king ing e edw dward memori rial al park ark fores resho
play

King ing E Edw dward Memori rial al Park ark Fores resho hore - PowerPoint PPT Presentation

King ing E Edw dward Memori rial al Park ark Fores resho hore re Communi nity ty L Lia iais ison n Working ing Gro roup 17 Ju 7 July 20 2019 19 Staff Tideway ay Tidewa way Communi unicati ations ns Rebe becca a


  1. King ing E Edw dward Memori rial al Park ark Fores resho hore re Communi nity ty L Lia iais ison n Working ing Gro roup 17 Ju 7 July 20 2019 19

  2. Staff Tideway ay Tidewa way Communi unicati ations ns • Rebe becca a Major or Tidewa way Project t Manag anager r • Ania a Gonz nzal alez CVB VB • Domin minic ic Love velo lock • Project t Manag anager • June une Saunde aunders • Communi unity ty Relati ations ns Of Officer 2

  3. CON CONTE TENTS Env Environm nment ntal updat update (no noise se and and ai air qual quality) Legacy acy and and Communit ity Progr ogres ess report Upco pcomi ming ngwor works 3

  4. Envi vironmen ental tal 4

  5. Noise se & Ai Air Quality ity N o exceedances - Ma May & y & Ju June 2019 KEMPF/AA/2 KEMPF/AA/1 Long-term unattended air monitoringlocation Long-term unattended noise monitoringlocation Short-term attended noise & vibration monitoring location 5

  6. Le Legacy y an and Co Commun munity y Relati elation ons 6

  7. 2019 Oarsome Challenge 20 2018 18 • 5 e 5 event nts • 360 360 bag bags of rubbi ubbish • 124 v volunt unteer ers • 300 300 vol olunt nteer hr hrs 9

  8. WIN FOR WAPPING PIRATES Tideway Teams Smash the Oarsome Challenge! On Thursday 27 June 16 teams from across Tideway took part in this year’s Oarsome Challenge, raising more than Wapping pirates £34,000 for London Youth Rowing and Tideway’s three main King Edward Memorial Park Foreshore Site charity partners. Teams of eight rowers sported fancy dress while rowing a 13- mile stretch of the River Thames. This year, the route was from Shadwell in the East, to Putney Bridge in the West, before a final sprint following the university Boat Race course to the finish line at Chiswick Bridge. Rowing in perfect summer conditions, the Wapping Pirates were the fastest team, completing the race section in 29 mins and 10 seconds, followed closely by The Putney Varsity Disgraceful 8 in 30 mins. Chambers Wharf site

  9. Tideway staff gave this school an insight to the many jobs within the project, they were then challenged to design, build and cost a tunnel to specifications. Volunteers from were on hand to support and assess the results. The team who came closest to the specifications and within budget were presented with reusable water bottles Ju July 20 2019 19 Stephe ephen T n Timms M MP Des esign & & Enginee eering C Chal hallen enge e

  10. PRI RIDE 2019 2019 13

  11. BREAKI AKING BARRI RRIERS 201 2019 Breaking Barriers has restarted with two schools rowing at Surrey Docks Water sports centre, whilst other students visited Chambers Wharf on Friday 28 June. A participant said, “ It was a thrilling and exciting experience. I got to see the shaft and the start of the tunnel-it was really good to see it in person. I have started rowing at Surrey Quays and I’m really enjoying it, it’s different. I am looking forward to mentoring at Chambers Wharf.” 12 week programme led by staff volunteers in partnership with London Youth Rowing 10

  12. ‘ Flo lori rida Pub a Publi lic H Hea ealth lth Stu Studen ents ts learn a about T Tideway way “Thank you so much to the Tideway group for providing us with such a great tour and taking the time to teach us about their work with the sewage system!” “As public health students, it is interesting to see how many people and the work they do play a role in the overall health of the community! The tour today really showed us how one seemingly small system can make a huge impact. Thanks again” @tidewaylondon 13

  13. ‘ WELCOME TO REGATTA LONDON CENTRAL LONDON - 29 SEPTEMBER 2019 For further information about Regatta London visit: https://regatta.london/ 13

  14. Prog ogress ess repo eport Ju June 2019 e 2019 13

  15. AERIAL SHOT June 2019 16

  16. Adit G dit Grouting ng W Works Ju June e 20 2019 19

  17. July 2019 Hinterland Adit Grouting works 18

  18. View of site June 2019

  19. 75 columns to be installed in the archaeological area Some plant moved off site in August July 2019 Deep soil mixing works 20

  20. Arc rchae haeology Sheet heet P Pile R e Rem emoval 72 of the 86 sheet piles have been removed. Different methods of extraction have been implemented to remove the sheet piles. July 2019

  21. Programme me King Edward Memorial Park Foreshore Programme Overview PROGRAMME OVERVIEW 2018- 2017 2018 2019 2020 2021 2022 2023 2021 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Install cofferdam completed Relieving platform completed Building Slab is tidally affected Additional Sheet Piles Impact and Vibro piling Prepare cofferdam platform & DSM Diaphragm Walls Extended hours for long pours / Removal of spoil tidally affected Excavate shaft Extended hours for long pours / Removal of spoil tidally affected Build Shaft Extended hours for long pours Hydraulic Structures Extended hours for long pours Extended hours for long pours Connect into Sewer Build Adit Remove cofferdam Removal tidally affected Moving parts and tests Landscaping Removal tidally affected Standard Working Hours 08:00 to 18:00, Monday to Friday. Extended Working Hours 05:00 to 08:00 Monday to Friday 18:00 to 22:00 Monday to Friday This work or movement of marine plant will occur only when necessary due to tidal restrictions or long concrete pours Mobilisation and Demobilisation Hours Up to one hour before and after our standard hours and 30 minutes after extended hours working 07:00 to 08:00 and 18:00 to 19:00 Monday to Friday or 22:-00-22:30 Monday to Friday Maintenance periods On occasions due to health & safety requirements we will also carry out maintenance between 08:00 to 17:00 Saturdays and 10:00 to 16:00 Sundays 14

  22. Pro rogre ress • The cofferdam is complete • Surcharge of the cofferdam has been completed and the results have been positive. • Cofferdam Hoarding works have been completed • Soil mixing is progressing and is 90% complete and on programme • Drilling for grout block installation commenced on the 9th April and is due for completion in late September • Extraction of sheet piles in the Hinterland is almost complete 15

  23. Upco coming ming wo work 21

  24. Upc Upcom oming wor orks ks • D-walling is due to commence in October • Backfilling of the cofferdam • Surfacing • Guide walls • Mobilisation of the equipment for the d-walling 22

  25. Diaphrag aphragm Walling ing - Begins ins Octo tobe ber 20 2019 19 26

  26. KEMP MPF – Non Ma Mater erial Am l Amen endment to to th the e Develo elopment C Consent Or Order er (DCO) O) • Additional ground improvement works mean that construction at the site will take longer than anticipated To minimise the additional construction duration, Tideway propose to submit a Non • Material Amendment (NMA) to the DCO for a change to the main tunnel alignment • If approved, this will mean the main tunnel will be constructed approximately 15m further southeast than the alignment approved under the DCO • The realignment will mean the tunnel will not pass directly through the KEMPF drop shaft, but will instead pass to the east of the shaft. A new connection tunnel (approx 15m in length) will then connect the drop shaft to the main tunnel This will enable the drop shaft and main tunnel to be built at the same time and will • minimise the additional construction duration at KEMPF All changes will be approx 60m below ground • • This NMA will not change the size or location of the shaft or any above ground features 27

  27. KEMP MPF – Non Ma Mater erial Am l Amen endment to to th the e Develo elopment C Consent Or Order er (DCO) O) Schematic of DCO alignment and NMA alignment • NMA submission will be made to the Secretaries of State in June / July • Local residents will be notified and will be able to make comments on NMA 28

  28. KEMP MPF – Non Ma Mater erial Am l Amen endment to to th the e Develo elopment C Consent Or Order er (DCO) O) Diagram of the Main Tunnel Realignment which will be submitted. 29

  29. Questi stions? s? 27

  30. If If yo you have ve any ny quest stio ions o s or e enquir irie ies s please se contact ct the he Tid Tidewa way y Helpdes esk on: n: Tel elep ephon one: 080 08000 3080 8080 80 Email: il: Helpdesk@ k@Tideway.Lon London on 28

  31. THANK HANK YOU King ing E Edw dward Memori rial al Park ark Fores resho hore re Communi nity ty L Lia iais ison n Working ing Gro roup 8 Ma 8 May 20 2019 19 29

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend