Lloyds Shoals Study Plan Meeting (FERC No. 2336)
January 16, 2019
Lloyds Shoals Study Plan Meeting (FERC No. 2336) January 16, 2019 - - PowerPoint PPT Presentation
Lloyds Shoals Study Plan Meeting (FERC No. 2336) January 16, 2019 Introduction Courtenay OMara, P.E. Southern Company 2 Study Plan Meeting Agenda 10:00 a.m. 12:00 p.m. Morning Session: Welcome, Introductions & Operations
January 16, 2019
2
3
Study Plan Meeting Agenda
Morning Session:
10:00 a.m. ‒ 12:00 p.m.
10:00 – 10:30 a.m.
10:30 – 11:00 a.m.
11:00 – 11:30 a.m.
11:30 a.m. – 12:00 p.m. Lunch:
12:00 p.m. ‒ 1:00 p.m.
Afternoon Session:
1:00 p.m. ‒ 5:00 p.m.
1:00 – 1:30 p.m.
1:30 – 2:00 p.m.
2:00 – 2:30 p.m.
2:30 – 3:00 p.m.
3:00 – 3:30 p.m.
3:30 – 5:00 p.m.
4
Study Plan Development Schedule
Comments on PAD and SD1, and Study Requests Study Plan Meeting GPC Files Proposed Study Plan
FERC Issues SD2 if Necessary
Comments
Proposed Study Plan DUE DATE GPC Files Revised Study Plan
File Reply Comments within 15 days
45 30 90 Nov 5, 2018 Dec 20, 2018 Jan 16, 2019
Mar 20, 2019
FERC Issues Study Plan Determination
No Disputes
First Season Studies 30 30 20 Apr 19, 2019 May 20, 2019 May 2019-Apr 2020
Notice of Study Dispute If Necessary
20
Jun 10, 2019 Study Dispute Resolution Process
70
Resolution of Study Issues
If Necessary
5
Content of Study Request (18 CFR § 5.9(b)) 1. Goals and objectives of study proposal 2. Relevant resource management goals 3. Relevant public interest 4. Existing information, and need for additional information 5. Nexus between project operations and effects 6. Study methodology and generally accepted practice 7. Level of effort and cost
6
Study Plan Outline by Resource Area
7
Master Schedule for Study Implementation
Activity Start Date Completion Date
Conduct Field Studies
May 2019 Apr 2020 Study Progress Report (All Studies)
Study Report (First Season of Studies)
Study Results Meeting
8
Project Boundary
Project Boundary Georgia Power Project Recreation Facilities Public/Private Recreation Access
1
2
Lloyd Shoals Project (FERC No. 2336)
Generating Capacity 18 MW Number of units: 6 (horizontal, Francis-type)
620 cfs/unit or 3,720 cfs total plant capacity Full reservoir storage: 107,000 acre-feet Normal operating range: 527 to 530 feet Average annual inflow: 1,732 cfs Operation mode: Modified run-of-river Minimum flow: 400 cfs or inflow, whichever is less Spillway Capacity: 16,770 cfs
3
Lloyd Shoals Project Works Flow Release Sequence
Lake Jackson
Spillway Auxiliary Spillway Substation Powerhouse
4
Lloyd Shoals Generating Unit Cross-section and Terminology
Lake Jackson / Reservoir Ocumlgee River Operating Unit: Turbine, Generator and Shaft Headworks/Intake Discharge/Tailrace
5
Inflow = outflow all the time
where steady power was more important than peaking power
power or no power Reservoir Storage and Effect on Operations Small Reservoirs – Run-of-River Operation
6
daily Reservoir Storage and Effect on Operations Medium Reservoirs – Modified Run-of-River Operation
Inflow = outflow on a weekly basis
Lake Jackson (useable storage = 74,750 acre-feet)
7
Inflow ≠ outflow
flow periods for use in low flow periods Reservoir Storage and Effect on Operations Large Reservoirs – Storage Operation
https://media.defense.gov/2017/Nov/29/2001849723/-1/-1/0/171129- A-CE999-006.JPG
Lake Lanier (Useable Storage = 1,087,600 acre-feet)
and recreation
8
Hydroelectric Project Purpose Comparison Lanier Basin 1,040 square miles Jackson Basin 1,400 square miles Lanier Storage 2,554,000 acre-ft Jackson Storage 107,000 acre-ft
9
Large Drainage Basin – Small Amount of Storage
Atlanta Covington Lawrenceville McDonough
10
20-Year Average Monthly Calculated Inflow January 1997 through December 2016
500 1000 1500 2000 2500 3000 3500 Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov Dec Flow (cfs) Average Flow Into Lake Jackson
11
518.00 519.00 520.00 521.00 522.00 523.00 524.00 525.00 526.00 527.00 528.00 529.00 530.00 531.00 532.00 500 1000 1500 2000 2500 3000 3500 4000 5/12/2013 5/13/2013 5/14/2013 5/15/2013 5/16/2013 5/17/2013 5/18/2013 5/19/2013 Reservoir Elevation Flow (cfs)
Lloyd Shoals Operations Example NORMAL Inflow Week of 1,547 cfs, Average Annual Inflow = 1,732 cfs
Average Annual Inflow (cfs)
12
Lloyd Shoals Operations Example DROUGHT Period of 313 cfs, Average Annual Inflow = 1,732 cfs
Average Annual Inflow (cfs)
518.00 519.00 520.00 521.00 522.00 523.00 524.00 525.00 526.00 527.00 528.00 529.00 530.00 531.00 532.00 400 800 1200 1600 2000 2400 2800 3200 3600 4000 7/24/2011 8/13/2011 9/2/2011 9/22/2011 10/12/2011 11/1/2011 11/21/2011 12/11/2011 Flow (cfs) Daily Average Inflow (cfs) Hourly Discharge (cfs) Reservoir Elevation (ft)
13
518.00 519.00 520.00 521.00 522.00 523.00 524.00 525.00 526.00 527.00 528.00 529.00 530.00 531.00 532.00 5000 10000 15000 20000 25000 30000 35000 40000 45000 12/19/2015 12/21/2015 12/23/2015 12/25/2015 12/27/2015 12/29/2015 12/31/2015 1/2/2016 Flow (cfs) Daily Average Inflow (cfs) Hourly Discharge (cfs) Reservoir Elevation
Lloyd Shoals Operations Example HIGH Inflow Period of 17,544 cfs, Average Annual Inflow = 1,732 cfs
Average Annual Inflow (cfs)
14
Lake Jackson Elevation 2007-2016 Typical Range Between 527 to 530 Feet
522 524 526 528 530 532 J F M A M J J A S O N D Elevation (ft) Daily Maximum Elevation (ft) Daily Minimum Elevation (ft)
Typical Operating Range
15
Spillway Gate Enhancement / Operational Improvements
16
Obermeyer Gates Significantly Reduce Frequency of Reservoir Fluctuations
replace spillway flashboards
Lake Jackson fluctuations
elevation range caused by high flow events
for plant personnel
more water for reliable, clean, and renewable generation
17
Operations Outside of Normal Pool Elevation Range
18
1
2
Study Objectives
recreational opportunities at the Project
Jackson and in the Lloyd Shoals tailrace area
meet current and future recreational demand
Program to address land use practices, including erosion, and protect environmental resources within the project boundary
3
Issues Identified during Scoping
recreation in the Ocmulgee River
in the project boundary to meet current and future recreation demand, including special events (e.g. fishing tournaments) at the Project
address land use practices, including erosion, and to protect environmental resources within the project boundary
4
Study Modification Requests and Comments
Resources Division (WRD):
data were calculated in the FERC Form 80 from 2015
including the tailrace boat ramp facility, to ensure they adequately support user needs
between leased and non-leased lands
5
Study Modification Requests and Comments (Continued)
map with respect to the project boundary
including any erosion due to project-related recreational use
6
Existing Information
tournament information
for Georgia
developed for the state-wide water planning process
7
Study Area
around Lake Jackson and the Lloyd Shoals tailrace area
and Henry Counties
Project Recreation Facilities Project Boundary Public/Private Recreation Access
8
Project Recreation Facilities
Butts County Jasper County
Ocmulgee River Park Lloyd Shoals Park Tailrace Fishing Pier Jane Lofton Public Access Area
Lake Jackson
9
Project Recreation Facility Amenities
Park/Facility County Area within PB Amenities Lloyd Shoals Park Butts 5 acres Boat ramp, dock, picnic tables, pavilion, playground, swimming beach, restrooms, fishing pier, bank fishing Jane Lofton Public Access Area Butts 0.7 acre Bank fishing Tailrace Fishing Pier Butts 0.6 acre Barrier-free ramp, fishing pier Ocmulgee River Park Jasper 4 acres Boat ramp, picnic tables, bank fishing
10
Methodology Overview
11
Methodology – Recreational Usage Trends and Demand
405 Recreation Report completed in 2015
records, staff observations, and visitor counts/surveys
from Georgia Bass Chapter Federation reports
12
Methodology – Existing Recreation Facilities and Opportunities
recreation access to project waters
boundary, and show on map
13
Methodology – Recreation Field Surveys
5 days in spring and summer 2019
14
Recreation Survey Form
Site info County of origin, group size, ages Duration and frequency of visits Reasons for visit Species fished for Quality of facilities Improvements desired Other parks used
15
Methodology – Future Recreation Demands
recreational demand based
and review of the SCORP and other relevant plans and information
the estimated carrying capacity of the existing project recreation facilities
16
Methodology – Land Use Assessment
zone extending 2,000 ft beyond
leased Georgia Power lands within project boundary
regional, and local resource management plans
17
Schedule for Recreation and Land Use Study
Activity Deadline Begin literature-based review and field surveys May 2019 Complete literature-based review and field surveys October 2019 File progress report January 31, 2020 File study report May 19, 2020
18
Georgia Power Shoreline Management Mission – Georgia Power is committed to preserving the scenic, environmental, and recreational values of our lakes
http://georgiapowerlakes.com/lakejackson/
19
Georgia Power Shoreline Management Program
removal, grading, and dredging
setbacks, docks, seawalls, boat houses, gazebos, etc.
20
Permitting Program
permits for construction on Georgia Power lakes and property
before beginning any construction, renovation, clearing, tree removal, grading, etc.
permitted within 25 feet of the shoreline
21
Shoreline Management Guidelines
enjoyment of lake while limiting aesthetic impact to shoreline
configuration of shoreline structures (e.g., decks, docks, boat slips, boathouses, seawalls)
GP requires the placement
all seawalls…helps reduce undermining and restores shoreline habitat
22
Compliance Program
contractors
permits, termination of access lease, legal action
23
24
25
Study Objectives
botanical resources occurring in the Lloyd Shoals project area
habitats occurring in the project area
community types, including wetlands
Shutterstock.com
26
Issues Identified during Scoping
project-related recreation, and shoreline development on upland habitat, reservoir wetland, and littoral habitats, and associated wildlife
well as project-related recreation, on state species of concern in the vicinity of the project
activities, including shoreline management, and project- related recreation on non-native invasive botanical and wildlife species
27
Study Modification Requests and Comments
aquatic habitat planning and addressing future issues
WRD of aquatic nuisance vegetation treatment
and assessing potential project-related effects
each species’ flowering or fruiting period
28
Sources of Existing Information
Communities of Georgia
terrestrial and aquatic invasive nuisance vegetation
29
Study Area
around Lake Jackson and tailrace area downstream
and wetlands, a zone extending 2,000 ft beyond the project boundary
Project Recreation Facilities Project Boundary
30
Methodology – Review of Existing Information
activities for Lake Jackson and project lands
31
Methodology – Field Reconnaissance Survey
representative communities for field reconnaissance
riparian communities from a boat and/or walking on Georgia Power or public lands
submersed aquatic vegetation within project boundary
within project boundary, including project recreation facilities
Wikipedia CC BY-SA 3.0
32
Schedule for Terrestrial, Wetland, and Riparian Resources Study
Activity Deadline Begin field studies and literature review May 2019 File progress report January 31, 2020 Complete field studies and literature review April 2020 File study report May 19, 2020
33
34
35
Study Objectives
species currently under federal status review, with known records of occurrence near the Project
presently occurring near the Project
36
Issues Identified during Scoping
project-related recreation, on federally listed endangered, threatened, and candidate species, and their habitat, in the vicinity of the project
U.S. Fish and Wildlife Service
Michaux’s Sumac – Federally Endangered
37
Study Modification Requests and Comments
Shoals tailrace as part of the Water Resources Study because Robust Redhorse is under federal status review for listing
RTE species coincides with each species’ flowering or fruiting period, as appropriate, for accurate identification
listed species or their habitats be filed as “Not for Public Disclosure, Privileged”
38
Sources of Information and Data
Section rare element data portal
Online System
and technical reports
as part of the Fish and Aquatic Resources Study
Shutterstock.com Nate Tessler, NANFA.org
Altamaha Shiner – GA Threatened Bald Eagle – GA Threatened
39
Aquatic RTE Species
Scientific Name Common Name Georgia Status Federal Status Location Alasmidonta arcula Altamaha arcmussel T
Ocmulgee River Pyganodon gibbosa Inflated floater
Lake Jackson Somatogyrus alcoviensis Reverse pebblesnail
review
Alcovy River upstream
Cyprinella xaenura Altamaha shiner T
Moxostoma robustum Robust redhorse E
Under review
Ocmulgee River
a Not listed or under review but considered to be at-risk in Altamaha River basin.
40
Terrestrial RTE Species
Scientific Name Common Name Georgia Status Federal Status Occurs at Project Amphianthus pusillus Pool spritea T LT
Dwarf hatpinsa E
Black-spored quillworta E LE
Michaux’s sumac E LE
Granite stonecropa T
Relict trillium E LE
Southern hognose snake T
Bald eagle T
Picoides borealis Red-cockaded woodpecker E LE
41
Study Area
boundary around Lake Jackson and tailrace area downstream, including the project recreation facilities
Project Recreation Facilities Project Boundary
42
Methodology – Review of Existing Information
as well as those potentially occurring in the project area
43
Methodology – Field Surveys
using existing maps, aerial photography, and literature review
early summer, during flowering/fruiting periods of RTE plants
Terrestrial, Wetland, and Riparian Resources Study
44
Schedule for RTE Species Study
Activity Deadline Begin field studies and literature review May 2019 File progress report January 31, 2020 Complete field studies and literature review April 2020 File study report May 19, 2020
45
Relict Trillium – Federally Endangered
Pete Pattavina, U.S. Fish and Wildlife Service
1
2
Study Objectives
quality, including dissolved oxygen (DO) concentrations and water temperature, in Lake Jackson and the tailrace area within the project boundary
water uses downstream in the Ocmulgee River
3
Issues Identified during Scoping
including DO concentrations and water temperature, in Lake Jackson and the Ocmulgee River downstream from the Project
development and levels in Lake Jackson, including assess the need for measures to address cyanobacteria levels
4
Study Modification Requests and Comments
chemistry parameters to support GEPD’s hydrodynamic and water quality model for the Ocmulgee River
boundary for the proposed water quality studies
standards compliance
sources including state and federal agencies
5
Sources of Existing Information and Data
Jackson at multiple locations from 2000 to 2017
member Jackson Lake Association
and land use practices upstream of Lake Jackson and their potential influences on water quality, eutrophication, cyanobacteria, and harmful algal blooms in the reservoir
Georgia Water Planning District (2017)
6
Study Area
Lloyd Shoals tailrace area downstream to end of project boundary
upstream of Lake Jackson
downstream of project boundary based on available water quality data
7
Methodology Overview
blooms in Lake Jackson
8
Georgia Power Lake Jackson Water Quality Sampling 2000-2017
Winter Spring Summer Fall Year Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017
Profile & chemistry
data at 6 stations Profile & chemistry data at <6 stations
Profile data only at
6 stations
9
Lake Jackson Water Quality Monitoring Stations
stations for several decades
seasonally 2000-2017
seasonally 2014-2017
Lloyd Shoals Dam
Station Vertical Profiles Water Chemistry JA1 JA2 JA3 JA4 JA5 JA6 GEPD station Georgia Power water quality station
10
Vertical Profiles of Lake Jackson – Forebay
Thermocline DO Chemocline
Bottom of Intake
Summer
11
Lake Jackson Seasonal Water Chemistry Parameters
Parameter Alkalinity (mg/L) Ammonia (mg/L) Calcium (mg/L) Chlorophyll a (µg/L) Fecal coliform bacteria (MPN colonies/100 ml) Hardness (mg/L) Iron (mg/L) Magnesium (mg/L) Manganese (mg/L) Nitrate (mg/L) Nitrite (mg/L) Total Phosphorus (mg/L) Turbidity (NTU)
12
Water Quality Monitoring in the Lloyd Shoals Tailrace Area
station in May 2019
at depth of 1 meter (m)
recorded every 60 minutes May 2019-April 2020
1-m depth
nitrate-nitrite, organic nitrogen, total phosphorus,
phosphorus
Proposed Area for Monitoring Station
13
Analysis of Information and Data
evaluate effects of operations during summer and performance of existing passive draft tube aeration system
14
Literature Review of Cyanobacteria Occurrence and Blooms
15
Schedule for Water Resources Study
Activity Deadline Begin field studies and literature review May 21, 2019 File progress report January 31, 2020 Complete field studies and literature review April 2020 File study report May 19, 2020
16
17
18
Study Objectives
shoreline and littoral-zone aquatic habitat (as part of Geology and Soils Study shoreline survey)
freshwater mussels and snails
for primary sport fish species in Lake Jackson
habitat in the Ocmulgee River downstream of the Project
mortality at the Lloyd Shoals powerhouse
Shutterstock.com
19
Issues Identified during Scoping (SD2 additions in italics)
(e.g., docks, seawalls, etc.) on fish habitat and aquatic resources in Lake Jackson, including addressing the need for habitat improvements in Lake Jackson
sport fish species in Lake Jackson, including Largemouth Bass and stocked Striped Bass
mussel habitat downstream in the Ocmulgee River
Ocmulgee River, including addressing the need for fish passage (American Eel and American Shad) at the Project
20
Issues Identified during Scoping (Continued)
turbine-induced mortality at the Project
flora and fauna within the project boundary, and the effects of continued project operation and maintenance activities and project-related recreation on non-native invasive aquatic species
concern in the vicinity of the Project
21
Study Modification Requests and Comments
Fisheries Service (NMFS) requested a study of American Eel abundance and upstream movements
habitat survey
estimate of total number of fish entrained annually by species, size class, and season
entrainment and impingement
22
Key Sources of Existing Information
instream flow (IFIM) study in the Ocmulgee River downstream
database of bass catch statistics in Georgia reservoirs
movements of riverine fish in the Ocmulgee River downstream
existing Candidate Conservation Agreement with Assurances
Ocmulgee River basin
23
Summary of GDNR Electrofishing Data for Lake Jackson, 2013-2017
PAD, Table 11:
Source: GDNR
24
Habitat-Discharge Relationships for Target Fish Species and Life Stages in Ocmulgee River Instream Flow (IFIM) Study
GDNR and FWS
from site-specific field studies
Model (PHABSIM) produced discharge versus weighted usable area relationships for each species life stage
Average PMWUA Average PMWUA Discharge (cfs)
SPAWNING/REARING SEASON (May-Oct) NON-SPAWNING SEASON (Nov-Apr)
PMWUA = Percent of Maximum Weighted Usable Area
25
Freshwater Mollusk Occurrences near Lloyd Shoals Project, 2008-2014
PAD, Table 15:
26
Study Area
around Lake Jackson and the Lloyd Shoals tailrace area
to Juliette Dam (19 miles)
Upstream extent
fish migration
Project Boundary
27
Methodology Overview
28
Methodology – Freshwater Mollusk Survey
abundance, and species richness of native mollusk community
Conservation Agreement for Mollusks of Altamaha River Basin
1. Lake Jackson mussel survey 2. Reverse Pebblesnail survey upstream but near project boundary 3. Lloyd Shoals tailrace area mussel survey
Altamaha Arcmussel
GDNR Wildlife Resources Division
29
Methodology – Freshwater Mollusk Survey
hand grubbing, snorkeling, SCUBA, or surface-supplied air
30
Methodology – Habitat for Primary Sport Fish Species
species in Lake Jackson, including Largemouth Bass and Striped Bass
literature for primary sport fish species
31
Methodology – Habitat for Primary Sport Fish Species
locations in the reservoir collected annually
growth characteristics of primary sport fish species
abundance, catch per unit effort, and other descriptive statistics
Striped Bass based on water temperature, DO, and other habitat suitability information from the scientific literature
project waters during the current license term
32
Methodology – Downstream Riverine Habitat
to water temperature, DO, and other relevant habitat suitability information for riverine species from the scientific literature
developed in previous IFIM study for comparison of habitat availability across discharges ranging from 50 to 3,500 cfs
information for Robust Redhorse, other riverine fish and invertebrate species, and diadromous fishes to further characterize current conditions and the potential for impacts of continued project operations to the riverine aquatic community
33
Methodology – Fish Entrainment Evaluation
number of fish entrained annually, their size distribution and species composition, and seasonal variation in entrainment rates
survival tests conducted at other projects with similar head and turbine design characteristics to those at Lloyd Shoals
34
Methodology – Fish Entrainment Evaluation
hydroelectric sites with consideration of the physical,
Striped Bass and hybrid bass management and experimental stocking of American Shad
35
Schedule for Fish and Aquatic Resources Study
Activity Deadline Begin field studies and literature review May 2019 File progress report January 31, 2020 Complete field studies and literature review April 2020 File study report May 19, 2020
36
37
38
Study Objectives
migrating to Lloyd Shoals Dam
seasonality and any correlation with discharge, water temperature, and percent of moon illumination
Lloyd Shoals Dam
Atlantic States Marine Fisheries Commission
39
Scoping Issue and Study Requests
the Ocmulgee River, including addressing the need for fish passage (American Eel and American Shad) at the Project
abundance and upstream movements
proposed modifications to reflect existing information
40
American Eel (Anguilla rostrata) Life Cycle
water then migrating to sea to spawn
currents toward coast
and rivers
surmounting vertical obstacles
migrating upstream; occupy wide range of habitats for several years
and to Sargasso Sea to spawn
41
American Eel Abundance in the Ocmulgee River
Station 1 Station 2 Station 3 Station 4 Miles below Lloyd Shoals Dam 0.6 – 1.1 4.2 – 4.8 14.0 – 15.0 27.6 – 28.2 Quarterly Catch (no. of fish) April 11 26 1 10 June 30 29 23 15 September 4 19 5 10 December 2 11 6 2 Total 47 85 35 37 Quarterly CPUE (fish/0.5 hr) April 7.3 14.3 0.2 6.0 June 19.3 17.0 3.8 7.6 September 2.7 11.3 0.8 6.3 December 1.0 6.7 1.0 1.3 Lengths (mm) Mean = 343; range: 168 – 825
American Eel Electrofishing Catch Statistics below Lloyd Shoals Dam, 1988:
Source: EA Engineering, Science, and Technology, Inc. (1990)
42
Study Area
Lloyd Shoals Dam downstream about 1.2 river miles to the Hwy 16 bridge
Lloyd Shoals Dam
43
Methodology
6 months of a 1-year period
June to encompass onset and probable peak of upstream migration (after water temperature rises above 15°C)
before water temperature falls below 15°C
Water temperatures between 15 and 25 °C, suitable for migration
2017 2018
Ocmulgee River Water Temperature
44
Methodology - Electrofishing
Mar-Jun and Sep-Oct
daylight during off-peak releases
representative habitats and both sides of river
electrofishing runs
electrofishing runs in wadeable habitats
Study Area
45
Methodology – Eel Trapping
month in Mar-Jun and Sep-Oct
consecutive nights in up to five locations near base of dam
attraction flow, and bucket in readily accessible locations
South Carolina DNR Kleinschmidt Associates Google Earth
46
Methodology – Data Analysis
weighed, caudal fin-clipped, a Passive Integrated Transponder (PIT) tag inserted, and released to study area
volumetrically and a subsample measured for total length
mark-recapture population estimates will be presented
temperature, discharge, and percent moon surface illumination
47
Schedule for American Eel Abundance and Upstream Movements Study
Activity Deadline Begin field studies and literature review May 2019 File progress report January 31, 2020 Complete field studies and literature review April 2020 File study report May 19, 2020
48
Julie Devers, U.S. Fish and Wildlife Service
49
50
Piedmont
Atlanta
Coastal Plain
SC GA AL FL
Ecoregions of Georgia
Lloyd Shoals Project
51
Study Objectives
erosion and sedimentation in Lake Jackson and the Lloyd Shoals tailrace
project-related recreation on reservoir and tailrace shoreline erosion and sedimentation
review on the relationship between shoreline structural stabilization practices and littoral-zone fish habitat
52
Representative Shorelines
53
Issues Identified during Scoping
recreation on reservoir and tailrace shoreline erosion and sedimentation
and accumulation within Lake Jackson, including contaminated sediment and evaluation of the need for measures to address sedimentation
54
Study Modification Requests and Comments
project shoreline areas
shoreline development affect sport fish species such as Largemouth Bass, Black Crappie, and sunfish
and duration, for planning aquatic plantings and fish stockings inside the project boundary
55
Study Modification Requests and Comments (Continued)
through a comparison of new and historical data, such as bathymetry, topography, and/or aerial photography
reservoir and tailrace shorelines indicating whether land is privately or project-owned
available information pertaining to each dredging event
56
Other Scoping Comments
consequences for water quality of Lake Jackson
sediment in Lake Jackson with respect to mercury and PCBs
sedimentation with respect to water and accumulated pollutants
57
Study Area
boundary around Lake Jackson and tailrace area downstream
watersheds upstream
for literature review
Project Recreation Facilities Project Boundary
58
Study Area Sections for Shoreline Survey
selection of 500-ft shoreline sites
recreation facility represented
MR TR
25 25 25 25
SR AR TC
6
Number of survey sites
59
Shoreline Survey Form
Site info Riparian zone Bank stability and protection Stabilization practices Erosion causes
(project & non-project related)
Shoreline fish habitat Land uses
60
Methodology – Analysis of Existing Information and Data
since 1993; identify changes & trends in representative areas
sedimentation using data on reservoir fluctuation frequency
and their effects on littoral-zone aquatic habitat in reservoirs
dredging events (purpose, location, methods, volume)
privately or project-owned
Lake Jackson, including mercury and PCBs in sediment
61
Schedule for Geology and Soils Study
Activity Deadline Begin temporal change analysis and literature review May 21, 2019 Conduct shoreline survey Summer 2019 File progress report January 31, 2020 Complete data analysis and literature review February 28, 2020 File final study report May 19, 2020
62
63
64
Source: Hudson (1997). Knights of Spain, Warriors of the Sun
65
66
Study Objectives
review
the National Register of Historic Places (NRHP)
the operation and maintenance of the Project or by activities conducted along the shoreline of the project reservoir
67
Issues Identified during Scoping
properties that are included in, or eligible for inclusion in, the NRHP
archaeological and historic resources at the Project
68
Study Modification Requests and Comments
project boundary
from the GDNR Historic Preservation Division (HPD) and potentially affected tribes
69
Study Background – Resource Management Goals
(HPD) administers state historic preservation under Georgia’s State Historic Preservation Plan 2017-2021: Integrating Innovation with Preservation
consistent with the plan include:
historic properties
structures of the project dam and powerhouse and historical information regarding the development of the Project
70
Study Background – Existing Information and Data
annually as part of existing Cultural Resources Management Plan (CRMP):
managed according to CRMP maintenance guidelines
71
Archaeological Investigations
Brockington and Associates (1989)
72
NRHP-Eligible Lloyd Shoals Powerhouse
Prior to 1983 transformer explosion and fire (EDAW, 1990) Powerhouse today, with upper floor half the size of the original The interior of the first floor today remains remarkably similar to historic photographs
73
Study Area
and project boundary
boundary with landowner permission
powerhouse, and operations areas within project boundary Project Recreation Facilities Project Boundary
74
Methodology
NRHP
Standards and Guidelines for Archaeological Surveys
project works
75
Tribal Consultation
tribes identified by FERC as having cultural, religious, or historical ties to the project area
designee”
studies, report findings, and the Historic Properties Management Plan (HPMP) as appropriate
76
Schedule for Cultural Resources Study
Activity Deadline Begin field studies and literature-based review May 2019 File progress report January 31, 2020 Complete field studies and literature-based review March 2020 File final study report May 19, 2020
77