SLIDE 1 Introduction to Asset Management
Gordon Sparks, Ph.D.
Professor Emeritus, Civil Engineering University of Saskatchewan Technical Advisor, AM-SK
SLIDE 2
What is Asset Management?
SLIDE 3 Infrastructure Asset Management :
- Is Asset Management focusing
- n infrastructure, rather than financial assets.
- Asset Class for todays discussion - Bridges
SLIDE 4 Infrastructure Asset Management is: The planning related to determining what
is required in terms of activities and costs to:
Create Operate Maintain Renew, and Dispose,
Of a infrastructure asset so it provides the Desired Level of Service.
SLIDE 5
A Lifecycle Forecast for Infrastructure Assets includes activities & Costs related to: – Create – Operate – Maintain – Renew – Dispose
SLIDE 6 An Asset Management Plan:
“Documents” Life Cycle Activities & Costs required
so they provide the “Desired Level of Service”
SLIDE 7 The Asset Management Plan:
- Provides the “Information” required for:
- “Informed Discussions”
- Which leads to:
- “Informed Decisions”
SLIDE 8
Asset Management Plans Link to other Planning Activities
SLIDE 9 Asset Management Plan
Version 1.0 November 2018
Example
SLIDE 10
Table of Contents
1.1 The Purpose of the Plan 1.2 Asset Description 1.3 Levels of Service 1.4 Future Demand 1.5 Lifecycle Management Plan 1.6 Financial Summary
SLIDE 11
Pulling It Altogether Output of an Asset Management Plan
SLIDE 12
SLIDE 13 What We Cannot Do!
- The Long Term Financial Plan will also identify what
infrastructure / services we do not currently have enough funding to sustain at the desired standard going forward
SLIDE 14 Managing the Risks
Are present funding levels sufficient to continue to manage risks in the medium term? The main risks and consequences are for example:
- extreme weather events
- flooding
- ???
SLIDE 15
SLIDE 16 1.7 Asset Management Systems
are a combination of:
- Information / Technology / Software
- Financial Accounting
- Asset Register
- Analysis
- Life Cycle Costing
- Teams
- Administration
- Finance
- Public Works
- Political Leaders
SLIDE 17 Monitoring and Improvement Program
- Formally develop and implement a Continuous
Improvement Plan for Asset Management.
- Review and update the asset useful lives and current
replacement costs in the Asset Register.
- Develop a Plan for Capital Renewals and Upgrades.
- Review Risks and Develop a Risk Management Plan.
- Develop Customer and Technical Levels of Service.
SLIDE 18 Topic of Today’s Discussion:
- Developing Asset Management Plans
for Rural Bridges
SLIDE 19 Challenge:
1468 Rural Bridges Predominately Treated Timber structures 85.6% Timber (1256) 7.8% concrete (114) 6.6% Steel/concrete (98) Useful Service Life Highly Variable Assume - 50 to 60 years
SLIDE 20
SLIDE 21
SLIDE 22
SLIDE 23
SLIDE 24
SLIDE 25
SLIDE 26
Rural Bridges - Saskatchewan
SLIDE 27
Roads Class 5 and Better – Bridges Restricted
SLIDE 28
Roads Class 5 and Better – Bridges Poor
SLIDE 29
Roads Class 5 and Better – Bridges Fair
SLIDE 30
Roads Class 5 and Better – Bridges Good
SLIDE 31
Road Classes 6 & 7 – Bridges Fair, Poor, Restricted
SLIDE 32 So Major Challenge:
- the “Sustainability” of the Rural Bridges!
So “what” Could & Should be Done!
- Clear need for an
- Asset Management Plan for Rural Bridges
SLIDE 33 50 100 150 200 250 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 75+
Rural Bridges Number by Age
50 Years + 771 Bridges 52% Age - Years 1468 Bridges in Total
SLIDE 34 50 100 150 200 250 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 75+
Rural Bridges Number by Age
60 Years + 488 Bridges 33% Age – Years
SLIDE 35 50 100 150 200 250 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 75+
Rural Bridges Number by Age
70 Years + 145 Bridges 10% Age - Years
SLIDE 36 Cost to Replace a Rural Bridge
Range from $300,000 - $1,300,000 Assuming average $600K 145 bridges 70+ years - $87 million to replace 488 bridges 60+ years - $292 million to replace 771 bridges 50+ years - $421 million to replace
Current Rate of Bridge Replacement
- in the order of 5 bridges/yr.
- 5 x $600,000 = $3 million/yr.
SLIDE 37
- Conclusion:
- Rural Bridges are not “sustainable” at
current funding level of $3 million/yr.
SLIDE 38 Options:
- Access more funding to sustain All Bridges
- All Road Classes
- 488 bridges 60+ yrs
replaced over 10 yrs = 50 Bridges/yr.
- 50 x $600,000 Bridge = $30 million/yr.
SLIDE 39 Minimal Option: Priority/Focus on Timber Bridges on Class 5+ Roads Restrict & Close Bridges on Class 6 &7 Roads as
required with time.
“Minimal Option” – not acceptable – but order of
magnitude of absolute minimum funding required “Going Forward”.
SLIDE 40 Class 5+ - 339 Treated Timber Bridges
130 Bridges built 1962 – 1971 therefore 47 to 56
Assuming 130 Bridges replaced over next 10
years = 13 Bridges /yr.
Average Cost/ Bridge on Class 5+ =
$800,000/bridge
13 Bridges/yr. x $800,000 = $10.4 million/yr. $10.4 million/yr. – Minimal Option
SLIDE 41 Summary
- Current Funding for Rural Bridge - 5 bridges/ yr.
$3 million/ yr.
- replacement rate – Bridges unsustainable!
- Funding Level Required to Sustain All Bridges on all Class of
Roads
- 50 Bridges/yr.
- $30 million/yr
- Minimal Funding – Sustain only Bridges on Class 5+ Roads
- 13 Bridges per yr.
- $10.4 million/yr.
SLIDE 42 What Is Required?
Develop “Credible” Asset Management Plan for all
Bridges.
Address the question: Are there bridges that are “no longer” needed
going forward?
Are there bridges that the “costs” for the
service provided can not be justified?
SLIDE 43 Another Issue:
How is “Inter – Generational Equity” going to be
addressed?
Those using the bridges over the next 50 years should
each pay their share.
Folks today should not have to bear the financial
burden of the cost of replacing a bridge that will serve folks for the next 50+ years.
Option – Finance the Bridge over Time Going Forward
SLIDE 44 Cost to Replace a Bridge – Annualized
- $600,000 at 4% over 50 years
- Annual Cost (A/P
,I,N) = $600,000 x (A/$600,000, 4%, 50yrs) = $600,000 x .04655 = $27,930/yr
SLIDE 45 $600,000 at 3% 0ver 50 years = $600,000 x .03887 = $23,322/yr
- $600,000 at 2% over 50 years
= $600,000 x .03182 = $19,092/yr
SLIDE 46 Summary
The Capital Costs of $600,000 for a Bridge Translates into in the order of $24,000/yr. $2000/month/bridge! Capital Costs only
SLIDE 47
Costs in the order $2000/month per Bridge = $2000/month / 30 days/month = $67/day Average Daily Traffic = 10 vehicles =$6.70/vehicle
SLIDE 48
Vehicles/day (ADT) Cost/vehicle/crossing 10 = $6.70/vehicle 20 = $3.35/vehicle 40 = $1.67/vehicle 50 = $1.34/vehicle 100 = $.67/vehicle
SLIDE 49 So Major Challenge:
- regarding the “Sustainability” of the Rural Bridges!
So “what” Could & Should be Done!
SLIDE 50 1) Need for a “Transportation Network Plan”
to determine:
- Which Bridges are “Required” Going Forward?
- Which Bridges can be “decommissioned”?
- Economic considerations
- Social considerations
2) Asset Management Plans for all Bridges
SLIDE 51
Example: Transporation Network Plan
SLIDE 52
SLIDE 53 2 Mile Detour 2 Cars x 2 miles x $.60/mile = $2.40/day 1 Truck/day x 2 miles x $1/mile = $2.00/day Total $4.40/day x 365 days/yr = $1606/year $150,000 to replace bridge – 75 yr Life = $2000/yr at 0% 2 Cars 1 Truck / Day
SLIDE 54
2) Asset Management Plans for All Bridges
SLIDE 55
Life Cycle Costs
SLIDE 56
Foundation of Asset Management Plans:
Asset Registers
An inventory of infrastructure assets
SLIDE 57 Asset Register: Excel Spreadsheet
Year Constructed Useful Life Replacement Cost
SLIDE 58
Output: Asset Management Plan
SLIDE 59
SLIDE 60
SLIDE 61
SLIDE 62
SLIDE 63 An Asset Management Plan:
“Documents” the information / data related to
infrastructure assets, and thus supports:
“Informed Discussions”, and “Informed Decisions”
SLIDE 64 Next Steps: Developing AMP For Bridges
Build on Existing Bridge Inspection Program Inspection Program – Assesses “Condition” of Bridges ever 3 years Add development of Feasible “Maintenance, Repair, Rehabilitation,
Replace, Decommission, Alternatives for each Bridge.
Add “Life Cycle Costing Analysis” of M &R etc. Alternatives for each
Bridge and select a “Costs/Effective” M & R etc. Strategy for each Bridge – document in Asset Management Plans for each Bridge.
Integrate individual AMP’s for each Bridge together into a “Bridge
Network Management Plan & Long Term Financial Plan”.
SLIDE 65 1) Transportation Network Plan 2) Asset Management Plans for each Bridge. 3) Bridge Network Management Plan & Long Term Finance Plan Will Support:
“Informed Discussions”, and “Informed Decisions”
Maximize “Back for the Buck”!
SLIDE 66 Topics for Further Discussion:
“Innovation” in Bridge Replacement
Large Diameter Culverts Modular Bridges Prefabricated Fiberglass Composites Etc.
SLIDE 67
Concept Design: Culvert Bridge
SLIDE 68
SLIDE 69
Questions?