Introduction to Asset Management Gordon Sparks, Ph.D. Professor - - PowerPoint PPT Presentation

introduction to asset management
SMART_READER_LITE
LIVE PREVIEW

Introduction to Asset Management Gordon Sparks, Ph.D. Professor - - PowerPoint PPT Presentation

Introduction to Asset Management Gordon Sparks, Ph.D. Professor Emeritus, Civil Engineering University of Saskatchewan Technical Advisor, AM-SK What is Asset Management? Infrastructure Asset Management : - Is Asset Management focusing on


slide-1
SLIDE 1

Introduction to Asset Management

Gordon Sparks, Ph.D.

Professor Emeritus, Civil Engineering University of Saskatchewan Technical Advisor, AM-SK

slide-2
SLIDE 2

What is Asset Management?

slide-3
SLIDE 3

Infrastructure Asset Management :

  • Is Asset Management focusing
  • n infrastructure, rather than financial assets.
  • Asset Class for todays discussion - Bridges
slide-4
SLIDE 4

 Infrastructure Asset Management is: The planning related to determining what

is required in terms of activities and costs to:

Create Operate Maintain Renew, and Dispose,

Of a infrastructure asset so it provides the Desired Level of Service.

slide-5
SLIDE 5

A Lifecycle Forecast for Infrastructure Assets includes activities & Costs related to: – Create – Operate – Maintain – Renew – Dispose

slide-6
SLIDE 6

An Asset Management Plan:

 “Documents”  Life Cycle Activities & Costs required

so they provide the “Desired Level of Service”

slide-7
SLIDE 7

The Asset Management Plan:

  • Provides the “Information” required for:
  • “Informed Discussions”
  • Which leads to:
  • “Informed Decisions”
slide-8
SLIDE 8

Asset Management Plans Link to other Planning Activities

slide-9
SLIDE 9

Asset Management Plan

Version 1.0 November 2018

Example

slide-10
SLIDE 10

Table of Contents

1.1 The Purpose of the Plan 1.2 Asset Description 1.3 Levels of Service 1.4 Future Demand 1.5 Lifecycle Management Plan 1.6 Financial Summary

slide-11
SLIDE 11

Pulling It Altogether Output of an Asset Management Plan

slide-12
SLIDE 12
slide-13
SLIDE 13

What We Cannot Do!

  • The Long Term Financial Plan will also identify what

infrastructure / services we do not currently have enough funding to sustain at the desired standard going forward

slide-14
SLIDE 14

Managing the Risks

Are present funding levels sufficient to continue to manage risks in the medium term? The main risks and consequences are for example:

  • extreme weather events
  • flooding
  • ???
slide-15
SLIDE 15
slide-16
SLIDE 16

1.7 Asset Management Systems

are a combination of:

  • Information / Technology / Software
  • Financial Accounting
  • Asset Register
  • Analysis
  • Life Cycle Costing
  • Teams
  • Administration
  • Finance
  • Public Works
  • Political Leaders
slide-17
SLIDE 17

Monitoring and Improvement Program

  • Formally develop and implement a Continuous

Improvement Plan for Asset Management.

  • Review and update the asset useful lives and current

replacement costs in the Asset Register.

  • Develop a Plan for Capital Renewals and Upgrades.
  • Review Risks and Develop a Risk Management Plan.
  • Develop Customer and Technical Levels of Service.
slide-18
SLIDE 18

Topic of Today’s Discussion:

  • Developing Asset Management Plans

for Rural Bridges

slide-19
SLIDE 19

Challenge:

 1468 Rural Bridges  Predominately Treated Timber structures 85.6% Timber (1256) 7.8% concrete (114) 6.6% Steel/concrete (98)  Useful Service Life Highly Variable Assume - 50 to 60 years

slide-20
SLIDE 20
slide-21
SLIDE 21
slide-22
SLIDE 22
slide-23
SLIDE 23
slide-24
SLIDE 24
slide-25
SLIDE 25
slide-26
SLIDE 26

Rural Bridges - Saskatchewan

slide-27
SLIDE 27

Roads Class 5 and Better – Bridges Restricted

slide-28
SLIDE 28

Roads Class 5 and Better – Bridges Poor

slide-29
SLIDE 29

Roads Class 5 and Better – Bridges Fair

slide-30
SLIDE 30

Roads Class 5 and Better – Bridges Good

slide-31
SLIDE 31

Road Classes 6 & 7 – Bridges Fair, Poor, Restricted

slide-32
SLIDE 32

So Major Challenge:

  • the “Sustainability” of the Rural Bridges!

So “what” Could & Should be Done!

  • Clear need for an
  • Asset Management Plan for Rural Bridges
slide-33
SLIDE 33

50 100 150 200 250 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 75+

Rural Bridges Number by Age

50 Years + 771 Bridges 52% Age - Years 1468 Bridges in Total

slide-34
SLIDE 34

50 100 150 200 250 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 75+

Rural Bridges Number by Age

60 Years + 488 Bridges 33% Age – Years

slide-35
SLIDE 35

50 100 150 200 250 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 75+

Rural Bridges Number by Age

70 Years + 145 Bridges 10% Age - Years

slide-36
SLIDE 36

Cost to Replace a Rural Bridge

 Range from $300,000 - $1,300,000  Assuming average $600K  145 bridges 70+ years - $87 million to replace  488 bridges 60+ years - $292 million to replace  771 bridges 50+ years - $421 million to replace

Current Rate of Bridge Replacement

  • in the order of 5 bridges/yr.
  • 5 x $600,000 = $3 million/yr.
slide-37
SLIDE 37
  • Conclusion:
  • Rural Bridges are not “sustainable” at

current funding level of $3 million/yr.

slide-38
SLIDE 38

Options:

  • Access more funding to sustain All Bridges
  • All Road Classes
  • 488 bridges 60+ yrs

replaced over 10 yrs = 50 Bridges/yr.

  • 50 x $600,000 Bridge = $30 million/yr.
slide-39
SLIDE 39

 Minimal Option: Priority/Focus on Timber Bridges on Class 5+ Roads Restrict & Close Bridges on Class 6 &7 Roads as

required with time.

“Minimal Option” – not acceptable – but order of

magnitude of absolute minimum funding required “Going Forward”.

slide-40
SLIDE 40

Class 5+ - 339 Treated Timber Bridges

130 Bridges built 1962 – 1971 therefore 47 to 56

  • yrs. old

Assuming 130 Bridges replaced over next 10

years = 13 Bridges /yr.

Average Cost/ Bridge on Class 5+ =

$800,000/bridge

13 Bridges/yr. x $800,000 = $10.4 million/yr. $10.4 million/yr. – Minimal Option

slide-41
SLIDE 41

 Summary

  • Current Funding for Rural Bridge - 5 bridges/ yr.

$3 million/ yr.

  • replacement rate – Bridges unsustainable!
  • Funding Level Required to Sustain All Bridges on all Class of

Roads

  • 50 Bridges/yr.
  • $30 million/yr
  • Minimal Funding – Sustain only Bridges on Class 5+ Roads
  • 13 Bridges per yr.
  • $10.4 million/yr.
slide-42
SLIDE 42

What Is Required?

 Develop “Credible” Asset Management Plan for all

Bridges.

 Address the question: Are there bridges that are “no longer” needed

going forward?

Are there bridges that the “costs” for the

service provided can not be justified?

slide-43
SLIDE 43

Another Issue:

 How is “Inter – Generational Equity” going to be

addressed?

Those using the bridges over the next 50 years should

each pay their share.

Folks today should not have to bear the financial

burden of the cost of replacing a bridge that will serve folks for the next 50+ years.

Option – Finance the Bridge over Time Going Forward

slide-44
SLIDE 44

Cost to Replace a Bridge – Annualized

  • $600,000 at 4% over 50 years
  • Annual Cost (A/P

,I,N) = $600,000 x (A/$600,000, 4%, 50yrs) = $600,000 x .04655 = $27,930/yr

slide-45
SLIDE 45

$600,000 at 3% 0ver 50 years = $600,000 x .03887 = $23,322/yr

  • $600,000 at 2% over 50 years

= $600,000 x .03182 = $19,092/yr

slide-46
SLIDE 46

Summary

The Capital Costs of $600,000 for a Bridge  Translates into in the order of $24,000/yr. $2000/month/bridge! Capital Costs only

slide-47
SLIDE 47

Costs in the order $2000/month per Bridge = $2000/month / 30 days/month = $67/day Average Daily Traffic = 10 vehicles =$6.70/vehicle

slide-48
SLIDE 48

Vehicles/day (ADT) Cost/vehicle/crossing 10 = $6.70/vehicle 20 = $3.35/vehicle 40 = $1.67/vehicle 50 = $1.34/vehicle 100 = $.67/vehicle

slide-49
SLIDE 49

So Major Challenge:

  • regarding the “Sustainability” of the Rural Bridges!

So “what” Could & Should be Done!

slide-50
SLIDE 50

1) Need for a “Transportation Network Plan”

to determine:

  • Which Bridges are “Required” Going Forward?
  • Which Bridges can be “decommissioned”?
  • Economic considerations
  • Social considerations

2) Asset Management Plans for all Bridges

slide-51
SLIDE 51

Example: Transporation Network Plan

slide-52
SLIDE 52
slide-53
SLIDE 53

2 Mile Detour 2 Cars x 2 miles x $.60/mile = $2.40/day 1 Truck/day x 2 miles x $1/mile = $2.00/day Total $4.40/day x 365 days/yr = $1606/year $150,000 to replace bridge – 75 yr Life = $2000/yr at 0% 2 Cars 1 Truck / Day

slide-54
SLIDE 54

2) Asset Management Plans for All Bridges

slide-55
SLIDE 55

Life Cycle Costs

slide-56
SLIDE 56

Foundation of Asset Management Plans:

Asset Registers

An inventory of infrastructure assets

slide-57
SLIDE 57

Asset Register: Excel Spreadsheet

Year Constructed Useful Life Replacement Cost

slide-58
SLIDE 58

Output: Asset Management Plan

slide-59
SLIDE 59
slide-60
SLIDE 60
slide-61
SLIDE 61
slide-62
SLIDE 62
slide-63
SLIDE 63

An Asset Management Plan:

 “Documents” the information / data related to

infrastructure assets, and thus supports:

“Informed Discussions”, and “Informed Decisions”

slide-64
SLIDE 64

Next Steps: Developing AMP For Bridges

 Build on Existing Bridge Inspection Program  Inspection Program – Assesses “Condition” of Bridges ever 3 years  Add development of Feasible “Maintenance, Repair, Rehabilitation,

Replace, Decommission, Alternatives for each Bridge.

 Add “Life Cycle Costing Analysis” of M &R etc. Alternatives for each

Bridge and select a “Costs/Effective” M & R etc. Strategy for each Bridge – document in Asset Management Plans for each Bridge.

 Integrate individual AMP’s for each Bridge together into a “Bridge

Network Management Plan & Long Term Financial Plan”.

slide-65
SLIDE 65

1) Transportation Network Plan 2) Asset Management Plans for each Bridge. 3) Bridge Network Management Plan & Long Term Finance Plan Will Support:

“Informed Discussions”, and “Informed Decisions”

Maximize “Back for the Buck”!

slide-66
SLIDE 66

Topics for Further Discussion:

“Innovation” in Bridge Replacement

Large Diameter Culverts Modular Bridges Prefabricated Fiberglass Composites Etc.

slide-67
SLIDE 67

Concept Design: Culvert Bridge

slide-68
SLIDE 68
slide-69
SLIDE 69

Questions?