPS LINK IEC 104, 128 Kbps
IEC 104, 256 Kbps IEC 104, 256 Kbps
WRLDC TPC REL
PRIMARY 10 MBPS LINK FOR MULTISITE BACKUP 10 MBPS LINK FOR MULTISITE
36
SCADA System Configuration
Data Points Analog, Digital, Protection alarms and diagnostic alarms Sensor Intelligent Electronic Devices(IEDs) for each EHV Bay Protocol with SLDC Internationally accepted IEC-104 protocol, Vendor independent Input Protocols IEC 60870-5-104 RTU reset and diagnostics Possible Reporting Simultaneously to both SLDC and ALDC Architecture Simultaneous data acquisition with Main Back-up Configuration Hardware SUN Microsystems SUN T4-1, SUN NETRA 240 and Ultra-25 servers Monitors 24" LCD Operating System Solaris-10 Application Software Sinaut Spectrum latest version 4.5.1 Additional functionalities Intelligent Alarm Processor, State Estimator, Network management System, Contingency Evaluation and Bus Scheduler Software packages Database Administration JAVA based user friendly database administration Database Modifications Centralised database modifications Video Projection system BARCO 67" 4x2 Video Projection Cubes
S.No. Details Quantity in Nos.
1 MSETCL RTUs 142 * 2 MSETCL SAS 20 3 Wind Farms 74 4 Solar Farms 39 5 Major IPP Stations 11 6 Bagasse (SSK- Sugar Factories) 89 6 Small IPP / CPP Stations 26 7 Tata Power Company Ltd. – RTUs (over ICCP) 27 8 R-Infra – RTUs (over ICCP) 7
Abstract of RTUs /SAS in Maharashtra (As on 31-07-2018) * 220 kV level sub-station 80 nos. RTU and 50 nos. SAS integration work in progress Generation and Demand Overview, ICT / Line Loadings, Wind, Solar, Bagasse and Small CPP/IPP real time generation are available in public domain on SLDC website.
Separate Network for SCADA and Other Applications. Intrusion Prevention. Web Content Filtering & Application Control. Anti-Virus, Anti Spam, Anti-Malware. Web Application Firewall (WAF). VPN Logging and Reporting. Port Blocking. Redundant Firewall / Router for MPLS SCADA Communication. Prevention from DOS and DDOS Attack. Country Based Blocking
Cyber Security - Proposed IT Security Solution Architecture
Integrated advanced threat protection solution. Next Generation Firewall. Anti-APT (Advanced Persistent Threat). Zero-day Protection. Network with DMZ. High availability. Deep packet inspection (DPI). User & Application Control. SandBox for file inspection. Anti-Bot, Anti-Malware Anti-ransomware for end- point protection. Centralized Monitoring & Reporting.
SLDC Finance and Accouting Human Resource SLDC man power 140 Nos.
Additional 41 nos. sanctioned by MSETCL Board in 2017 and 15 nos. posted. Chief Engineer (SLDC) has been given powers for deputing its employees for training, workshops and seminar etc. Any transfer/posting to/from SLDC is effected only after consent of Chief Engineer(SLDC) as MSETCL Board Resolution. Certificate linked incentive is granted to SLDC as per Task Force under Pradhan Committee Report. (40 nos. Basic Level & 15 nos. Specialist Level Certified) Every Employee Birthday is celebrated in SLDC
SLDC finance and Accounting is separated within MSETCL
Operating and Non-Operating accounts are independently operated by SLDC Chief Engineer has been given financial power at par Executive Director SLDC is filing its ARR petition to MERC since 2007 SLDC Fees and Charges approved by MERC are paid by DISCOM utilities
Summary ARR (FY 2015-16 to FY 2019-20)
43
Particulars FY 2015-16 Approved Petition Total Expense MSLDC 3,636.36 3,794.44 Revenue 4,310.24 4,967.43 Revenue Gap/(Surplus) (673.88) (1,172.99) Impact of Truing Up (499.09)
Particulars FY 2016-17 FY 2017-18 FY 2018-19 FY 2019-20 Approved Petition Approved Petition Approved Petition Approved Petition Annual Fixed Charges (incl. NTI & Op. Income) 1484.17 686.72 1879.60 2332.15 1925.19 3124.97 1944.36 3665.04 Revenue 1484.17 1698.50 1879.60 1879.60 1925.19 3124.97 1944.36 3665.04 Revenue Gap/(Surplus) (1011.78) 452.55 Past period Truing up impact (1,058.33) Amortization of Surplus (529.16) (529.16) Net revised AFC 2,595.80 3,135.88
(Rs. Lakhs) (Rs. Lakhs)
Income from Annual SLDC Fees 675.72 Income from Monthly SLDC Operating Charges 1,884.54 SLDC Scheduling Charges 2,140.00 Rescheduling Charges 163.20 Other receipts 104.88 Total
4,967.43
(Rs. Lakhs)
22/0.44 kV indoor Sub-station capacity 2 x 500 kVA capacity Gas Insulated SF6 HT Switchgear. Charged with 2 nos. 22 kV incomer from different 220 kV sub-stations for redundancy and reliability. 2 x 250 kVA capacity Diesel Generator procurement in progress.
Modular Static transformer less Uninterruptable Power Supply. Capable of providing clean and continuous Sine wave power supply upto 90kVA load. Scalable according the connected load. Energy efficient, silent operation, redundant, parallel operation, etc.
Network based CCTV system. Complete monitoring of the periphery. Also monitoring done by Commissioner of Police Navi Mumbai Control Room for City Surveillance Electronic Access control system in SLDC premises
Fire alarm and automatic water spray fire fighting system for office floor. Automatic Fire/Gas Suppression System for equipment floor Complete suppression of any type of fire/gas within maximum 1.5 minutes without any human interference. Monitored by VESDA system and Fire/Gas controlled by Novec 1230 Gas agent which clean and eco friendly.
Fire Safety
Motorised Road Blocker installed as security measure citing the sensitivity to wards act of terrorism.
51
52
53