inter ercon onnec ection on o of e electricity n networks
play

Inter ercon onnec ection on o of e electricity n networks b - PowerPoint PPT Presentation

Inter ercon onnec ection on o of e electricity n networks b between een regions a and c continents ts TGEG19 27 June 2019 Ioannis Margaris Chief Technology, System Planning and Strategy of Officer ADMIE (IPTO) General


  1. Inter ercon onnec ection on o of e electricity n networks b between een regions a and c continents ts TGEG’19 27 June 2019 Ioannis Margaris Chief Technology, System Planning and Strategy of Officer ADMIE (IPTO) General Manager Ariadne Interconnection Vice-Chairman BoD ADMIE (IPTO)

  2. ADMIE Major Projects Major Project Locations ID Project description Expected commissioning year 5 First 400 kV branch to Peloponnese (OHL 2019 1 Megalopoli – Patras – Acheloos) Skiathos island interconnection 2021 2 400 kV 150 kV Crete interconnection (Phase I) 2020 DC 3 Second 400 kV branch to Peloponnese (OHL 2024 4 Megalopoli – Korinthos – Koumoundouros) 2 New 400 kV interconnector to Bulgaria 5 2023 N. Santa (GR) – Maritsa (BG) 1 4 2024 Cycladic Islands interconnection (Phases B’, 6 (2019 for Phase B’, 2020 for C’ and D’) Phace C’ and 2024 for Phase D’) 6 8 7 Crete interconnection (Phase II) 2022 7 3 8 Dodecanese Interconnection 2027 Source: TYNDP 2020 – 2029 (under public consultation)

  3. Cycladic Islands Interconnection Phase B’ Lavrio Tinos Mykonos Syros Technical Characteristics  Paros – Naxos: Naxos Paros AC XLPE cable, 150 kV, 140 MVA, 7.6 km  Naxos – Mykonos: AC XLPE cable, 150 kV, 140 MVA, 40 km  Livadi – Andros (Upgrade): AC XLPE cable, 150 kV, 200 MVA, 14.5 km  Tinos – Livadi (Upgrade): AC XLPE cable, 150 kV, 200 MVA, 4 km  1 GIS Substation at Naxos

  4. Cycladic Islands Interconnection Phase C’ Lavrio Tinos Mykonos Syros Technical Characteristics Naxos Paros  Lavrio – Syros (2 nd cable)  Voltage: 150 kV  Capacity: 200 MVA  Cable technology: XLPE  Maximum depth: ̴ 300 m  Cable length: 108 km

  5. Cycladic Islands Interconnections Phase D’ Project Identity o Budget: 390 MEuros o Start by: 2021 o Completion by: 2024 Lavrio Tinos Technical Characteristics . Mykonos AC XLPE cables 150 kV, 200 MVA, Syros total length ̴ 340 km Serifos  Naxos – Thira or Paros – Thira Naxos Paros  Thira – Folegandros  Folegandros – Milos  Milos – Serifos  Serifos – Lavrio Folegandros Milos 4 GIS Substations Thira  Thira  Folegandros  Milos  Serifos

  6. Crete Interconnection – Phase I Project Identity The longest AC underground-submarine interconnection includes the upgrade of the Peloponnese transmission o Contracts signed: November 2018 system o Participants: CABLEL, FULGOR, NEXANS, TERNA ENERGY o Budget: : ̴ 330 Million Euros o Completion by: mid 2020 Technical Characteristics  Voltage: 150 kV AC  2 GIS Substations  Capacity: 2 x 200 MVA  Cable technology: XLPE  Maximum depth: ̴ 980 m  Cable length: 2 x 135 km

  7. Crete Interconnection – Phase II (IPTO / Ariadne Interconnection) Project Identity o Tender expected: 2019, Q2 o Budget: <1 Billion Euros Technical Characteristics o Completion by: 2022, Q3  VSC MMC Converters  Voltage: ̴ 500kV  Bipolar Configuration  Link Capacity: 2 x 500 MW  Maximum depth: ̴ 1250m  Cable length: 2 x 330 km Similar Projects in Europe SAPEI : Sardinia-Italy, 1000 MW, 500 kV, LCC, depth 1650 m, 420 km long MONITA : Italy-Montenegro, 1000 MW, 500 kV, LCC, depth 1200 m, 415 km long SKAGERRAK IV : Denmark-Norway, 700 MW, 500 kV, VSC, depth 550 m, 137 km long NORD.LINK : Germany-Norway, 1400 MW, 525 kV, VSC, depth 230 m, 623 km long NSL : UK-Norway, 1400 MW, 525 kV, VSC, depth 600 m, 730 km long

  8. Dodecanese & North Aegean Interconnection – 1 st Scenario (1) Project Identity o In TYNDP 2020-2029 Korinthos - Kos  o Under consultation 2x450 MW, 2x380 km  o Budget: 1.5 Billion Euros o Completion by: 2027 Technical Characteristics  Korinthos – Kos: Bipolar HVDC cable, 2x450 MW,  Kos – Rodos: 3 AC cables, 150 kV, 200 MVA.  Rodos – Karpathos: 1 AC cable, 150 kV, 200 MVA.  2 GIS Substations at Karpathos, Rodos.

  9. Dodecanese & North Aegean Interconnection – 1 st Scenario (2) Technical Characteristics  Continental System – Limnos: AC cables, 150 kV, 2x200 MVA.  Limnos – Lesvos: AC Cable, 150 kV, 2x200 MVA.  Lesvos – Chios: AC cable, 150 kV, 1x200 MVA.  Chios – Samos: AC cable, 150 kV, 1x200 MVA.  Samos – Kos: AC cable, 150 kV, 1x200 MVA. Requires the HVDC link to Dodecanese

  10. Dodecanese & North Aegean Interconnection – 2 nd Scenario Technical Characteristics  Double HVAC link at 220 kV Limnos – Lesvos – Chios – Samos – Kos (2x380 MVA)  New GIS 220 kV S/S at these islands  Coupling 220/150 kV at Kos  Double HVAC link at 150 Kos – Rodos (2x200 MVA)  Connection to Crete through Karpathos island (1x200 MVA)  Lesvos – Skyros – Aliveri connection (1x380 MVA)  STATCOM at Lesvos, Kos and Rodos

  11. SuperGrid in the Mediterranean

  12. Actors-Factors-Sectors • Technology challenges: deep sea, long lengths, infrastructure requirements in the continental parts • Market challenges: reliable assessment of interconnections’ impact in a changing electricity and energy market environment • Geopolitical risks: transmission infrastructure requires long-term financial-political-social stability • TSOs-ENTSO-E: leadership role in the future development of interconnections’ infrastructure • Internal – International – Intercontinental: steps and enablers

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend