M/s Supra Vessels & Engineers Pvt. Ltd. Company Profile About Supra Established in 1999, the company have carved a niche for themselves for delivering high-quality products and services. Centrally located in Bharatpur, closer
About Supra
- Established in 1999, the company have
carved a niche for themselves for delivering high-quality products and services.
- Centrally located in Bharatpur, closer to
the commercial hub of the country, New Delhi.
- 80% of client retention rate
- Delivered more than 70 + projects within
a span of 19 years.
- Employees’ strength of more than 100
Why Supra?
▪ Remarkable expertise in project execution and service delivery ̶ A team of skilled and technically sound professionals ▪ Broad array of services & ability to deliver any kind of project ̶ We have the ability to deliver any kind of Fabrication Project. ▪ Strong and liquid balance sheet ̶ You can be assured about the quality of the product within the given time frame ▪ History of consistent growth ̶ Since inception, the company has grown multiple folds. The company has proven track record of delivering technically advanced projects ▪ Association with Renowned Brands ̶ We have an impressive clients’ list, which gives us an edge over competitors.
What we do?
MECHANICAL FABRICATION
Supra Vessels
▪ Technological / Structural Steel Fabrication ▪ Material Handling Equipments for Cement/ Sugar/ Power ▪ Petrochemical Equipments (Reformer/ Heater Parts) ▪ Hydro Mechanical Equipments
About Supra
Our Respected Clientele
Engineering important milestone’s identification
A Glimpse of Similar Projects
- Project Name: Modular Penex
Unit
- Client: Honeywell Uop
- Owner: BORL Bina Refinery
- Duration of Project: 6 Months
- Tonnage of Project: 350 MT.
- Material: IS:2062 E350 BR.
- Challenges Faced & Key
Highlights of Project:
- Complete trial assembly of
Pipe Rack Modules required as per Project done in Workshop with complete bolting arrangement.
- All Welding done with FCAW
Process.
- No Site Mismatches
Observed.
- More than 30 types of
Structural Steel Sections handled during fabrication .
A Glimpse of Similar Projects
- Project Name: IOCL –INDMAX
Gasoline Desulphurization
- Client: TechnipFmc
- Owner : IOCL, Bongaigaon
Refinery
- Duration of Project: 10 Months
- Tonnage of the Project: 650 MT.
- Material: IS:2062 E250 BR.
Challenges Faced & Key Highlights of Project:
- Complete Trial Assembly of Pipe
Rack Modules required as per Project done in Workshop with complete bolting arrangement.
- All Welding done with FCAW
Process.
- More than 5000 holes bolted in one
grid wise assembly in workshop
- No Major Site Mismatches
Observed.
- More than 45 types of Structural
Steel Sections handled during Fabrication .
Result Oriented Approach:
- Apart from Fabrication Shop one
dedicated shop was allocated specially for trial assembly of Pipe Rack Modules.
- In order to meet delivery time &
quality requirements additional manpower & resources allocated resulting in timely completion of project.
Pictures of Pipe Rack Module During Dispatch
Pictures of Pipe Rack During Trial Assembly In Workshop
Photographs of Bolting Arrangement
Shop Presentation and Manufacturing Capacity
A look at the Workshop
- Covered / Shed Area 8000 Sq.
Yard
- Open Area 5000 Sq. Yard
- Total Area 13000 Sq. Yard
Installed Annual Production Capacity - 2000-2500 MT
Day & Night View of Workshop
Photographs of Recently Executed Fabrication Works
Photographs of Recently Executed Fabrication Works
Photographs of Recently Executed Fabrication Works
Photographs of Recently Executed Fabrication Works
Photographs of Recently Executed Fabrication Works
In House Quality Assurance Process
Quality Assurance Process
Manufacturing Process
Raw Material Procurement as per the requirement Material identification as per QAP Marking, Cutting, Fit-up Inspection Welding preparation & Set-up Inspection Review of WPS, WPQ & PQR as applicable Welding inspection (Visual & Dimension) DT & NDT Test on weld as applicable Fabrication Inspection as per QAP Review of various charts & reports as applicable Inspection during & after machining
- peration if any
Mockup assembly check-up/ assembly inspection
Contd
Quality Assurance Process
Execution of additional tests if applicable Final inspection as per fabrication
- Drgs. / General guide line
Checking of surface preparation & protection from corrosion of heat Visual Inspection of Painting process Final Painted Material inspection Job identification & match-make verification Final review of quality records as per QAP required Final clearance for job completion and for client inspection Delivery of the Product Mockup assembly check-up/assembly inspection