inwood community meeting
play

INWOOD COMMUNITY MEETING PRESENTED BY: Rudy Garza Senior Vice - PowerPoint PPT Presentation

INWOOD COMMUNITY MEETING PRESENTED BY: Rudy Garza Senior Vice President Distribution Services & Operations 1/4/2018 Community Update AGENDA Outage History Remediation Plan Tree Trimming Map Points of Contact 2 OUTAGE


  1. INWOOD COMMUNITY MEETING PRESENTED BY: Rudy Garza Senior Vice President Distribution Services & Operations 1/4/2018 Community Update

  2. AGENDA • Outage History • Remediation Plan • Tree Trimming Map • Points of Contact 2

  3. OUTAGE HISTORY Duration Outage Date Cause Of Outage (Hours) 11/17/2016 21:52 0.1 Substation Lockout - Animal 2/19/2017 22:46 0.9 Thunderstorms - Tornadoes 2/22/2017 19:19 1.1 Failed Connection 4/11/2017 14:10 Momentary Cause Unknown 5/6/2017 1:27 0.1 Substation Lockout - Animal 5/23/2017 16:39 Momentary Cause Unknown Substation Lockout – Equipment Failure 5/29/2017 1:30 0.1 5/30/2017 15:37 0.4 Thunderstorms 8/26/2017 11:53 4.4 Thunderstorms - Trees (Tropical Storm Harvey High Wind) 9/27/2017 9:22 1.6 Vehicle Hit Pole 12/7/2017 19:31 7.1 Snow on Trees 12/19/2017 6:53 0.1 Cause Unknown 12/19/2017 8:04 2.0 Lightning Arrestor Failure 3

  4. OUTAGE CAUSES Lightning – damaged cross arm Trees touching lines Failed equipment Animals Car hit pole 4

  5. OUTAGE TIME SUMMARY Event Cause Duration (Hours) Weather - Trees 12.8 Equipment Failure 3.1 Vehicle 1.6 Substation Equipment 0.1 Substation Animal 0.2 17.8 5

  6. REMEDIATION PLAN • Proactive Response • Reactive Response • Completed full circuit • Installation of inspection September additional equipment 2017 – identified tree to minimize customer trimming impact. • Clearing trees • Using drone contacting overhead technology with power lines by end of infrared scan to February 2018 proactively assess • Install animal guards at equipment Substation by beginning of February 2018. 6

  7. TREE TRIMMING Completed Tree Trimming PHASE 3 PHASE 5 PHASE 2 PHASE 1 PHASE 4 Install Animal Guard 7

  8. POINTS OF CONTACT • Senior Executive Leadership • Rudy Garza – 210-353-3640 • Maria Garcia – 210-353-2368 • Engineering Executives • Ben Jordan- 210-353-4493 • CPS Energy Construction • Tony Alvarado 210-353-4128 • To Report Unplanned, Extended Outages • CPS Outage Line – 210-353- HELP (4357) 8

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.