January 18, 2017 1. Phase IC Overview 2. Budget and Cost Escalation 3. Construction Phasing Plan 4. Timeline 5. Q&A 1. Phase IC Overview 2. Budget and Cost Escalation 3. Construction Phasing Plan 4. Timeline 5. Q&A Oyster Point


slide-1
SLIDE 1

January 18, 2017

slide-2
SLIDE 2
  • 1. Phase IC Overview
  • 2. Budget and Cost Escalation
  • 3. Construction Phasing Plan
  • 4. Timeline
  • 5. Q&A
slide-3
SLIDE 3
  • 1. Phase IC Overview
  • 2. Budget and Cost Escalation
  • 3. Construction Phasing Plan
  • 4. Timeline
  • 5. Q&A
slide-4
SLIDE 4

Oyster Point – Existing Conditions

slide-5
SLIDE 5

Oyster Point – Phase IC

Phase IIC Cap Repair Yacht Club

Boundary of Phase IC

slide-6
SLIDE 6

WHERE ARE WE SINCE 2011?

− Focus on Implementing Phase I − Phase IC includes infrastructure and open space − Phase ID includes 508,000 SF of Office/R&D buildings − Project Ownership Transfer Completed − August 2016, Oyster Point Development (“OPD”) acquired the Oyster Point project from Shorenstein/SKS − Project Team Set Up − OPD has set up office and operation at Oyster Point − SKS retained as consultant, leveraging their knowledge and project continuity − Civil, environmental and geotechnical consultants are engaged − Regular Communication with City Staff − Ongoing weekly standing meeting with City Staff since July 2016 − Community Outreach − Outreach to all tenants at Oyster Point who will be impacted by Phase I

slide-7
SLIDE 7
  • 1. Phase IC Overview
  • 2. Budget and Cost Escalation
  • 3. Construction Phasing Plan
  • 4. Timeline
  • 5. Q&A
slide-8
SLIDE 8

2011 Phase IC Cost Estimate:

$ 29,875,095 Hard Costs from Hathaway Dinwiddie $ 5,395,019 Soft Cost (assumed 20% of Hard Cost) $ 35,610,113 Total Costs

2017 Phase IC Cost Estimate:

$ 34,129,757 Hard Costs with escalation through Oct 2016 from Hathaway Dinwiddie $ 1,706,488 Additional escalation from Oct 2016 through construction contract $ 8,305,256 Soft Costs (fully developed budget includes design contingency*) $ 44,141,501 Total Costs *Fully developed soft cost budget = 23% of Hard Costs

slide-9
SLIDE 9

2011 Phase IIC Cap Repair Cost Estimate:

$ 476,972 Hard Costs from Hathaway Dinwiddie $ 95,394 Soft Cost (assumed 20% of Hard Cost) $ 572,366 Total Costs

2017 Phase IIC Cap Repair Cost Estimate:

$ 708,985 Hard Costs with escalation through Oct 2016 from Hathaway Dinwiddie $ 42,486 Additional escalation to start of construction $ 140,741 Soft Costs $ 892,212 Total Costs

slide-10
SLIDE 10
  • 1. Phase IC Overview
  • 2. Budget and Cost Escalation
  • 3. Construction Phasing Plan
  • 4. Timeline
  • 5. Q&A
slide-11
SLIDE 11

Oyster Point – Phase I: Existing Conditions

slide-12
SLIDE 12
slide-13
SLIDE 13
slide-14
SLIDE 14

Red dashed line indicates overall construction site fencing at this phase.

slide-15
SLIDE 15
slide-16
SLIDE 16

Oyster Point – Phase IC/ID at Completion

Yacht Club

slide-17
SLIDE 17
  • 1. Phase IC Overview
  • 2. Budget and Cost Escalation
  • 3. Construction Phasing Plan
  • 4. Timeline
  • 5. Q&A
slide-18
SLIDE 18

Anticipated Timeline:

35% Design Drawings January 2017 65% Design Drawings June 2017 Landfill Agency Approvals August 2017 Demo/Grading Permits August 2017 Land Conveyance Closing August 2017 First DDA Payment to City August 2017 Start of Construction (Demo/Temp Roads) September 2017 95% and 100% Design Drawings October 2017 Completion of Phase IC End of 2018

slide-19
SLIDE 19
  • 1. Phase IC Overview
  • 2. Budget and Cost Escalation
  • 3. Construction Phasing Plan
  • 4. Timeline