Is cost-of-service plus incentives the best that we can do? David - - PowerPoint PPT Presentation
Is cost-of-service plus incentives the best that we can do? David - - PowerPoint PPT Presentation
Is cost-of-service plus incentives the best that we can do? David Newbery 12 th ACCC Regulatory Conference Brisbane 28 th July 2011 http://www.eprg.group.cam.ac. uk Outline Regulation is inevitable for grids & distribution
D Newbery ACCC 2011 2
Outline
- Regulation is inevitable for grids & distribution
– Legacy of under-pricing state assets
- need for increased investment => pricing problems
– raises questions about efficacy of regulation
- natural monopolies in power networks
– What have we learned? What remains the same? – How to set the X-factor?
- Future possibilities
– Making networks contestable?
D Newbery ACCC 2011 3
Classic network utilities
e.g. electricity grids
- network is natural monopoly
– competition from rival networks uneconomic
- capital-intensive
- provides essential services
- connected to consumer/voter
Regulation inevitable, state ownership likely
D Newbery ACCC 2011 4
Capital Investment ESI 1948-1989
0.00 0.50 1.00 1.50 2.00 2.50 3.00 3.50 4.00 4.50 1948/9 1953/4 1958/9 1963/4 1968/9 1973/4 1978/9 1983/4 1988/9 £ billion (reflated to 1985) 10 20 30 40 50 60 70
percent of revenue
Total Central/CEGB Area Boards % of revenue
Emerging spare capacity cuts investment demand But stores up future investment need
D Newbery ACCC 2011 5
Investment in Water in England and Wales
Industry actual total capital expenditure from 1920 to 2002 with Ofwat's latest assumptions for 2003 to 2005
1 2 3 4 5
1920- 21 1940- 41 1960- 61 1980- 81 2000- 01
Financial year
Notes
- 1. Original data for the period 1920 to 1980 was for water and sewerage companies only. These figures have been increased by 8% (based on a long term average
- f actual spend since 1980), to allow for expenditure by the water supply companies over this period.
- 2. Projected expenditure from 2002-03 to 2004-05 is that assumed in Ofwat's 1999 price limits but with a) the underspend in investment from 2000-01 and 2001-02
included and b) an estimated efficiency saving of 7% removed.
£ billion (2001-02 prices using RPI)
IMF imposes budget cuts Privatisation
WW2
Source: Byatt
D Newbery ACCC 2011 6
GB infrastructure needs
Source; Buchanan, 10/2/11
D Newbery ACCC 2011 7
Dynamic efficiency
- main determinant of prosperity is quantity
and quality of investment
- Investment: hazard current $ for uncertain
future gain
- private investors require:
– secure title to future returns – commercial not political risks
D Newbery ACCC 2011 8
Regulatory credibility
- Public (regulator) and utility both want
investment ⇒ cooperate
- both want rents ⇒ conflict
=> Sunk investment risks regulatory opportunism
- easier to privatise and restructure if prices fall
Regulation/public ownership evolves to finance investment and distribute rent
D Newbery ACCC 2011 9
Regulation
- Transfer efficiency gains to consumer
p ≤ bp + (1-b)c p = efficient price, c is unit cost b is power of incentive
- conflict between incentives and transfers
- high power=strong efficiency incentive
- low power for rent transfer
Applies to public ownership and regulation
10
Retail prices after privatisation
UK real domestic utility prices
20 40 60 80 100 120 140 160 180
1 9 8 1 9 8 1 1 9 8 2 1 9 8 3 1 9 8 4 1 9 8 5 1 9 8 6 1 9 8 7 1 9 8 8 1 9 8 9 1 9 9 1 9 9 1 1 9 9 2 1 9 9 3 1 9 9 4 1 9 9 5 1 9 9 6 1 9 9 7 1 9 9 8 1 9 9 9 2 2 1 2 2
Index 1987=100 water rail electricity gas telephones
Rail privatised Electricity privatised water privatised gas privatised BT privatised
D Newbery ACCC 2011 11 Newbery IIB 1 11
Basic trade-offs
- Efficiency vs equity
- Increase credibility => reduces required return
– longer-term guarantees vs flexibility – contracts vs market support/subsidies
- Reduce cost of capital to lower price (rises)
– delivering investment efficiently => allocate risk – reduce risk => reduce WACC but increase cost?
reduce informational asymmetries
eases equity-efficiency trade-off
D Newbery ACCC 2011 12
Setting Price-caps
- Initial P0, X set at privatisation
– P0 for smooth transition, X for good sale
- Price controls reset every 5 years
– but how to reset and still preserve incentives? – P0 to claw back some efficiency gains – X: catch up frontier, then industry prod growth?
=> benchmark where possible
– fine for distribution companies, hard for grids
D Newbery ACCC 2011 13
Incentives for investment
- benchmarking used for opex, hard for capital
- Investment plans ⇒ RABt+i ⇒ price path
⇒ Utility overstates investment plans
– delay investment until end of price control period – if RAB updated ⇒ rate-of-return regulation? – If RAB based on benchmarks ⇒ under-invest?
How judge if investment is good value?
D Newbery ACCC 2011 14
British Electricity Distribution Investment
200 400 600 800 1000 1200 1400 1600 1800 2000
8 9 / 9 9 / 1 9 1 / 2 9 2 / 3 9 3 / 4 9 4 / 5 9 5 / 6 9 6 / 7 9 7 / 8 9 8 / 9 9 9 / / 1 ' 1 / 2 ' 2 / 3 ' 3 / 4 ' 4 / 5 £ millions (2003/4 prices)
Company forecast Regulator's allowance Actual investment
Source: Green
D Newbery ACCC 2011 15
Transmission investment pre-privatization
Transmission investment England and Wales 1978-2011
£0 £100 £200 £300 £400 £500 £600 £700 £800 £900 £1,000
7 8 / 7 9 7 9 / 8 8 / 8 1 8 1 / 8 2 8 2 / 8 3 8 3 / 8 4 8 4 / 8 5 8 5 / 8 6 8 6 / 8 7 8 7 / 8 8 8 8 / 8 9 8 9 / 9 9 / 9 1 9 1 / 9 2 9 2 / 9 3 9 3 / 9 4 9 4 / 9 5 9 5 / 9 6 9 6 / 9 7 9 7 / 9 8 9 8 / 9 9 9 9 / / 1 1 / 2 2 / 3 3 / 4 4 / 5 5 / 6 6 / 7 7 / 8 8 / 9 9 / 1
£ million (2007/8)
NGC NGET
D Newbery ACCC 2011 16
Transmission investment is increasing rapidly
Transmission investment England and Wales 1978-2011
£0 £100 £200 £300 £400 £500 £600 £700 £800 £900 £1,000
7 8 / 7 9 7 9 / 8 8 / 8 1 8 1 / 8 2 8 2 / 8 3 8 3 / 8 4 8 4 / 8 5 8 5 / 8 6 8 6 / 8 7 8 7 / 8 8 8 8 / 8 9 8 9 / 9 9 / 9 1 9 1 / 9 2 9 2 / 9 3 9 3 / 9 4 9 4 / 9 5 9 5 / 9 6 9 6 / 9 7 9 7 / 9 8 9 8 / 9 9 9 9 / / 1 1 / 2 2 / 3 3 / 4 4 / 5 5 / 6 6 / 7 7 / 8 8 / 9 9 / 1
£ million (2007/8)
NGC NGET
Post -privatisation
D Newbery ACCC 2011 17
Capex, Allowances & Constraints
£0 £100 £200 £300 £400 £500 £600 £700 £800 £900 £1,000
90/91 91/92 92/93 93/94 94/95 95/96 96/97 97/98 98/99 99/00 00/01 01/02 02/03 03/04 04/05 05/06 06/07 07/08 08/09 09/10
Capex £m 07/08 £0 £50 £100 £150 £200 £250 £300 £350 £400 £450 £500 Constraints £m 07/08
Allowance TO Investment E&W Constraints GB constraints
GB transmission investment
D Newbery ACCC 2011 18
Capex, Allowances & Constraints
£0 £100 £200 £300 £400 £500 £600 £700 £800 £900 £1,000
90/91 91/92 92/93 93/94 94/95 95/96 96/97 97/98 98/99 99/00 00/01 01/02 02/03 03/04 04/05 05/06 06/07 07/08 08/09 09/10
Capex £m 07/08 £0 £50 £100 £150 £200 £250 £300 £350 £400 £450 £500 Constraints £m 07/08
Allowance TO Investment E&W Constraints GB constraints
Regulatory gaming or smarter investment? Investment runs ahead of regulation
- in pursuit of returns?
D Newbery ACCC 2011 19 Newbery IIB 1 19
Reforming regulation
- Reduce informational asymmetry
– standardized accounting no-brainer (free-ish lunch?) – allows benchmarking
- menu regulation => incentive compatible
efficiency revelation
– higher b for lower P0
- Most regulatory choices address power b
– longer periods, glide paths, marking up capex, …
is P0, X for PDV of planned I or future incentives?
D Newbery ACCC 2011 20 Newbery IIB 1 20
Ofgem’s RIIO
- Revenue=Incentives+Innovation+Outputs
- Intended to be more output-oriented
– Utility specifies outcomes – Remove capital bias -look at total operating budget – 8-year price control, longer depreciation periods (lowers initial cost, charge future customers more) – Contestable investment; customer engagement
- Competition for innovation trials - LCNF
D Newbery ACCC 2011 21 Newbery IIB 1 21
Contestable networks
- Aim – to deliver low-C at least cost
- Problem – grid proposes expensive solution
– Lengthy assessment, misaligned incentives
- Solution: invite proposals – choose best value
– Encourages customer engagement – Upgrades, relocate wind, different quality – Encourage local partners for planning applications – Bid on payment stream from regulated revenues
Risk: entrants overoptimistic on planning => greater delay
D Newbery ACCC 2011 22 Newbery IIB 1 22
Conclusions
- Regulation is inevitably inefficient: conflict between
efficiency and rent extraction
– least bad option if competition not possible
- but there are ways of making networks contestable
- and reducing informational asymmetries
- Main problems - predicting future:
– setting X; financing investment
- Regulatory reforms aim to remove distortions
– between capex and opex, over life of price control
but the change in incremental, not radical
23
D Newbery ACCC 2011 24
Planned and realised CEGB
- utput
*assuming 10% planning margin Electricity Council
ACS Demand (GW) (log scale)
1948/49 1958/59 1968/69 1978/79 1988/89 10 Out-turn (at ACS) Planning Forecast Available capacity*
Forecasts and outturns CEGB 1950-88
20 30 50 60
High demand for investment Investment demand falls dramatically
D Newbery ACCC 2011 25 Newbery IIB 1 25
Capital under-valuation
- CEGB 1947-90 earned 2.7% real
- GB water industry sold for £6bn, MEA>£100bn
- Railtrack sold for £2.5bn, WCML costs £10bn
- Eskom value = US$8.5 bn, HC = US$18.5 bn
inflation adjusted, ODV > US$47 bn
– Economic return < 2.3% on ODV
=> underpricing when investment falls
– difficult to fund investment without price rises
privatize and take asset write-down? if private, revisit regulation?
D Newbery ACCC 2011 26 Newbery IIB 1 26
Why undervalue assets?
- Writing down existing assets rapidly
– companies want fast depreciation (tax, cash-flow) – public sector bad at current cost accounting
- HC < ODV (unless rapid obsolescence)