KentuckyWired Investigation Status Report Program Review and - - PowerPoint PPT Presentation

kentuckywired investigation status report
SMART_READER_LITE
LIVE PREVIEW

KentuckyWired Investigation Status Report Program Review and - - PowerPoint PPT Presentation

KentuckyWired Investigation Status Report Program Review and Investigations Committee June 7, 2019 Contributing staff Van Knowles Jeremy Skinner Katherine Halloran Susannah Stitzer Sarah Ortkiese Joel Thomas Richard Shufelt History Of


slide-1
SLIDE 1

KentuckyWired Investigation Status Report

Program Review and Investigations Committee

June 7, 2019

Contributing staff Van Knowles Katherine Halloran Sarah Ortkiese Richard Shufelt Jeremy Skinner Susannah Stitzer Joel Thomas

slide-2
SLIDE 2

2

History Of KentuckyWired

2011/2012  Concept development by Center for Rural Development 2013  SOAR presentation, RFP for consultant 2014  Procurement and interim contract 2015  Detailed planning, negotiations, restructured contracts, and bond sale

slide-3
SLIDE 3

3

History Of KentuckyWired

2015-2018  Construction with costly delays 2018  Planned completion in July 2018  Settlement of claims, ongoing construction 2019  KCNA borrowing to fund settlement 2020  Revised completion in October

slide-4
SLIDE 4

KentuckyWired Project Structure

4

State of Kentucky

Project Company/KWIC (nonprofit) Operations Company/KWOC

(indirectly owned by consortium)

Design-Builder Service Company Wholesaler OpenFiber

slide-5
SLIDE 5

KentuckyWired Financial Structure

  • A common P3 financing method
  • “Non-recourse” bonds and equity

return supported by availability payments (AP) over 30 years

  • APs supported by appropriations

5

slide-6
SLIDE 6

KentuckyWired Financial Structure

  • Assumed existing agency broadband

spending would pay for APs

  • But unable to use K-12 funds
  • Wholesale revenues originally

considered supplemental income

6

slide-7
SLIDE 7

Delays And Payments

  • Claims of supervening events caused

delays and extra costs

  • Settlement agreed December 2018
  • Estimated claims of $191 million negotiated

to $101 million

  • New completion date October 2020
  • New borrowing of $110 million authorized
  • APs locked into original schedule

7

slide-8
SLIDE 8

Wholesale Revenues

  • Network designed with extra fiber to lease
  • Macquarie projected more than $1 billion

wholesale revenue for state

  • Revenue projection is uncertain
  • Revenue could cover shortfalls and extra

expenses

8

slide-9
SLIDE 9

Major Conclusions

  • Financing and funding
  • Project structure and risks
  • Policies and procedures
  • Project Justification

9

slide-10
SLIDE 10

Financing And Funding Conclusion

10

KentuckyWired faces significant funding challenges, most of which should have been anticipated. These include possible revenue sharing, loss of expected K-12 participation, substantial costs outside the availability payments, and variations in market prices.

slide-11
SLIDE 11

Financing And Funding Detailed Findings

  • Availability payments
  • Cover operations & maintenance costs, debt

service, and equity return

  • Structured to match state’s internet spending

(state agencies, higher education, K-12)

  • Subject to adjustments annually
  • Estimated to total $1.15 - $1.2 billion

11

slide-12
SLIDE 12

Financing And Funding Detailed Findings

  • Shortfalls in funding of APs
  • Example: Failure to obtain K-12 contract

potentially represents 45 percent of funds needed for APs

  • Wholesale revenues could make up for

the shortfall

  • Center for Rural Development might receive

a significant portion of the state’s wholesale revenue share

12

slide-13
SLIDE 13

Financing And Funding Detailed Findings

  • Examples of additional costs not

covered by APs

  • System refreshes
  • Two required system refreshes with a total

estimated cost of $87.4 million

  • Settled and future supervening event

claims

  • Will be funded with up to $110 million in

additional borrowing

13

slide-14
SLIDE 14

Financing And Funding Detailed Findings

  • Tax-exempt financing saved money, but
  • ther tax-exempt financing options might

have saved more

  • The reliability of the wholesale revenue

projections is unknown

  • The project is sensitive to changes in

broadband market prices

14

slide-15
SLIDE 15

15

Project Structure And Risks Conclusion

The chosen risk allocation might have been the only way to obtain financing and lower costs. State officials handled some risks poorly.

slide-16
SLIDE 16

16

Project Structure And Risks Detailed Findings

  • Risk allocation favored private partners, but

rating agencies found it reasonable

  • Rewritten contract structure similar to original

Macquarie proposal but cost more

  • 37% cost increase from Macquarie’s proposal,

approximately $74 million more

  • Failure to make contractual availability

payments would damage state’s credit rating

  • Establishing Project Company had no effect on

state’s risks or obligations

slide-17
SLIDE 17

Project Structure And Risks Detailed Findings

  • State’s consultant predicted many key

risks that were poorly managed

  • Pole attachment agreements
  • State highway rights-of-way
  • Private easements
  • Settlement terms described as reasonable
  • State agencies and other potential

customers have doubts about service

17

slide-18
SLIDE 18

Policies And Procedures Conclusion

18

Although the contract negotiations and bond sale technically followed all legislative oversight rules, the bond issue might have been inconsistent with the 2014 branch budget bill. Statutes do not appear to provide formal consequences for this and other apparent violations of policy.

slide-19
SLIDE 19

Policies And Procedures Detailed Findings

  • Post-award negotiations were typical of a

P3, but the Model Procurement Code at the time did not address this contractual structure

19

slide-20
SLIDE 20

Policies And Procedures Detailed Findings

  • Financing might have been inconsistent

with 2014 budget

  • Several 2015 meetings of Capital Projects and

Bond Oversight Committee were canceled, so the committee did not review financing

  • Other violations of law or policy
  • No formal consequences specified

20

slide-21
SLIDE 21

Project Justification Conclusion

21

High-speed broadband was seen as necessary, and state officials chose to focus on the middle mile to stimulate economic development and to increase broadband competition.

slide-22
SLIDE 22

Project Justification Detailed Findings

  • Economic alternative to private sector middle-

mile broadband

  • Increase competition and internet speed
  • Lower costs
  • High-speed broadband is an expected public

utility like electricity

  • No reliable information on existing middle mile
  • Last mile is a major expense
  • It is unknown if KentuckyWired will facilitate last

mile expansion

22