The Evolution of the AIA Documents From 2007 to 2017
Kenneth Cobleigh, Managing Director and Counsel for AIA Robin G. Banks, Goldberg & Banks, P.C.
A’17
AIA Conference on Architecture 2017 April 27-29, Orlando
Kenneth Cobleigh, Managing Director and Counsel for AIA Robin G. - - PowerPoint PPT Presentation
The Evolution of the AIA Documents From 2007 to 2017 Kenneth Cobleigh, Managing Director and Counsel for AIA Robin G. Banks, Goldberg & Banks, P.C. A17 AIA Conference on Architecture 2017 April 27-29, Orlando Agenda AIA Contract
A’17
AIA Conference on Architecture 2017 April 27-29, Orlando
2017?
Overview
documents? A. 1888 B. 1911 C. 1987, when Howard Goldberg first became outside counsel to the Documents Committee
First AIA Contract Document 1888
A. Architects B. Lawyers C. Insurance advisors D. Howard Goldberg’s family and friends E. All of the above
AIA Contract Documents? A. To create fair & balanced documents B. To balance competing interests C. To put risk where it is best managed D. All of the above
The Documents Committee takes all of the following steps when drafting AIA Contract Documents:
A’17
AIA Conference on Architecture 2017 April 27-29, Orlando
2017 Release
2017 Release
Guaranteed Maximum Price *
Guaranteed Maximum Price *
017 (formerly A107-2007), Standard Abbreviated breviated Form of Agreement Between Owner and Contractor
rt Form of Agreement Between Owner and Contractor
* with new Insurance Exhibit
A’17
AIA Conference on Architecture 2017 April 27-29, Orlando
2017 Release
lex Proje ject ct
breviat ated ed Form m of Agreement Between Owner and Architect
A’17
AIA Conference on Architecture 2017 April 27-29, Orlando
2017 Release
Guide for Sustainable Projects AIA Document D503™ (2011) SP versions of standard AIA Documents (2007-2009) Sustainable Projects Exhibit AIA Document E204-2017
located and coordinated within a single exhibit
A’17
AIA Conference on Architecture 2017 April 27-29, Orlando
parties
delayed or failed certification, and consequential damages) and the exhibit now allows us publish just one version of the key document.
A’17
AIA Conference on Architecture 2017 April 27-29, Orlando
AIA Document A101-2017 Exhibit A, Insurance and Bonds
A’17
AIA Conference on Architecture 2017 April 27-29, Orlando
Most, but t not
to the Exhibit:
A’17
AIA Conference on Architecture 2017 April 27-29, Orlando
builder’s risk “all-risk” completed value or equivalent policy form
parties to shift burden to Contractor
Contractor’s one-year period for correction of the Work
In addition, the parties may agree that the Owner will purchase and maintain certain optional extended property coverages:
The parties may also agree that the Owner will purchase and maintain certain other optional coverages:
Contractor Required Coverages for all Projects:
Contractor Required Coverages depending on the nature of the Project:
Other coverages the Contractor might obtain:
Payment and Performance Bonds
Key Take Away:
requirements
need ignore optional coverage sections and fill in required policy limits/sub-limits and penal sums for bonds.
cancellation or expiration of coverage
by that party
purchase required coverage
New provisions on adjustment and settlement of loss covered by property insurance:
allocation of proceeds
allocation
Owner and Contractor is resolved per the Claims and Disputes provisions
2017 Release
A’17
AIA Conference on Architecture 2017 April 27-29, Orlando
transmission of digital data, and
information contained in a Model, without first having established the protocols, is at the using or relying party’s own risk and without liability to any other project participant
executed”
services not performed”
eliminate automatic entitlement to OH&P and prompt parties to discuss and negotiate a termination fee
arguing over lost OH&P calculation
Earlier editions of Owner-Contractor Agreements had parenthetical note prompting parties to insert liquidated damages and incentive provisions Liquidated Damages can be used to offset waiver of consequential damages 2017 Documents have separate fill points to prompt the parties to discuss liquidated damages provisions and incentive provisions
17 § 1.6.1 Except as otherwise provided in Section 1.6.2, where the Contract Documents require one party to notify or give notice to the other party, such notice shall be provided in writi ting ng to the designated representative of the party to whom the notice is addressed and shall be deemed to have been duly served if delivered in person, by mail, by courier, or by electronic transmission if a method for electronic transmission is set forth in the Agreement.
201-20 2017 17 § 1.6.2 1.6.2 Notice of Claims as provided in Section 15.1.3 shall be provided in writing and shall be deemed to have been duly served only if delivered to the designated representative
providing proof of delivery.
A’17
AIA Conference on Architecture 2017 April 27-29, Orlando
3.3.1 3.3.1 The Contractor can object to means or methods specified and can propose alternative means and methods.
A’17
AIA Conference on Architecture 2017 April 27-29, Orlando
17 Secti tion
– More permissive of direct communications between the owner and contractor. – Owner must make Architect aware of direct communications
2017 § 5.1.6 5.1.6) – Provisions pertaining to the calculation of progress payments clarified and simplified to clearly delineate the basis for each progress payment.
2017 § 5.1.7 5.1.7) – Now in a new independent section – Specification of retainage amount – Items that should be excluded from retainage – How retainage may be reduced at or before substantial completion.
A’17
AIA Conference on Architecture 2017 April 27-29, Orlando
3.10.1 3.10.1 Expansion of basic content required in the Contractor’s Construction Schedule
Completion
A’17
AIA Conference on Architecture 2017 April 27-29, Orlando
Clarified that claims first discovered after the warranty period are not required to go through the IDM: § 15.1.3.2 15.1.3.2 Claims by either the Owner or Contractor, where the condition giving rise to the Claim is first discovered after expiration of the period for correction of the Work set forth in Section 12.2.2, shall be initiated by notice to the other party. In such event, no decision by the Initial Decision Maker is required
17 § 9.6.8 Provided the Owner has fulfilled its payment obligations under the Contract Documents, the Contractor shall defend and indemnify the Owner from all loss, liability, damage or expense, including reasonable attorney’s fees and litigation expenses, arising out of any lien claim or other claim for payment by any Subcontractor or supplier of any tier. Upon receipt of notice of a lien claim or other claim for payment, the Owner shall notify the Contractor. If approved by the applicable court, when required, the Contractor may substitute a surety bond for the property against which the lien or other claim for payment has been asserted.
2017 Release
A’17
AIA Conference on Architecture 2017 April 27-29, Orlando
B101-2017
agreement
A’17
AIA Conference on Architecture 2017 April 27-29, Orlando
B101-2017
– Clarify that Architect is not responsible for Owner’s acceptance of non- conforming work. – Updated approach to Sustainability Services – Bidding/Negotiation Phase now Procurement Phase – Substitutions During Procurement now Additional Service
A’17
AIA Conference on Architecture 2017 April 27-29, Orlando
B101-2017
– Clarifies Architect’s scope of review of Contractor’s design submittals
A’17
AIA Conference on Architecture 2017 April 27-29, Orlando
B101-2017
– Supplement lemental al Services ices – services not included in Basic Services that the Architect agreed to provide at the time the contract is executed (aka “that big table in Section 4.1”) – Addi ditiona tional l Services ices – services necessitated by circumstances as the project progresses
A’17
AIA Conference on Architecture 2017 April 27-29, Orlando
B101-2017
– Architect can obtain Additional compensation if re-design due to market conditions the Architect could not reasonably anticipate. – Approach is consistent with FAR Design Within Funding Obligation (Design Within Funding Limitations 48 CFR 52.236-22)
A’17
AIA Conference on Architecture 2017 April 27-29, Orlando
B101-2017
– Replaced with negotiable Termination Fee. – Paired with Licensing Fee for continued use of IOS
– One year from the date of Substantial Completion – Explicit on provisions that survive termination
A’17
AIA Conference on Architecture 2017 April 27-29, Orlando
B101-2017
compensation is on a percentage basis.
– previous payments will not be subsequently adjusted based on changes to the Owner’s budget.
A’17
AIA Conference on Architecture 2017 April 27-29, Orlando
Agreement includes a different standard, the Consultant agrees to perform consistent with the Prime Agreement standard of care.
A’17
AIA Conference on Architecture 2017 April 27-29, Orlando
– Separate Termination and Licensing Fees for terminations not the fault of the Consultant and terminations due to the Owner terminating the Prime Agreement
Consultant’s Termination and Licensing fees are contingent on the Architect receiving a Termination Fee from the Owner.
and Licensing fees are not contingent.
A’17
AIA Conference on Architecture 2017 April 27-29, Orlando
2017 Release
Hasti Hejazi Director of Global Innovation Education The American Institute of Architects hasti stihejazi hejazi@aia.org aia.org
AIA Contract Documents 2017 Webinar: Owner- Architect Agreements and New Sustainable Projects Exhibit
AIA Contract Documents 2017 Webinar: Revised General Conditions and New Sustainable Projects Exhibit
AIA Contract Documents 2017 Webinar: Owner-Contractor Agreements and New Sustainable Projects Exhibit
A’17
AIA Conference on Architecture 2017 April 27-29, Orlando
AIA Contract Documents Learn Page: www.aiacontracts.org/learn AIA Contract Documents education on AIAU: aiau.aia.org/aia-contract-documents Questions about AIA document content: Email: docinfo@aia.org Tel.: (202) 626-7526 Questions about ACD5: Email: docstechsupport@aia.org Tel.: (800) 942-7732
A’17
AIA Conference on Architecture 2017 April 27-29, Orlando