ITS Georgia Kyle Mote GDOT Office of Planning June 27, 2013 - - PowerPoint PPT Presentation

its georgia
SMART_READER_LITE
LIVE PREVIEW

ITS Georgia Kyle Mote GDOT Office of Planning June 27, 2013 - - PowerPoint PPT Presentation

ITS Georgia Kyle Mote GDOT Office of Planning June 27, 2013 Agenda 2009 Managed Lane System Plan overview Current activities: Managed Lane Implementation Plan Lessons learned and emerging findings Next steps 2009 Atlanta


slide-1
SLIDE 1

ITS Georgia

Kyle Mote GDOT Office of Planning June 27, 2013

slide-2
SLIDE 2

Agenda

  • 2009 Managed Lane System Plan overview
  • Current activities: Managed Lane Implementation

Plan

  • Lessons learned and emerging findings
  • Next steps
slide-3
SLIDE 3

2009 Atlanta Regional Managed Lane System Plan (MLSP) - Overview

  • First regional managed lanes

plan in the country

  • In 2009, there were no Priced

Managed Lanes in the Atlanta region (only HOV lanes)

  • Identified $16 Billion in MLs
  • Assumed $9 Billion could be

delivered via PPP

  • $5.9 Billion programmed in

current Atlanta MPO Plan

slide-4
SLIDE 4

2009 Managed Lane System Plan Goals

  • Protect mobility with all new capacity
  • Maximize person/vehicle throughput
  • Minimize environmental impacts
  • Provide a financially feasible system
  • Design and maintain a flexible infrastructure

network, for varying lane management

slide-5
SLIDE 5

Managed Lane Corridors Currently in Operation or in Development (Priced & HOV)

slide-6
SLIDE 6
  • Open to traffic:

– I-85 North Express Lanes (16 miles)

  • HOV2+ to HOT3+ conversion in 2011
  • 250,000 transponders issued
  • Under Development:

– Northwest Corridor (I-75/I-575 North) Express Lanes

  • ROD issued May 2013

– I-75 South Express Lanes

  • Expect FONSI, summer 2013

– I-85 North Extension

  • Construction currently planned for FY 15
  • In the Alternative Evaluation Process:

– I-285 Top End (revive285)

  • EIS under development

– SR 400 North of I-285

  • Feasibility study underway

Existing & Planned Priced Managed Lanes

slide-7
SLIDE 7
  • All limited access highway new capacity in Metro

Atlanta will likely be tolled

  • Remove HOV2+ to HOT3+ conversions from MPO

TIP

  • Eliminate assumptions of long-term concession

agreements

  • Evaluate lower-cost managed lane treatments

New Planning Assumptions Moving Forward

slide-8
SLIDE 8

Managed Lane Implementation Plan (MLIP) Overview

  • Updating MLSP as part of Managed Lanes Implementation Plan

(MLIP) to:

– Build upon previous MLSP goals – Reflect current funding constraints – Identify feasible locations for managed lane projects – Redefine and reprioritize projects from the previous plan based on current and future needs – Prioritize list of managed lane projects and accompanying financing strategies (P3 and traditional funding sources)

  • Incorporate recommendations into RTP and TIP update, as

appropriate during 2013-2014

slide-9
SLIDE 9

Innovations and Emerging Findings-MLIP

  • Considering non-traditional Managed Lane solutions

– Reversible lanes

  • Moveable barrier (new option)
  • Fixed barrier (existing option)

– Shoulder lanes

  • Consider managing inside lane in peak periods and off-setting the

removed general purpose capacity with travel on shoulder

– Option: use reversible barrier and shoulder lanes in conjunction with each other

  • Intent is to not “reduce” current travel options for

motorists

slide-10
SLIDE 10

Shoulder Lanes

slide-11
SLIDE 11

Shoulder Lanes – Typical Section BEFORE

Source: Atlanta Regional Managed Lanes Implementation Plan, GDOT.

slide-12
SLIDE 12

Shoulder Lanes – Typical Section AFTER

Source: Atlanta Regional Managed Lanes Implementation Plan, GDOT.

slide-13
SLIDE 13

Shoulder Lanes – Case Studies

  • Washington State - US 2

– 1.5 miles during PM only

  • Minneapolis

– 3.0 miles during AM & PM – Use left shoulder – Region wide bus shoulders

  • UK M42 Highway

– 10 miles – Shoulders used in conjunction with variable speed limits

  • Netherlands

– Use left and right shoulder

Shoulder Sign in Washington State

slide-14
SLIDE 14

Shoulder Lanes – Considerations

  • Shoulder pavement depth
  • Shoulder width
  • Bridge spans and pillar

locations

  • Entrance/exit ramp

locations and volumes

  • Additional signage
  • Refuge sites (incidents and

emergency access)

  • Segment length

SR 400 Shoulder Lane (Atlanta, GA)

Source: www.itsinternational.com

slide-15
SLIDE 15

Shoulder Lanes-Lessons Learned

  • Manage expectations, not all shoulders lend

themselves to travel

  • Capital costs vary dramatically based on existing

infrastructure

  • Develop active traffic management system concept
slide-16
SLIDE 16

Shoulder Lanes-Lessons Learned

  • Pre-determine enforcement roles/processes,

incident response, training, public outreach and education

  • Strategic placement of video cameras to monitor

traffic

  • Strategic placement of emergency refuge areas,

with proper signing

slide-17
SLIDE 17

Moveable Barriers

slide-18
SLIDE 18

Moveable Barriers – Typical Section BEFORE

Source: Atlanta Regional Managed Lanes Implementation Plan, GDOT.

slide-19
SLIDE 19

Moveable Barriers – Typical Section AFTER

Source: Atlanta Regional Managed Lanes Implementation Plan, GDOT.

slide-20
SLIDE 20

Moveable Barriers – Case Studies

  • I-30/Thornton Freeway: Dallas, TX
  • 5.2 mile managed lane during AM & PM
  • Increased speeds from 22 to 41 mph
  • 1,200 – 1,400 vehicles per hour (vph)
  • I-93: Boston, MA
  • 6.0 mile managed lane during AM & PM
  • Flows at posted speed (55 mph)
  • 1,500 - 1,800 vph
  • No increase in accidents
  • I-70: West of Denver, CO
  • 13.5 mile EB Sundays
  • Significant decrease in EB travel times (79 to 41

min.) and increase in WB travel times (34 to 69 min.)

  • 2% annual increase in crashes (snow conditions)

Source: Barrier Systems, Inc.

I-93 Rever versib ible le Lanes es in Boston ton

slide-21
SLIDE 21

Moveable Barriers – Considerations

  • Directional split of traffic and number of lanes
  • Estimated benefit (travel time savings)
  • Capital and Operating & Maintenance costs
  • Bridge spans and pillar locations
  • Median and/or shoulder widths
  • Borrow inside lane or shoulder for reverse direction and/or widen

to the median

  • Logistics of rev. lanes
  • Additional signage
  • Segment length

Source: Barrier Systems, Inc.

slide-22
SLIDE 22

Moveable Barriers-Lessons Learned

  • Plan ahead (traffic impacts, physical limitations,

storage, etc)

  • Develop standard operating procedures
  • Enforcement (if operated as managed lane)
  • Public education
  • Dependable contractor (if operation is privatized)
slide-23
SLIDE 23

Moveable Barriers-Lessons Learned

  • Spare parts inventory
  • Aggressive preventative maintenance
  • Adequate staffing for enforcement, traffic incident

management and maintenance

  • Consider multiple access points
slide-24
SLIDE 24

Priced Managed Lanes

slide-25
SLIDE 25

Georgia Priced Managed Lane Overview

  • High Occupancy Toll (HOT)

– Mixture of occupancy and tolling components – 17 currently in operation across US, including 1 in Georgia (I-85 North) – Relatively easy to convert HOV lanes to HOT (need public support) – Requires additional enforcement/back office operations – Transit buses have free access

  • Express Toll Lanes (ETL)

– All users pay (except transit buses) – 1 currently in operation in US (SR 91, CA), 2 planned in Georgia (I-75 South & I-75/I-575 North) – Easier to enforce/back office operations, when compared to HOT – Higher revenue than HOT

slide-26
SLIDE 26

Priced Managed Lanes – Case Studies

  • High Occupancy Toll (HOT) Lanes

– I-95: Miami, FL – SR 167: Seattle, WA – I-15: Salt Lake City, UT – I-394: Minneapolis, MN – I-10 Katy Freeway: Houston, TX

  • Express Toll Lanes (ETL)

– SR 91: Orange County, CA

SR 91 Express ess Toll

  • ll Lanes

es

slide-27
SLIDE 27

Priced Managed Lanes

slide-28
SLIDE 28

Priced Managed Lanes-Lessons Learned

  • Tolling existing capacity (HOV and GP) can be

challenging

  • Likely not self-supporting, requiring funding

source, particularly in early years for O&M

  • Recognize ramp-up period for tolling, adjustment

time for motorists

  • Interface between differing managed lane types

(HOV to HOT) has been less of an issue than anticipated in MLSP

slide-29
SLIDE 29

Priced Managed Lanes-Lessons Learned

  • Ideally provide users with travel time estimates

and speed limits in using dynamic signs

  • Complete camera coverage aids in operations and

enforcement

  • Occupancy detection, declaration and

enforcement impact revenues

slide-30
SLIDE 30

Priced Managed Lanes-Lessons Learned

  • Access points may need modification after open to

traffic

  • Design and operation should be flexible enough to

accommodate fluctuating traffic patterns

  • Adequate signage is necessary to identify access

points

  • Evaluate potential funding resources early
slide-31
SLIDE 31

Priced Managed Lanes-Lessons Learned

  • Effective outreach is essential and must continue

throughout project planning, implementation, and

  • peration:

– Reliable/faster trips – Transit access – Increased network capacity – Limited ability to build additional general purpose lane capacity – HOV can be an ineffective way to regulate demand

slide-32
SLIDE 32

Priced Managed Lanes – Emerging Trends

  • Multi-lane facilities
  • Dual purpose investments (auto and transit)
  • Regional network
  • Develop performance measures (speeds,

throughput-both car and transit)

  • Moving from HOT based facilities to ETL facilities,

with new construction

slide-33
SLIDE 33

Managed Lane Implementation Plan Next Steps

slide-34
SLIDE 34

Corridors Selected for Managed Lanes Evaluation

slide-35
SLIDE 35

Corridors Selected for Moveable Barrier Evaluation

Directional Split Directional Split, MARTA Rail Grass Median Limited Shoulders Grass Median Arterial, Grass Median Limited Shoulders

slide-36
SLIDE 36

Corridors Selected for Shoulder Lane Evaluation

Limited Shoulders Limited Shoulders Limited Shoulders Limited Shoulders

slide-37
SLIDE 37
  • Evaluate potential improvements in each corridor

– Planning level traffic and toll revenue analysis – Detailed traffic assessment

  • Financial feasibility assessment

– Preliminary capital and O&M cost estimates – High level project financing plan

  • Develop and apply project prioritization framework
  • Final recommendations and documentation

Next Steps

slide-38
SLIDE 38

www.dot.ga.gov\MLIP Kyle Mote GDOT Office of Planning

(404) 631-1811 kmote@dot.ga.gov