King ing E Edw dward Memori rial al Park ark Fores resho hore - - PowerPoint PPT Presentation

king ing e edw dward memori rial al park ark fores resho
SMART_READER_LITE
LIVE PREVIEW

King ing E Edw dward Memori rial al Park ark Fores resho hore - - PowerPoint PPT Presentation

King ing E Edw dward Memori rial al Park ark Fores resho hore re Communi nity ty L Lia iais ison n Working ing Gro roup 17 Ju 7 July 20 2019 19 Staff Tideway ay Tidewa way Communi unicati ations ns Rebe becca a


slide-1
SLIDE 1

King ing E Edw dward Memori rial al Park ark Fores resho hore re Communi nity ty L Lia iais ison n Working ing Gro roup 17 Ju 7 July 20 2019 19

slide-2
SLIDE 2

2

Staff

Tideway ay

  • Rebe

becca a Major

  • r
  • Ania

a Gonz nzal alez Tidewa way Communi unicati ations ns

CVB VB

  • Domin

minic ic Love velo lock

  • June

une Saunde aunders

  • Project

t Manag anager

  • Communi

unity ty Relati ations ns Of Officer Tidewa way Project t Manag anager r

slide-3
SLIDE 3

3

CON CONTE TENTS

Env Environm nment ntal updat update (no noise se and and ai air qual quality) Legacy acy and and Communit ity Progr

  • gres

ess report Upco pcomi ming ngwor works

slide-4
SLIDE 4

4

Envi vironmen ental tal

slide-5
SLIDE 5

5

Noise se & Ai Air Quality ity

No exceedances - Ma May & y & Ju June 2019

KEMPF/AA/1

KEMPF/AA/2

Long-term unattended noise monitoringlocation Long-term unattended air monitoringlocation Short-term attended noise & vibration monitoring location

slide-6
SLIDE 6

6

Le Legacy y an and Co Commun munity y Relati elation

  • ns
slide-7
SLIDE 7
slide-8
SLIDE 8

9

20 2018 18

  • 5 e

5 event nts

  • 360

360 bag bags of rubbi ubbish

  • 124 v

volunt unteer ers

  • 300

300 vol

  • lunt

nteer hr hrs

2019 Oarsome Challenge

slide-9
SLIDE 9

WIN FOR WAPPING PIRATES

Tideway Teams Smash the Oarsome Challenge! On Thursday 27 June 16 teams from across Tideway took part in this year’s Oarsome Challenge, raising more than £34,000 for London Youth Rowing and Tideway’s three main charity partners. Teams of eight rowers sported fancy dress while rowing a 13- mile stretch of the River Thames. This year, the route was from Shadwell in the East, to Putney Bridge in the West, before a final sprint following the university Boat Race course to the finish line at Chiswick Bridge. Rowing in perfect summer conditions, the Wapping Pirates were the fastest team, completing the race section in 29 mins and 10 seconds, followed closely by The Putney Varsity in 30 mins.

Wapping pirates King Edward Memorial Park Foreshore Site Disgraceful 8 Chambers Wharf site

slide-10
SLIDE 10

Stephe ephen T n Timms M MP

Tideway staff gave this school an insight to the many jobs within the project, they were then challenged to design, build and cost a tunnel to specifications.

Ju July 20 2019 19 Des esign & & Enginee eering C Chal hallen enge e

Volunteers from were on hand to support and assess the results. The team who came closest to the specifications and within budget were presented with reusable water bottles

slide-11
SLIDE 11

13

PRI RIDE 2019 2019

slide-12
SLIDE 12

10

BREAKI AKING BARRI RRIERS

201 2019

Breaking Barriers has restarted with two schools rowing at Surrey Docks Water sports centre, whilst other students visited Chambers Wharf on Friday 28 June. A participant said, “It was a thrilling and exciting experience. I got to see the shaft and the start of the tunnel-it was really good to see it in person. I have started rowing at Surrey Quays and I’m really enjoying it, it’s different. I am looking forward to mentoring at Chambers Wharf.”

12 week programme led by staff volunteers in partnership with London Youth Rowing

slide-13
SLIDE 13

13

Flo lori rida Pub a Publi lic H Hea ealth lth Stu Studen ents ts learn a about T Tideway way

“Thank you so much to the Tideway group for providing us with such a great tour and taking the time to teach us about their work with the sewage system!” “As public health students, it is interesting to see how many people and the work they do play a role in the overall health of the community! The tour today really showed us how one seemingly small system can make a huge impact. Thanks again” @tidewaylondon

slide-14
SLIDE 14

13

WELCOME TO

REGATTA LONDON CENTRAL LONDON - 29 SEPTEMBER 2019

For further information about Regatta London visit: https://regatta.london/

slide-15
SLIDE 15

13

Prog

  • gress

ess repo eport

Ju June 2019 e 2019

slide-16
SLIDE 16

16

June 2019 AERIAL SHOT

slide-17
SLIDE 17

Adit G dit Grouting ng W Works Ju June e 20 2019 19

slide-18
SLIDE 18

18

Hinterland Adit Grouting works July 2019

slide-19
SLIDE 19

June 2019 View of site

slide-20
SLIDE 20

20

Deep soil mixing works July 2019 75 columns to be installed in the archaeological area Some plant moved off site in August

slide-21
SLIDE 21

July 2019

72 of the 86 sheet piles have been removed. Different methods of extraction have been implemented to remove the sheet piles.

Arc rchae haeology Sheet heet P Pile R e Rem emoval

slide-22
SLIDE 22

14

Programme me

King Edward Memorial Park Foreshore Programme Overview

PROGRAMME OVERVIEW 2018- 2021

Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4

Install cofferdam Relieving platform

Building Slab is tidally affected

Additional Sheet Piles

Impact and Vibro piling

Prepare cofferdam platform & DSM

Diaphragm Walls

Extended hours for long pours / Removal of spoil tidally affected

Excavate shaft

Extended hours for long pours / Removal of spoil tidally affected

Build Shaft

Extended hours for long pours

Hydraulic Structures

Extended hours for long pours Extended hours for long pours

Connect into Sewer Build Adit Remove cofferdam

Removal tidally affected

Moving parts and tests Landscaping

Removal tidally affected

Standard Working Hours

08:00 to 18:00, Monday to Friday.

Extended Working Hours

05:00 to 08:00 Monday to Friday 18:00 to 22:00 Monday to Friday This work or movement of marine plant will occur only when necessary due to tidal restrictions or long concrete pours

Mobilisation and Demobilisation Hours

Up to one hour before and after our standard hours and 30 minutes after extended hours working 07:00 to 08:00 and 18:00 to 19:00 Monday to Friday or 22:-00-22:30 Monday to Friday

Maintenance periods

On occasions due to health & safety requirements we will also carry out maintenance between 08:00 to 17:00 Saturdays and 10:00 to 16:00 Sundays

2022 2023

completed completed

2017 2018 2019 2020 2021

slide-23
SLIDE 23

15

Pro rogre ress

  • The cofferdam is complete
  • Surcharge of the cofferdam has been completed and the

results have been positive.

  • Cofferdam Hoarding works have been completed
  • Soil mixing is progressing and is 90% complete and on

programme

  • Drilling for grout block installation commenced on the

9th April and is due for completion in late September

  • Extraction of sheet piles in the Hinterland is almost

complete

slide-24
SLIDE 24

21

Upco coming ming wo work

slide-25
SLIDE 25

22

Upc Upcom

  • ming wor
  • rks

ks

  • D-walling is due to commence

in October

  • Backfilling of the cofferdam
  • Surfacing
  • Guide walls
  • Mobilisation of the equipment

for the d-walling

slide-26
SLIDE 26

26

Diaphrag aphragm Walling ing - Begins ins Octo tobe ber 20 2019 19

slide-27
SLIDE 27

27

KEMP MPF – Non Ma Mater erial Am l Amen endment to to th the e Develo elopment C Consent Or Order er (DCO) O)

  • Additional ground improvement works mean that construction at the site will take longer

than anticipated

  • To minimise the additional construction duration, Tideway propose to submit a Non

Material Amendment (NMA) to the DCO for a change to the main tunnel alignment

  • If approved, this will mean the main tunnel will be constructed approximately 15m further

southeast than the alignment approved under the DCO

  • The realignment will mean the tunnel will not pass directly through the KEMPF drop shaft,

but will instead pass to the east of the shaft. A new connection tunnel (approx 15m in length) will then connect the drop shaft to the main tunnel

  • This will enable the drop shaft and main tunnel to be built at the same time and will

minimise the additional construction duration at KEMPF

  • All changes will be approx 60m below ground
  • This NMA will not change the size or location of the shaft or any above ground features
slide-28
SLIDE 28

28

KEMP MPF – Non Ma Mater erial Am l Amen endment to to th the e Develo elopment C Consent Or Order er (DCO) O)

Schematic of DCO alignment and NMA alignment

  • NMA submission will be made to the Secretaries of State in June / July
  • Local residents will be notified and will be able to make comments on NMA
slide-29
SLIDE 29

29

KEMP MPF – Non Ma Mater erial Am l Amen endment to to th the e Develo elopment C Consent Or Order er (DCO) O)

Diagram of the Main Tunnel Realignment which will be submitted.

slide-30
SLIDE 30

27

Questi stions? s?

slide-31
SLIDE 31

28

If If yo you have ve any ny quest stio ions o s or e enquir irie ies s please se contact ct the he Tid Tidewa way y Helpdes esk on: n: Tel elep ephon

  • ne: 080

08000 3080 8080 80 Email: il: Helpdesk@ k@Tideway.Lon London

  • n
slide-32
SLIDE 32

29

THANK HANK YOU

King ing E Edw dward Memori rial al Park ark Fores resho hore re Communi nity ty L Lia iais ison n Working ing Gro roup 8 Ma 8 May 20 2019 19