Weedon Island Feasibility Study
Presentation for the Tampa Bay Regional Planning Council Agency
- n Bay Management –
August 9, 2018
Island Feasibility Study Presentation for the Tampa Bay Regional - - PowerPoint PPT Presentation
Weedon Island Feasibility Study Presentation for the Tampa Bay Regional Planning Council Agency on Bay Management August 9, 2018 Project Background SWFWMD / County Cooperative Funding Initiative 2012 Weedon Island Preserve
Presentation for the Tampa Bay Regional Planning Council Agency
August 9, 2018
SWFWMD / County Cooperative Funding
2012 Weedon Island Preserve
Goals and Objectives
Habitat Restoration and Improvement Hydrologic Preservation and Restoration Exotic and Nuisance Species Management
Evaluate Habitat Restoration/Enhancement
Existing and Proposed Site Conditions Permitablitiy Costs – Measurable Benefits
3,190-acre preserve
Study area 1,100-acres
Mangrove forest habitat dominates the landscape
Maritime hammock Salterns Salt marsh Scrubby flatwoods Seagrass
Significant cultural and historical resources present
Shell middens Domiciliary mounds Sand burial mounds
Mosquito Ditching in 1950’s
1943 1958 1970
Goals
Habitat Restoration and Improvement
Restore saltern, mangrove, and salt marsh communities Improve habitats by removing upland spoil mounds and improving circulation Natural resource management practices such as prescribed fire
Exotic and Invasive Species Management and Control
Reduce the extend and abundance of exotic and invasive plants
Hydrologic Preservation and Restoration
Improve hydrology to improve water quality and circulation
Objectives
Increase Wetland Habitat Area Improve Native Wetland Plant Communities
Removal of upland spoil mounds Nuisance species removal Hydrology improvements
Decrease nuisance species cover in both upland and wetland habitats
by various methods of control
Identify project approaches that will not adversely affect cultural and
historical resources within the study area
Constraints
Significant Cultural and Historical Resources Access Issues
Cover type Distance from uplands or open water Lack of survey
Permit Complexity Performance Criteria Public Involvement
Spoil Mound Removal Nuisance Species Removal
Focused, complete effort in larger areas of nuisance species Selectively remove scattered nuisance species
Hydrology Improvements
Improve flushing and natural tidal regimes
Based on changes in community and natural features Allow assessment of:
Access restrictions Cultural Resources Permit complexity
Low, moderate, or high ranking assigned
The process of moving soil with pressurized water
Portable water pumps Specialized hoses Blast mounds of spoil Direct resulting slurry into existing mosquito ditches
Requires removal of nuisance species prior to Hydroblasting
Follow-up recommended
Grade lowered to that of surrounding wetland Methodology yields mixed results
Amount of material removed Elevation achieved Type of soil remaining
Photo courtesy of SWFWMD
Unit ID Unit Acreage Cost Estimate (by Unit Acreage) Unit Access Restrictions Cultural Resources Permit Complexity
SMR-1 2.62 $19,925 Low Low Low SMR-2 25.18 $191,494 Low Low Low SMR-3 8.94 $67,989 Low Low Low SMR-4 5.91 $44,946 Low Moderate/Low Moderate SMR-5 8.02 $90,225 Moderate High High SMR-6 6.89 $52,398 Low High High SMR-7 6.49 $146,025 High High High SMR-8 12.35 $138,938 Moderate Low Low SMR-9 17.24 $193,950 Moderate Low Moderate SMR-10 11.27 $253,575 High High High SMR-11 20.51 $155,979 Low High High SMR-12 43.23 $328,764 Low High High SMR-13 15.34 $268,327 Low Low Low SMR-14 12.62 $220,749 Low Low Low SMR-15 18.62 $481,793 Moderate Moderate/Low Low/Moderate SMR-16 17.09 $298,938 Low Moderate/Low Low/Moderate SMR-17 16.30 $421,763 Moderate Moderate/Low Moderate SMR-18 12.47 $645,323 High Low Moderate/High SMR-19 18.63 $325,876 Low Low Moderate SMR-20 18.15 $469,631 Moderate Low High SMR-21 16.00 $414,000 Moderate Low High SMR-22 15.68 $405,720 Moderate Low High SMR-23 14.09 $729,158 High Low High SMR-24 13.90 $719,325 High Low High SMR-25 20.61 $533,284 Moderate Low High SMR-26 13.93 $720,878 High Low High SMR-27 13.74 $355,523 Moderate Low Moderate SMR-28 13.39 $234,218 Low Low Moderate TOTALS 419.21 $8,928,710 South Spoil Mound Removal Study Units North Spoil Mound Removal Study Units
Per Mound
Low - $1,690 Mid - $2,500 High - $5,000
Estimated
Mound Size Number per Acre
419 Acres $8.93 M $21,310 per Acre
Includes temporary access roads
Spoil mound removal to create
the temporary fill
Crane mats to reduce the
amount of fill used
Temporary pipes to maintain
flow
Longer-term temporary access
Removed in phases
Long reach, amphibious
Spoil used to selectively
Or, hauled away
Dig the access road out (Dig Out) Removal of remaining spoil
Restoration of temporarily-
Fill backwater ditches Hydrology Improvements
Improve Diurnal Flow Deeper-water Refugia
Square Feet Acreage Spoil Mounds 83,457 1.9 13.0% Black Mangroves 381,517 8.8 59.4% Red Mangroves/Mosquito Ditches 177,000 4.1 27.6% TOTAL AREA 641,974 14.7 100% Square Feet Acreage Access Road Impacts (fill) 74,620 1.7 11.6% Mosquito Ditch Impacts (fill) 7,172 0.2 1.1% Mosquito Ditch Impacts (dredge) 170,527 3.9 26.6% TOTAL TEMPORARY IMPACTS 252,319 5.8 39.3% Square Feet Acreage Black Mangroves Not Impacted 306,198 Restored Black Mangrove Temporary Impacts 74,620 Removed Spoil Mounds 64,022 Black Mangroves (Total) 444,840 10.2 69.3% Red Mangroves/Mosquito Ditches Restored 129,360 3.0 20.2% Deeper Water Refugia 41,167 0.9 6.4% Saltern/High Marsh 26,607 0.6 4.1% TOTAL AREA 641,974 14.7 100.0% Size Cover Type % Existing Conditions
Table 4-3 Sample Work Area
Temporary Impact Quantities Proposed Conditions Size Cover Type % Size Work Area %
Restored temporary impacts Filled backwater ditches Removed all nuisance species’
Hydrology Improvements
Improved diurnal flow Created refugia
Cost Type Cost Cost per month 42,000 Manhours 10,000 Fuel 3,500 Maintenance 4,200 Total Cost 59,700 $ Cost Type Cost Cost per month 10,000 manhours 6,000 160 hours, $15 / hr, 2.5 multiplier Fuel 1,680 Maint 1,000 Total Cost 18,680 $ Cost Type Cost Cost per month 2,315 manhours 6,000 Fuel 1,680 Maint 232 Total Cost 10,227 $ Cost Total Cost 10,000 $ 160 hours, $25 / hr, 2.5 multiplier Rate Type Front-end loader Rate Type Foreman 10% rental rate rental rate 160 hours, $15 / hr, 2.5 multiplier 24 gal/day @$3.50/gal 24 gal/day @$3.50/gal 10% rental rate
Table B-2 Equipment Cost Estimate
Rate Type Amphibious Excavator Off-Road Articulating Truck Rate Type rental rate rental rate 160 hours, $25 / hr, 2.5 multiplier 50 gal/day @$3.50/gal 10% rental rate
Cost Type Cost Amphibious Excavator 59,700 Truck 18,680 Front-end Loader 10,227 Foreman 10,000 98,607 $ 4,930 $ Cost Type Days Cost Comment Main Access Road 1.1 5,423 1000 feet per day Spur Access Road 4.8 23,666 720 feet per day Long Reach Spoil Removal 12.0 59,164 6 mounds per day Fill Ditch 1.5 7,395 240 feet per day Dredge Ditch 3.9 19,228 350 feet per day Dig Out 4.8 23,666 720 feet per day removal TOTAL 28.1 138,542 $ Cost Type Quantity temporary pipe 140 2,800 crane mats 10 5,000 TOTAL $ 7,800 Cost Type Quantity Erosion Control 10% 14,634 $ Overhead 30% 43,903 $ Mobilization 10% 14,634 $ Contingency 10% 13,197 $ 86,368 $ TOTAL 232,710 $ PER ACRE 15,831 $ Cost Other Incidentals (Reusable) Cost Construction Time per month per day
Table B-3 WIDO Cost Estimate
Equipment Plus Labor
Unit ID Size (Acre) Price per Acre Cost per Study Unit Cultural Resources Permit Complexity
SMR-1 2.62 15,831 $ $41,477 Low Low SMR-2 25.18 15,831 $ $398,625 Low Low SMR-3 8.94 15,831 $ $141,529 Low Low SMR-4 5.91 15,831 $ $93,561 Moderate/Low Moderate SMR-5 8.02 15,831 $ $126,965 High High SMR-6 6.89 15,831 $ $109,076 High High SMR-7 6.49 15,831 $ $102,743 High High SMR-8 12.35 15,831 $ $195,513 Low Low SMR-9 17.24 15,831 $ $272,926 Low Moderate SMR-10 11.27 15,831 $ $178,415 High High SMR-11 20.51 15,831 $ $324,694 High High SMR-12 43.23 15,831 $ $684,374 High High SMR-13 15.34 16,244 $ $249,183 Low Low SMR-14 12.62 16,244 $ $204,999 Low Low SMR-15 18.62 16,244 $ $302,463 Moderate/Low Low/Moderate SMR-16 17.09 16,244 $ $277,610 Moderate/Low Low/Moderate SMR-17 16.30 16,244 $ $264,777 Moderate/Low Moderate SMR-18 12.47 16,244 $ $202,563 Low Moderate/High SMR-19 18.63 16,244 $ $302,626 Low Moderate SMR-20 18.15 16,244 $ $294,829 Low High SMR-21 16.00 16,244 $ $259,904 Low High SMR-22 15.68 16,244 $ $254,706 Low High SMR-23 14.09 16,244 $ $228,878 Low High SMR-24 13.90 16,244 $ $225,792 Low High SMR-25 20.61 16,244 $ $334,789 Low High SMR-26 13.93 16,244 $ $226,279 Low High SMR-27 13.74 16,244 $ $223,193 Low Moderate SMR-28 13.39 16,244 $ $217,507 Low Moderate TOTALS 419.21 $6,739,995 Southern Portion of Preserve Northern Portion of Preserve
419 Acres $6.74 M $16,078 / Acre
Mosquito Lagoon, Canaveral National Seashore Dragline
St. John’s Water Management District Volusia County Mosquito Control National Park Service Florida Fish and Wildlife Conservation Commission U.S. Fish and Wildlife Service
$1,375/Acre District Staff No Survey No Material
40% Wetland
Hydro-axe Roller Chop Herbicide (Bower Tract) Quarterly maintenance events for
Foliar Spray Basal Spray Hack and Squirt
Chainsaw Prescribed Burn
Brazilian Pepper Signature
Non-ditched Areas
Average - $273 per Acre
Ditched Areas
Average - $2,429 per acre
419 Acres $1.02 M
Cost (Total) Size (Acres) Cost (Per Acre) Referenced Project Non-Mosquito Ditched Areas 500 1 500 Foliar Spray 2000 9 222 9800 102 96 273 $ Average Mosquito Ditch Mangroves Bower Tract 9,800 initial 102 acres 100,440 3 years quarterly 110,240 $ Total 1,081 $ per acre Feather Sound 10,000 initial Feather Sound 9 acres 24,000 3 years quarterly 34,000 $ Total 3,778 $ per acre 2,429 $ Average Bower Tract Herbicide Table B-4 Nuisance Species Removal Cost Estimate FDOT District -Wide Contract Feather Sound Bower Tract
Mosquito ditch filling Dead-end ditch/berm
Pipe desilting Ditch dredging
Approach Size (Acre) Total Cost Price per Acre
Hydrology Improvement
$
14.51 236,250 $ $16,282 Nuisance Species Removal 246.19 68,299 $ $406 Nuisance Species Removal and Prescribed Burn 262.32 73,049 $ $278 Nuisance Species Removal, Prescribed Burn, and Hydrology Improvements 6.89 19,550 $ $2,837 Nuisance Species Removal and Hydrology Improvement 63.74 287,380 $ $4,509 Walk In, Dig Out 306.11 4,742,448 $ $15,493 Walk In, Dig Out and Hydrology Improvements 27.96 520,460 $ $18,614 Walk In, Dig Out, Nuisance Species Removal, and Hydrology Improvements 6.89 146,760 $ $21,300 TOTALS 934.61 6,242,545 $ $6,679
Uniform Mitigation Assessment Methods (UMAM)
Relative Functional Gain (RFG) = 132.3 units Temporary Impacts – Functional Loss (FL) = 21.9 units Net RFG = 110.4 units Mitigation Bank @ $100K per Acre = $11.04 M ecological lift Cost = $6.24 M < $11.04 M
Final Report - September 2018 Pilot Project – 27.96 acres, $454,182
Cooperative Funding Initiative Application - October 2019 Design and Permitting – October 2020 Construction – October 2021
Repeat (10 to 15 years)
Pinellas County SWFWMD Tampa Bay Estuary Program Tampa Bay Regional
Planning Council
USGS Alliance for Weedon Island
Archaeological Research
Friends of Weedon Island Duke Power