June 2016 Key High ghway y at Light t Street Recent Progress - PowerPoint PPT Presentation

Key Highway at Light Street June 2016 Key High ghway y at Light t Street Recent Progress 95% Design Level Refinement of Design Elements Environmental and Park Coordination Utility Coordination Key High ghway y at Light t


  1. Key Highway at Light Street June 2016 Key High ghway y at Light t Street

  2. Recent Progress  95% Design Level  Refinement of Design Elements  Environmental and Park Coordination  Utility Coordination Key High ghway y at Light t Street

  3. Proposed 95% Plan Key High ghway y at Light t Street

  4. Overall Scope of Improvements  Full Depth Roadway Reconstruction with Complete Rail Track Removal  Concrete Roadway Repairs  Installation of New Traffic Signals:  Key Highway @ Light Street  Key Highway @ William Street  New Signing and Pavement Markings  Storm Drain Improvements, Stormwater Management  Increase to the Capacity of Existing Conduit System  Replacement of Water Line  Landscaping, Sidewalk & ADA Upgrades, Gwynns Falls Trail Extension Key High ghway y at Light t Street

  5. Light Street at Lee Street  Full Length Bumpout along the west side of Light Street  Lane Configuration Change – Light Street Southbound  Right Turn Movement onto Lee Street  Southbound Continuation into Federal Hill  Right Turn Movement onto Hughes Street  Landscaping Key High ghway y at Light t Street

  6. Key Highway at Light Street Key High ghway y at Light t Street

  7. Key Highway at William Street Key High ghway y at Light t Street

  8. Key Highway at Battery Avenue Key High ghway y at Light t Street

  9. Gwynns Falls Trail Extension  Gwynns Falls Trail Extension from William Street to Covington Street  Removal of Existing Berm between Key Highway and Rash Field  Installation of New Median along Key Highway from Battery Avenue to Covington Street Key High ghway y at Light t Street

  10. Schedule  PS&E Submission ……………………….May 2016  Final Approvals…………………….Summer 2016  Advertisement…...................Late Summer 2016  Construction………………………..Late Fall 2016 Schedule is subject to change based on unforeseen events Key High ghway y at Light t Street

  11. Contact Information Grishae Blackett’e Southeast Transportation Liaison • Planning Division City of Baltimore • Department of Transportation 443-984-4095 Grishae.Blackette@baltimorecity.gov www.baltimorecity.gov/transportation/planning Key High ghway y at Light t Street

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.