INVESTIGATION REPORT RECOMMENDATION AND ACTIONS Nkosazana Leseka - - PowerPoint PPT Presentation

investigation report
SMART_READER_LITE
LIVE PREVIEW

INVESTIGATION REPORT RECOMMENDATION AND ACTIONS Nkosazana Leseka - - PowerPoint PPT Presentation

ESSELEN SUBSTATION DOLOMITE STABILITY INVESTIGATION REPORT RECOMMENDATION AND ACTIONS Nkosazana Leseka Pr.Sci.Nat Date: 15 May 2018 Content Background Summary of the Esselen Substation DSI report Recommendations and Actions


slide-1
SLIDE 1

ESSELEN SUBSTATION DOLOMITE STABILITY INVESTIGATION REPORT RECOMMENDATION AND ACTIONS

Nkosazana Leseka Pr.Sci.Nat

Date: 15 May 2018

slide-2
SLIDE 2

Content

  • Background
  • Summary of the Esselen Substation DSI report
  • Recommendations and Actions
slide-3
SLIDE 3

BACKGROUND LEADING TO DSI

  • Esselen Substation has long history of sinkhole manifestations
  • Record Keeping Strategies?
  • Efforts of rehabilitation
  • Successes and Failures
  • Emergence of new sinkholes, subsidence features, and tension cracks
  • Unknown extent of hazard associated with Dolomite Instability
  • Proactive measures to manage hazards
  • Zonation of site according to defined hazard class
  • A geoscience consultant was appointed conduct the DSI to address these problems
slide-4
SLIDE 4

WORK AREA

slide-5
SLIDE 5

OBJECTIVES OF DSI

  • Assess the exposure and vulnerability of the site to dolomite geo-hazards which have

historically manifest into sinkholes and surface subsidence.

  • Characterize the suitability of the site for any future development
  • Highlight any discrepancies noted on the site in aspects of geotechnical stability risk
  • Determination of the site specific geological conditions
  • Determination of all potentially restraining dolomite stability factors including the

hydrogeological characteristics and soils

  • Establish the presence and proximity of groundwater to the surface including historic

groundwater data

  • Classification of the site according to SANS 1936 in respect of dolomitic land
  • Provide recommendations for future utilization of the site, risk management solutions
slide-6
SLIDE 6

GEOLOGICAL LOCALITY OF ESKOM ESSELEN SUBSTATION

  • Malmani Subgroup of the Chuniespoort

Group Rocks:

  • Dolomite & Chert
  • Composition of dolomite rock:
  • Water + Carbon Dioxide = Carbonic

Acid i.e.

  • Typical Dissolusion Mechanism:
  • CaMg(CO3)2 + 2 H2CO3

Ca(HCO3)2 + Mg(HCO3)2

540A

slide-7
SLIDE 7

Historic Karst Instability

CURRENTLY EXISTING SINKHOLE

slide-8
SLIDE 8

REGIONAL HYDROGEOLOGY MONITORING STATION: A2N0631 1987 - 2017 MONITORING STATION: A2N0627 1987 - 2017

slide-9
SLIDE 9

SITE INVESTIGATIONS

  • Geophysical Surveys
  • Test Pits
  • Borehole Drilling
  • Rehabilitations
  • Borehole Logging
slide-10
SLIDE 10

Gravity Survey

SITE TOPOGRAPHY GRAVITY SURVEY RESULTS

slide-11
SLIDE 11

Resistivity Survey NE-SW DIRECTION SE-NW DIRECTION

slide-12
SLIDE 12

TEST PITING & BOREHOLE DRILLING

slide-13
SLIDE 13

BOREHOLE PROFILING – Two groups of geological profiles

  • Defined by the gravity high

zones and higher apparent resistivity signature.

  • Characterized by shallow

dolomite bedrock conditions which vary based on weathered zones of chert and iron

  • xides/ferruginous soils and

cavities..

  • Defined by gravity low zones

and low resistivity signature

  • The gravity low zones are

characterized by deeper dolomite bedrock overlain by small persistent cavities and soft clay, clayey silt overburden in upwards succession

slide-14
SLIDE 14

GEOTECHNICAL FINDINGS

  • Due to the variable depth to dolomite bedrock, the site is inferred to be

more prone to develop medium to large sinkholes respective to the borehole results. Medium sinkholes are sinkholes expected to have a nominal diameter of 2 – 5 m and large sinkhole expected to have 5 – 15 m diameter.

  • The blanketing material at the site may be summed up as ferrugenised

SILTY SAND, SILT and SOFT CLAY with fragments of highly weathered CHERT.

  • less than 1 minute per meter drilling rate drilled over the blanketing

material suggest moderate to highly permeable material susceptible to collapse/movements.

  • Thus instability triggered by water ingress from the surface is highly likely

in situations whereby surface water is not drained at sufficient rate.

slide-15
SLIDE 15

GEOTECHNICAL FINDINGS

  • Groundwater level is assessed to be below the cavity prone dolomite

horizons at the site (i.e. >24 from surface).

  • Drawdown of existing groundwater level would have non to little

impact on the stability of the dolomitic land as it is not within highly leached / weathered CHERT and DOLOMITE horizons characterized by cavities.

  • Precautionary measure to manage the usage/fluctuation of the

groundwater particularly focusing on possible rise and fall of the groundwater table that could increase the inherent hazard for ground movement.

slide-16
SLIDE 16

GEOTECHNICAL FINDINGS

  • The vast area on the western flank of the Eskom Esselen Substation

has been zoned of as a high risk area as a whole due to evident sinkhole formation within that area. The triggering mechanism for sinkhole formation is by assessment due to sudden loss of support accelerated by surface water ingress.

slide-17
SLIDE 17

DOLOMITE LAND CLASSIFICATION

  • The site falls under C3 type development
  • Portions of the site are thus regarded to be conditionally developable

under D3 + Footprint Investigation conditions as a C3 Development Type

  • All future developments at the site may only be permitted after

satisfaction of footprint investigations (FPI)

  • Submitted to the CGS for consent prior to any investigation
  • Certified site development plan should be submitted to the CGS for

co-signing

slide-18
SLIDE 18

Recommendations and Actions

  • Re-route the high risk fence, non lethal fence and inner fence as a

proposal

  • Drainage (Concrete Line open drainage especially on the western

flank of the station) + Contouring of the entire site to achieve a general slope

  • fall of least 1:40 in general and to 1:15 away from structures within a

distance of 8 m of a structure is required

  • Once the fence is moved, we may rehabilitate the existing sinkhole, if

it impacts the risk within the fence (which will be outside the station parameter fence)

  • Put up a ground water monitoring station within the substation as per

the recommendation

slide-19
SLIDE 19

Recommendations and Actions (continuum)…

  • Contact Ekurhuleni Municipality for the risk management plan
  • Do a site specific Dolomite Risk Management Plan in accordance to

SANS 1936 – 4:2012

  • Involve all stakeholders to be part of the workgroup
  • Have an awareness campaign to inform all stakeholders especially safety

and environment as part of the safety talk

  • If any construction takes place, make the responsible person aware of

the risk (through the DRMP) to pro-actively apply sound water management system or procedure

  • It must form part of the Inspection Test Plan (ITP) of which there must be

hold points for inspection.

slide-20
SLIDE 20

Thank you

Nkosazana Leseka Pr.Sci.Nat Email: lesekana@eskom.co.za