Levy Nuclear Project Jeff Lyash President & CEO Progress - - PowerPoint PPT Presentation
Levy Nuclear Project Jeff Lyash President & CEO Progress - - PowerPoint PPT Presentation
Levy Nuclear Project Jeff Lyash President & CEO Progress Energy Florida Progress Energy Florida A Balanced Solution for the Future A Balanced Solution for the Future 2 Pl Planning to Meet Floridas Energy Needs i t M t Fl id
A Balanced Solution for the Future A Balanced Solution for the Future
2
Pl i t M t Fl id ’ E N d Planning to Meet Florida’s Energy Needs
3
V l til F l P i Volatile Fuel Prices
4
Fuel Diversity to Serve Florida’s Energy Needs y gy
Energy Generation by Fuel Type (percent of total)
Source: FPSC Review of 2008 10-Year Site Plans
5
Policy Decisions Promote Timely Results
Inception to Construction
6
2006 Fl id N l I t t A t
Pre-construction and licensing
2006 Florida Nuclear Investment Act
Capacity cost recovery clause (CCRC) Costs are recovered dollar for dollar
During construction
g
AFUDC is recovered through CCRC 8.848% AFUDC rate is locked until commercial operation Annual prudence reviews
p
Completion
Base rate adjustment at in-service for capital costs ROE and capital structure based on last approved levels ROE and capital structure based on last approved levels
(currently 11.75% ROE on 57.83% common equity)
Project cancellation cost recovery
Full recovery of costs incurred if project is cancelled
Full recovery of costs incurred if project is cancelled
7
L N l P j t Levy Nuclear Project
Location Technology # of units Capacity (MW) In Service Levy County, Florida Westinghouse AP1000 2 ~2,200 total 2016 - 2018
- 8 miles NE of our Crystal River
- 8 miles NE of our Crystal River
Energy Complex
- Signed engineering,
procurement & construction (EPC) agreement with Westinghouse and Shaw
- Negotiating joint ownership
with multiple parties (1) with multiple parties (1)
- Site prep and pre-construction
begin ~2010/11; safety-related construction begins 2012/13 g
(1) Confidentiality obligations preclude us from discussing this further until the negotiations are completed.
8
EPC A t Hi hli ht EPC Agreement Highlights
Signed December 2008 with Westinghouse Electric Company and
St & W b t b idi f Th Sh G Stone & Webster, a subsidiary of The Shaw Group
Two 1,105-net MW, AP1000 nuclear reactors EPC contract price = $7 65B EPC contract price = $7.65B
> 50% of which is fixed price or firm price with agreed-upon
escalation factors
Includes various performance incentives, penalties, warranties, Includes various performance incentives, penalties, warranties,
liquidated damage provisions and parent guaranties
Total estimated cost for the two generating units = ~$14B
Includes land price plant components construction labor regulatory Includes land price, plant components, construction, labor, regulatory
fees and reactor fuel for the two units, and
Forecasted inflation, owner costs, financing costs and contingencies
Additional $3B estimated for associated transmission facilities Additional $3B estimated for associated transmission facilities 9
L N l P j t A ti iti Levy Nuclear Project Activities
EPC Agreement executed on 12/31/08 EPC Agreement executed on 12/31/08 SCA Hearing (state siting) began 2/23/08
NRC COLA schedule pending
NRC COLA schedule pending Nuclear cost recovery proceeding under way Post EPC organization being formed Positioning for early construction
Barge, temporary haul path
Transmission project effort progressing
10
R l t Ti li f L P j t Regulatory Timeline for Levy Project
Mar. May July Sept. Oct.
2010
June
2012/13 2008
Aug. April y y p
2010 2012/13 2008
g Filed Hearing Vote Order
Need Case
p Filed Hearing Order Filed Hearing Vote Order
Need Case Cost Recovery
Issued Filed (18 month review)
Site Certification
Issued Filed (3 - 4 year review)
Combined License
11
K t S Keys to Success
Policy and regulatory stability
♦ Recognition of nuclear as a clean energy source ♦ Recognition of nuclear power’s role in energy security ♦ Resource commitment to support timely licensing/permitting
Financial continuity
♦ Financial tools to maintain utility strength during construction ♦ Options to mitigate early customer price impacts ♦ Options to mitigate early customer price impacts
Workforce development
♦ To build the plant p ♦ To operate the plant
Supply chain development
pp y p
12