L Project Update
New Design Recommendations Overall Project Update
January 15, 2019
L Project Update New Design Recommendations Overall Project Update - - PowerPoint PPT Presentation
L Project Update New Design Recommendations Overall Project Update January 15, 2019 Project Overview Sandy Rehabilitation, Core Capacity Improvement, Additional Projects Brooklyn Union Sq 1 Av Mid River Bedford Av Harrison Pl CBH 62
January 15, 2019
2
Sandy Rehabilitation, Core Capacity Improvement, Additional Projects
Union Sq Station 1 Av Station CBH 61 & Av B Substation Av D Shaft Mid River Pump Room N7 St Shaft
Manhattan
Brooklyn EAST RIVER
CBH 62 Bedford N.6 Substation Bedford Av Station Maspeth Av Substation Bushwick Cut/ Myrtle Viaduct Harrison Pl Substation 6 Av Station
Canarsie Tunnel contract work Additional projects planned to support / coincide with L work
3
Canarsie Tunnel a critical link in system and severely damaged in Sandy
concrete liner
225,000 riders each weekday
saltwater
electrical equipment
4
Bedford Ave. to 8th Ave
more
professors performed a peer review to examine the tunnel, rehabilitation needs and project goals in collaboration with MTA & WSP
project objectives with less customer impact
and determined all the goals of the initial plan will be met with the new plan
5
6
Executive summary of recommendations & overall project scope
WHAT’S NEW WHAT DOESN’T CHANGE
benchwalls
instead of within benchwall
and tunnel conditions
monitoring
track elements (i.e. ties, third rail)
7
Expert academic team focused on four key areas of opportunity
system design
cables
benchwall
halogen fireproof material
compromised and fortify using fiber reinforced
benchwall integrity
8
Racking cables is common technology around the world
Hong Kong London Riyadh
wall and rack
penetration poses no risk to tunnel lining
bolts than individually bolting cables to the tunnel lining
9
New approach saves time while maintaining safety
Proposed racking system
cementitious or other material
10
Evaluating condition to best support structural integrity
Benchwall in good condition
cementitious or other material
concrete:
including in NYS
& RFK Bridge
11
Industry-accepted approach for strengthening concrete
FRP on RFK Bridge
including those set for silica mitigation
plans:
12
Less demolition required, less silica
pumps
gates and sealing capability for
elevation
13
Ensure and strengthen tunnel resiliency for future flood events
Watertight gate at Queens Midtown Tunnel
silica
14
tunnel lining with repairs
15
Bench wall in poor condition
from the ties to the rail – will be made
16
Installation of stop arm
lead to a resilient, long-lasting infrastructure improvement in the form of a new tunnel
17
All goals of the initial plan will be met with this new plan
work
future upgrades
periodic, basis
18
Significant benefits to project, customers and agency
focus on design and implementation
and technical experts aligned and working together
19
Cross-functional Work Groups moving recommendations forward
groups across all project teams
1st Ave Stations
20
New proposal achieves same outcome
including:
21
Additional, planned capital projects to continue
approach of the rehabilitation of the tunnel that meets the original project goals while avoiding a complete shutdown and reducing customer impact
with Board and public
22