Jason Brune, DEC Commissioner Alice Edwards, AQ Director Cindy - - PowerPoint PPT Presentation

jason brune dec commissioner alice edwards aq director
SMART_READER_LITE
LIVE PREVIEW

Jason Brune, DEC Commissioner Alice Edwards, AQ Director Cindy - - PowerPoint PPT Presentation

Jason Brune, DEC Commissioner Alice Edwards, AQ Director Cindy Heil, Program Manager May 16, 2019 1 Overview Nonattainment Planning Status Overview Current Air Quality Trends When can the area attain? Key Goals and Elements of


slide-1
SLIDE 1

Jason Brune, DEC Commissioner Alice Edwards, AQ Director Cindy Heil, Program Manager May 16, 2019

1

slide-2
SLIDE 2

Overview

Nonattainment Planning Status Overview Current Air Quality Trends When can the area attain? Key Goals and Elements of SIP Summary of Control Measures Serious SIP Public Review Timeline How to Comment The Future:

Next SIP Advantages of a 5% Plan Planning Timelines –What Comes Next?

2

slide-3
SLIDE 3

Fairbanks North Star Borough PM2.5 Nonattainment Where are we at?

 Serious nonattainment area

 Public health concerns

 Goal is to have healthy air to

breathe

 Federal planning requirements

 Initial control plan is being

implemented

 Reclassification to Serious area

means a new plan must be developed

 Sanctions are imposed if state fails

to act

 Serious plan requires more

controls to bring area into compliance

3

slide-4
SLIDE 4

A Complete Serious Area SIP – What is it?

 A Serious area SIP must meet federal Clean Air Act requirements

 Must adopt and implement Best Available Control

Measures/Best Available Control Technologies

 Must have contingency measures  Must have an episode plan  Must either demonstrate attainment by 12/31/2019 or

demonstrate why it is impracticable to attain by the attainment date and request an extension

 Must meet all technical requirements (emission estimates,

modeling, milestones)

4

slide-5
SLIDE 5

What Happens if We Don’t Take Action?

Do Not Submit A SIP on Time

  • EPA will file a

“Failure to Submit”

  • Sanction clock

started

  • 18 months later

sanctions in effect

  • Federal

Implementation Plan start soon after Submit SIP Incomplete/Inadequate

  • EPA identifies

inadequacies

  • Sanction clock

started

  • 18 months to

update Serious SIP for deficiencies Complete/Adequate

  • EPA has 6 months

to determine completeness

  • EPA begins

process to approve SIP

  • Committed

measures in SIP implemented Federal Plan State Plan

5

slide-6
SLIDE 6

Progress is Being Made - Air Monitoring Trend

6

slide-7
SLIDE 7

Current Air Quality

 Air monitoring trends show great improvement  More pollution reduction needed to reach a Design Value of 35

micrograms per cubic meter (ug/m3) across the entire area

7

Air Monitoring Site Year: 3-Year Design Value

2012 2013 2014 2015 2016 2017 2018

State Office Building 46 41 40 35 37 38 35 Ncore 45 40 39 35 33 34 30 North Pole Hurst Rd 139 124 106 85 65

slide-8
SLIDE 8

When can the area attain the PM2.5 standard?

Serious Plan cannot demonstrate attainment in 2019 Plan shows that the area will realistically be able to reach

attainment in the timeframe between 2024 and 2029.

8

slide-9
SLIDE 9

Key Goals and Elements of the Serious SIP

Show how the area can reach attainment Continue to allow the use of solid fuel fired devices Limit the impact on large industrial sources as they are not

the main contributors of the problem

Meet the EPA completeness criteria for a SIP (avoid sanction) Meet the Best Available Control Measure (BACM) and Best

Available Control Technology (BACT) Requirements

 Are proposed controls technically and economically feasible?

Position the SIP and control measures for transition to

a 5% Plan, the next SIP update needed

9

slide-10
SLIDE 10

Summary of Proposed Control Measures

Proposed control measures build off existing/continuing

controls and Stakeholder recommendations

 Existing controls continue – some revisions proposed to meet BACM  Required to look at measures from across the nation  Timing of proposed controls varies to allow time to prepare and plan  Seeking comment on controls including timing, technical and

economic impacts

10

slide-11
SLIDE 11

Proposed Solid Fuel Heating Control Measures (nonattainment area)

 2-Stage solid fuel burning curtailments remain in place

 Propose to call at lower concentrations (thresholds reduced 5 ug/m3)  Hope that curtailments are primarily a bridge as other measures

implemented and the need for curtailments will be reduced over time.

 Stage 1 and No Other Adequate Source of Heat (NOASH) Waivers to

curtailment will still be available

 Have proposed changes to eligibility requirements.  Length of the waivers will depend on age, type and emission rating of

device.

 Device registration will be required for waivers, new device sales and

real estate transactions that contain a solid fuel fired device.

 Only dry wood may be sold,

 Proposed effective date October 2021 to allow time to prepare

11

slide-12
SLIDE 12

Proposed Solid Fuel Heating Device Standards

 Adopting the EPA Stage 2 emission standards for wood fired heaters (2.0 g/hr)  Only pellet-fueled hydronic heaters will be allowed to be sold.  Only pellet-fueled or catalyst-equipped woodstoves will be allowed to be

  • sold. Non-catalytic woodstoves may be sold if the manufacturer provides

additional information and DEC approves.

 All new solid fuel fired devices must be professionally sized and installed.  Solid fuel devices may still be used but EPA uncertified devices and devices

  • lder than 25 years old will need to be removed by earlier of December 2024 or

as part of a real estate transaction (current requirement).

 Retrofit Electrostatic Precipitators (ESPs) are not mandated but they

are acknowledged as a technology that needs more study.

 Borough has issued a Request For Proposal (RFP) to begin testing to get the

data needed.

12

slide-13
SLIDE 13

Other Control Measure Proposals

 Only Diesel #1 may be sold in the nonattainment area for space heating

 Proposed effective date is July 2020.

 Small commercial source requirements

 Information request for businesses with charbroilers, incinerators,

used oil burners

 Proposal for emission control for coffee roasters

 Best Available Control Technologies (BACT) for large industrial sources

 Individual BACT analysis and determinations for each source

 Ft. Wainwright  Aurora Energy Chena Power Plant  GVEA North Pole  GVEA Zehnder  UAF

13

slide-14
SLIDE 14

14

Highlights of BACT Controls by Pollutant Pollutant Aurora Fort Wainwright GVEA North Pole GVEA Zehnder UAF Fine Particulate Matter (PM.25) – Direct Existing No new control Existing No new control Existing No new control Existing No new control Existing No new control Volatile Organic Compounds (VOC)s Existing No new control Existing No new control Existing No new control Existing No new control Existing No new control Nitrogen Oxides (NOx) No new control Precursor Determination No new control Precursor Determination No new control Precursor Determination No new control Precursor Determination No new control Precursor Determination Ammonia (NH3) No controls available No controls available No controls available No controls available No controls available Sulfur Dioxide (SO2) Economically infeasible Use low sulfur coal 0.2% S by weight by 2021 NEPA process to determine either SO2 control on existing facility or replace facility Use low sulfur coal 0.2% S by weight by 2021 Short-term: fuel switch to Diesel #1 during curtailments Long-term: ULSD

  • r Natural Gas once

decision on utilization of Healy 1 & Healy 2 finalized around 2022. Owner requested limit to lower emissions below BACT threshold Economically infeasible, fuel switch to ULSD in emergency generators Use low sulfur coal 0.2% S by weight by 2021

Proposed BACT Determination Highlights

slide-15
SLIDE 15

Serious SIP Available for Public Review & Comment

May 14 - Start public comment period May 16 - Presentation to FNSB Assembly

5:30 PM

June 25 - Open House at Westmark Hotel

6-8 PM

June 26 – Hearings at FNSB Assembly Chambers

12- 1:30 PM and 5-8 PM

July 26 – End comment period

15

slide-16
SLIDE 16

Next SIP – 5% Plan

16

The Clean Air Act and EPA regulations give two

  • ptions for a Serious SIP

Reach attainment by 2019 Request an extension that shows attainment

by 2024. Area cannot reach attainment by 2019, and cannot

realistically demonstrate attainment by 2024.

Serious SIP requests an extension, but likely it will

not be granted, therefore a 5% Plan will be due December 2020.

slide-17
SLIDE 17

Advantages of 5% Plan

 Benefits of the regulations in Serious Plan will get credited in the 5%

Plan

 Example, fuel switch to Diesel #1 could provide almost 3 years

  • f benefits

 Most Stringent Measures (MSM) are not required

 Including MSM to Point Sources

 New modeling Design Value and base year

 Will be able to use lower monitored values

 Likely will have a positive impact on approvability of Serious SIP if 5%

Plan can be submitted to EPA prior to final EPA action on Serious SIP

 Will likely show attainment earlier that 2029, however this depends

  • n final control measures adopted in Serious SIP

17

slide-18
SLIDE 18

Planning Timelines – What Comes Next?

 After comment period, finish Serious SIP, adopt and submit to

  • EPA. Estimate early winter 2019.

 Begin development of 5% Plan. Gather 2018 emission data for a new

  • baseline. Develop new Design Value. Develop new modeled forecasts
  • nce regulations are adopted.

 Target release of 5% Plan for public comment around May 2020.

Submittal to EPA before December 2020 due date.

 Initiate data collection over 2019-2020 winter as the first step to

updating the model used in the SIPs. Current data is from 2008 and does not reflect the Hurst Road Monitor.

 Update the 5% Plan once the model is updated, which will take an est. 2

years once the data has been gathered. This update will also use latest monitored results and a new baseline.

18

slide-19
SLIDE 19

How to Comment

19

DEC wants your feedback

Comments are important to finalizing the plan

Several ways to submit comments:

Electronically - online form Email Mail Public Hearing

Handout with details on how to comment is

provided in the back of the room.

slide-20
SLIDE 20

Questions? Thank You!

20